05000313/LER-2002-001, Arkansas Unit 1 Main Steam Safety Valve as-Found Lift Settings Were Not within Technical Specification Limits

From kanterella
(Redirected from 05000313/LER-2002-001)
Jump to navigation Jump to search
Arkansas Unit 1 Main Steam Safety Valve as-Found Lift Settings Were Not within Technical Specification Limits
ML023250204
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 11/18/2002
From: Cotton S
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
1CAN110201 LER 02-001-00
Download: ML023250204 (7)


LER-2002-001, Arkansas Unit 1 Main Steam Safety Valve as-Found Lift Settings Were Not within Technical Specification Limits
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications

10 CFR 50.73(a)(2)(i)

10 CFR 50.73(a)(2)(vii), Common Cause Inoperability

10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded

10 CFR 50.73(a)(2)(viii)(A)

10 CFR 50.73(a)(2)(viii)(B)

10 CFR 50.73(a)(2)(ix)(A)

10 CFR 50.73(a)(2)(iv)(A), System Actuation

10 CFR 50.73(a)(2)(x)

10 CFR 50.73(a)(2)(v), Loss of Safety Function
3132002001R00 - NRC Website

text

Eu)7ter~gy Entergy Operations, Inc.

1448S R 333 Russeliville, AR 72802 Tel 501 858 5000 ICANI10201 November 18, 2002 U. S. Nuclear Regulatory Commission Document Control Desk Mail Station OPl-17 Washington, DC 20555

Subject:

Arkansas Nuclear One - Unit - 1 Docket No. 50-313 License No. DPR-51 Licensee Event Report 50-313/2002-001-00

Dear Sir or Madam:

In accordance with 10CFR50.73(a)(2)(i)(B), enclosed is the subject report concerning Main Steam Safety Valves. The enclosure contains no commitments.

Sincerely, Sherrie R. Cotton Director, Nuclear Safety Assurance SRC/ffs enclosure (V/

I CANI10201 PAGE 2 cc:

Mr. Ellis W. Merschoff Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 Institute of Nuclear Power Operations 700 Galleria Parkway Atlanta, GA 30339-5957 LEREvents~inpo.org

NRC FORM 366 U.S. NUCLEAR REGULA I DRY APPROVED BY OMB NO. 3160-0104 EXPIRES 6-30-2001 (1.2001)

COMMISSION Estimated burden per response lo comply vdth this mandatory information collection request: 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br />. Send comments regarding LICENSEE EVENT REPORT 'LER' burden estimate to the Records Management Branch (T-6 E6). US.

LICE4SE EVNT EPOT (ER)Nuclear Regulatory Commission. Washington. DC 2065550001. and to the Desk Officer. Office of Information and Regulatory Affairs, NEOB-10202 (3150.104). Office of Management and Budget, j

.Washington. DC 20503.

FACILITY NAME (1)

DOCKET NUMBER (2)

PAGE (3)

Arkansas Nuclear One -

Unit 1 05000313 1 OF 5 TITLE(4) Main Steam Safety Valve As-Found Lift Settings Were Not Within Technical Specifications Limits EVENT DATE (6_

LER NUMBER (6)

REPORT DATE (7)

OTHER FACILITIES INVOLVED (8)

MO DAY YEAR YEAR SEQUENTIAL REV MO DAY YEAR FACILITY NAME DOCKET NUMBER NUM13ER NO FACILITY NAME DOCKET NUMBER 09 25 2002 2002 001 00 11 18 2002 NBE NO 503a)2(.)

OPERATING REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR: (Check one or more) (11)

MODE (9) 1 20.2201 (b) 20 2203(a)(3)(i) 50.73(a)(2)(i)(C) 50.73(a)(2)(vii)

POWER 20.2201 (d) 20.2203(a)(3)(ii) 50.73(a)(2)(ii)(A) 50.73(a)(2)(viii)(A)

LEVEL (10) 080 20.2203(a)(1) 20.2203(a)(4)

_ 50 73(a)(2)(fi)(B) 50.73(a)(2)(viii)(B) 20.2203(a)(2)(i) 50.36(c)(1)(i)(A) 50 73(a)(2)(ihi) 50.73(a)(2)(ix)(A) 20.203(((2)(Ii) 5_

50.36(c)(1 )(ii)(A) 50.73(a)(2)(iv)(A) 50.73(a)(2)(x) 20.2203(a)(2)(mII) 50.36(c)(2) 50 73(a)(2)(v)(A) 73.71 (a)(4) 20.2203(a)(2)(iv) 50.46(a)(3)(ii) 50 73(a)(2)(v)(B) 73 71 (a)(5) 20.2203(a)(2)(v) 50 73(a)(2)()(A) 50.73(a)(2)(v)(C)

OTHER 20.2203(a)(2)(vi)

X 50.73(a)(2)(i)(B) 3 50 73(a)(2)(v)(D)

Specify in Abstract or I

I (17)

A.

Plant Status At the time this condition was discovered, Arkansas Nuclear One Unit 1 (ANO-1) was operating in Mode 1 with power coasting down prior to a scheduled refueling outage.

When testing of Main Steam Safety Valves (MSSVs) [SB]

started, the reactor power was approximately 81 percent power.

