05000285/FIN-2014002-07
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Inadequate 10 CFR 50.59 Screening for Containment Spray Design Change |
Description | A cited violation of 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, was identified involving the failure to take timely corrective action for a condition adverse to quality. Specifically, the licensee failed to restore compliance following NRC identification of the licensees failure to correct a runout condition of the containment spray system (CS) documented in NCV 05000285/2008003-05, in August 2008. Licensee corrective actions to correct the issue included completion of an analysis of containment spray pump operation during the main steam line break (MSLB) event; revision of CS design documentation; analysis of motor performance by an electrical vendor; and completion of a temporary modification to throttle the CS pump discharge valves to provide additional system resistance preventing pump runout. Future corrective actions include a permanent design change to prevent CS pump runout. The licensee initiated CR 2014-02242 on February 19, 2014, to document this failure to restore compliance. This finding was more than minor because it adversely impacted the Barrier Integrity cornerstone objective to provide reasonable assurance that physical design barriers (containment) protect the public from radionuclide releases caused by accidents or events. The inspectors reviewed NRC IMC 0609, Attachment 4, Initial Characterization of Findings , Table 3 SDP Appendix Router. While this issue was identified during a refueling outage, the inspectors determined that the majority of the exposure time for this violation occurred with the reactor at power and should be evaluated using the Significance Determination Process in accordance with IMC 0609, The Significance Determination Process (SDP) for Findings at- Power, Appendix A, Exhibit 3, Barrier Integrity Screening Questions. The inspectors determined that the finding did not represent an actual open pathway in containment or containment isolation logic, nor did the finding represent an actual reduction in the function of containment hydrogen igniters. Based on the guidance in the Exhibit 3 checklist the inspectors determined that the finding was of very low safety significance. The inspectors determined that the finding had a cross-cutting aspect of avoiding complacency in the human performance area, because the licensees staff failed to recognize latent issues even while expecting successful outcomes. |
Site: | Fort Calhoun |
---|---|
Report | IR 05000285/2014002 Section 4OA3 |
Date counted | Mar 31, 2014 (2014Q1) |
Type: | NCV: Green |
cornerstone | Barrier Integrity |
Identified by: | NRC identified |
Inspection Procedure: | IP 71153 |
Inspectors (proximate) | A Guzzetta A Sallman J Kirkland J Wingebach M Chambers M Farnan M Hay N Taylor W Lyon W Smith |
Violation of: | 10 CFR 50 Appendix B Criterion XVI |
INPO aspect | |
' | |
Finding - Fort Calhoun - IR 05000285/2014002 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Fort Calhoun) @ 2014Q1
Self-Identified List (Fort Calhoun)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||