05000266/LER-2002-002

From kanterella
Jump to navigation Jump to search
LER-2002-002,
Docket Number
Event date: 09-25-2002
Report date: 11-22-2002
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
2662002002R00 - NRC Website

Event Description:

On September 25, 2002 during the performance of a plant modification (MR 00-003), NMC personnel discovered that a Point Beach Nuclear Plant (PBNP) Unit 1 A-Train reactor protection {JC} cable {CBL1} was routed in B-Train cable trays {TY}. At the time of discovery, PBNP Unit 1 was in Mode 6 for its 27th refueling outage. Modification MR 00-003 was being performed to correct previously identified reactor protection cable train separation concerns In the conduits {CND} and cable trays above engineered safety features (ESF) {JE} cabinets {CAB} 1C157 and 1C167. These cabinets and trays are located in the cable spreading room {NA}. While pulling cables out of 1C157, to reroute reactor protection (RP) cable ZB1NB105A, a B-Train cable, cable ZA1NA105A, an A-train cable, was found in the same conduit (DM-1). This is a Train B conduit. Cables ZB1NB105A and ZA1NA105A are part of the unique four-cable scheme associated with a safety injection (SI) signal. Actuation of one train of ESF will cause a reactor trip signal on both trains. The complete scheme is shown below. Cable ZA1NA105A was designed to be routed between A-train cabinets in A-Train cable trays. However, finding that cable in conduit DM-1 indicates that it is routed in B-train cable trays, which is not in accordance with PNBP design requirements.

A-Train ESF � B-Train ESF 1C157 1C167 ZA1NA105A � ZB1NB106A 1C163 � 1C164 A-Train RP B-Train RP ZA1NA106A 1C153 1C154 Upon discovery of this routing discrepancy, a Corrective Action Program activity request was initiated (CAP 29532) to document the condition. The A-Train SI signal to the reactor protection system was declared inoperable due to improper cable separation. This condition affects Item 16 of Technical Specification Table 3.3.1, "Safety Injection Input from Engineered Safety Features Actuation System." That item is applicable only in Modes 1 and 2 and requires 2 trains to be operable. If a train is inoperable for greater than 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br />, the reactor is required to be in Mode 3. PBNP Unit 1 was in Mode 6 at the time of this discovery; therefore, the action condition for this item was not applicable at the time of discovery. However, PBNP Unit 1 had operated in Modes 1 and 2 in the past with this existing train separation discrepancy. Therefore, in accordance with the requirements of 10 CFR 50.73(a)(2)(i)(B), PBNP Unit 1 had operated in a condition which was prohibited by the plant's Technical Specifications. As clarified in NUREG 1022, this LER is required even if the condition was not discovered until after the allowable time had elapsed and the condition was rectified immediately upon discovery.

FACILITY NAME (1) PAGE (3) DOCKET NUMBER (2) LER NUMBER (6 Point Beach Nuclear Plant Unit 1 05000266 FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6 PAGE (3) Paint Beach Nuclear Plant Unit 1 05000266

Cause:

Both the plant's Cable and Raceway Data System (CARDS) and the original Architect Engineer cable data sheets were reviewed for cable ZA1NA105A. Cable ZA1NA105A was listed as having the same routing as cable ZA1NA106A.

Cables ZA1NA105A and ZA1NA106A cannot have the same routing since cable ZA1NA105A is routed to 1C157 and cable ZA1NA106A is routed to 1C167. This discrepancy had been noted in a 1998 condition report (CR 98-39441 CAP020254). The conclusion drawn in the resolution of that condition report was that the ZA1NA105A cable must be routed in A-train cable trays to 1C157 since the cable is physically located in the cabinet. However, the other end of the cable was not verified to check which cable tray/conduit cable ZA1NA105A was routed in when it left cabinet 1C153.

Based on a review of plant modification and work order history, the routing of cable ZA1NA105A had not previously been modified from original construction. Therefore we have concluded the apparent cause of this discrepancy results from an original construction installation error.

Corrective Actions:

An extent of condition assessment has been completed. As described in the "Component and System Description" below, the four cables in this SI to reactor trip scheme are unique to the plant. The other two Unit 1 cables associated with this unique cable scheme have been visually verified as being routed correctly or were being rerouted in accordance with the plant modification. PBNP Unit 2 also has the same four-cable scheme. The cables from this scheme (ZC2NA105A, ZC2NA106A, ZD2NB105A and ZD2NB106A) were checked and verified to be appropriately routed following the completion of a separate modification (MR 00-004) during the Unit 2 2002 refueling outage.

An engineering change request (ECR) to MR 00-003 was initiated to correct the separation violation documented in this report. The ECR abandoned the existing cable and relabeled it as ABN0006. A new cable ZA1NA105A has been installed in dedicated A-train cable trays between 1C153 and 1C157.

Component and System Description:

The engineered safety features actuation system detects plant conditions that require automatic ESF equipment operation, and actuates the appropriate ESF equipment when preset limits are reached. ESFAS subsystems monitor plant parameters indicative of different accidents. When the minimum number of channels of a monitored variable reaches a preset limit, trip bistables satisfy coincidence logic for an individual subsystem and the subsystem is automatically initiated. ESFAS subsystems include SI actuation. Among other things, a manual or automatic SI signal initiates a reactor trip through the reactor protection system. The SI actuation contacts that supply a signal to the reactor trip logic originate in each of the two ESFAS logic trains. Each ESFAS logic train supplies a reactor trip signal to both trains of reactor protection logic. This leads to a unique condition where the ESFAS logic A-Train is communicating with the RPS logic B-Train (as well as with the A -Train), and the ESFAS B -Train is communicating with the RPS A-Train (as well as with the B-Train). This condition does not create an electrical separation conflict between redundant trains because the inputs to reactor protection are channel-related. Within each train of reactor protection, the two inputs from SI actuation train A & B enter two separate channel-related racks. There, the inputs drive separately fused isolation relays. Additional information can be found in Section 7.3 of the PBNP FSAR..

Safety Assessment:

The cables and cabinets addressed by this LER are all located in the cable spreading room (CSR), which is a vital protected area in the Point Beach Plant. The train separation violation identified in the event description would not by itself make the SI actuation signal input to the reactor protection inoperable. However, a initiating event such as a fire U.S. NUCLEAR REGULATORY COMMISSION 00 2002 - 002 - could have effected both the A-Train and B-Train which were found installed in the B-Train cable trays. The CSR is protected from significant fire events by both heat and smoke detectors and an automatic Halon fire suppression system. Thus the potential for an uncontrolled fire in the CSR is minimized. In addition, in accordance with 10 CFR 50 Appendix R safe shutdown requirements, the plant can be safely shutdown and maintained in a safe shutdown condition without the availability of the CSR equipment.

Notwithstanding these fire protection provisions, if a fire had initiated in the B-Train cable trays, it is probable that the circuits would have failed to an open circuit or could have short circuited. In the former case, the function of the ESF to RP would have been satisfied since this circuit scheme is designed as a "de-energize to trip" circuit and an open circuit would result in a reactor trip signal. If a hot smart short occurred in the cable tray and the circuit remained energized, it is likely that the B-train ESF signal cable to the A-Train RP would remain unaffected by the initiating fire and capable of completing the ESF to RP trip function.

Based on these considerations we have concluded that the health and safety of the public and plant staff was not impacted by the event. Since we have not identified any loss of safety function that resulted from this lack of adequate ESF to RP train separation, we have also concluded that this event did not involve a safety system functional failure.

Similar Occurrences:

A review of LERs submitted in the past three years identified no other events involving cross train separation events.

An older LER dated September 7, 1996 was identified which discussed main control board circuit separation.

LER NUMBER Title Redundant Safety Related Circuits in Same Main Control Board Wireways