When testing was completed, reactor power was approximately 78 percent.

B.

Event Description

As-found lift settings of MSSVs were outside the requirements of Technical Specifications (TS).

ANO-1 has eight MSSVs per header.

During Modes 1, 2, and 3, TS 3.7.1 requires that seven MSSVs be operable on each header.

The Bases of Surveillance Requirement 3.7.1.1 specify an as-found lift setting within plus or minus three percent of the setpoint.

Routine MSSV surveillance testing began on September 24, 2002, and was completed on September 27, 2002.

MSSVs that were not within one percent of their setpoint were adjusted and retested until repeatable lifts were within tolerance.

Results of the initial as-found tests are provided below.

Set point and as-found pressure values are in psig units.

"A" HEADER Valve Number PSV-2692 PSV-2693 PSV-2694 PSV-2695 PSV-2696 PSV-2697 PSV-2698 PSV-2699 Setpoint 1100 1100 1090 1090 1070 1070 1060 1050 As-Found 1141.4 1107.5 1122.8 1094.9 1060.8 1016.3 1041.5 1038.3 Percent Deviation

+3.77

+0.68

+3.01

+0.45

- 0.86
- 5.02
- 1.75
- 1.11 "B" HEADER Valve Number PSV-2684 PSV-2685 PSV-2686 PSV-2687 PSV-2688 PSV-2689 PSV-2690 PSV-2691 Setpoint 1050 1060 1070 1070 1090 1090 1100 1100 As-Found 1015.9 1072.4 1081.5 1077.4 1032.0 1052.9 1138.4 1059.6 Percent Deviation
- 3.25

+1.17

+1.07

+0.69

- 5.32
- 3.40

+3.49

- 3.68 NRC FORM 388A (1-2001)

II rdlQ. ru,m.OOM u.O. r4ULLIU

uLiurz

uml NEST; FORM JbbA U.0. 1MUS-tJpu Mr mul-M Jr% SVMI (1-2001)

LICENSEE EVENT REPORT (LER)

FACILITY NAME (1 DOCKET (2)

LER NUMBER 6 F

YA SEQUENTIAL REVISION NUMBER NUMBER Arkansas Nuclear One -

Unit 1 05000313 2

SN2 001 00RS NARRATIVE (17)

C.

Root Cause No single root cause that explained all test results could be determined.

Five potential failure modes were identified during failure mode analysis.

They are spring relaxation, seat bonding, excessive spindle run out, a change to testing using the Crosby Set Point Verification Device (SPVD), and steam header pressure oscillations.

Spring relaxation is typically associated with springs that have been in service for an extended period of time.

During the evaluation of this condition it was noted that valves purchased in 1996 as spares might also be subject to this mechanism.

Spring assemblies for these valves may not have been preset since the vendor may not have specified presetting and it was not an ASME Code requirement at the time these springs were manufactured.

Changes in the spring can result in setpoint drift after a plant trip and result in subsequent lifts being below the setpoint for valves that cycled open.

The 316SS disc material is susceptible to seat bonding that can cause high initial lifts.

Seat bonding occurs on a molecular level between the dissimilar stainless steel metals of the seat and nozzle.

This phenomenon has been experienced in similar valve designs used by other licensees.

Additionally, the 316SS spindle is susceptible to run out that can also affect valve lift point and repeatability.

The testing associated with this condition was the first use of the Crosby SPVD test method for ANO-1 MSSVs.

There are inherent accuracy differences between test methods and the change of test method is expected to have introduced some difference in results.

The power level at which the testing was conducted resulted in steam header pressure oscillations larger than those normally experienced during MSSV testing.

Since the SPVD does not average header pressure readings, a pressure not representative of the average value could have been used in the lift point calculation.

D.

Corrective Actions

All MSSVs were adjusted using the SPVD to within the required as-left tolerance.

Additional in-situ testing of certain MSSVs, as determined by failure mode selection criteria, is planned following startup from the current outage.

Selected spare MSSVs have been tested at an off-site facility.

Results of these tests will be used to determine further actions.

An activity will be added to the forced outage plan to test MSSVs that lift during future transients.

Actions to minimize the effects of steam header pressure oscillations on test results will be evaluated.

MIQIaUN I1 NRC FORM 388A (1-2001)

I

1IE'JI' NRCI FRUM 000A 1V. U%1Lr-MM nr.WULAI %Jr% NUAMI (1-2001)

LICENSEE EVENT REPORT (LER)

FACILITY NAME (1)

DOCKET 2 LER NUMBER 6 P

YEAR SEQUENTIAL REVISION NUMBER NUMBER Arkansas Nuclear One -

Unit 1 05000313 2002 001 00 4

NARRATIVE (17)

ANO plans to use the SPVD to re-certify a spare MSSV after it is installed to ensure that the same test device is used for as-left and as-found testing.

E.

Safety Significance

The as-found lift settings of the MSSVs were evaluated with respect to the safety analysis events that would be negatively impacted by these values being above or below the nominal setpoints by more than three percent. These safety analysis events are Steam Generator Tube Rupture (SGTR), Loss of Load, and Loss of All AC Power for low lift settings and Small Break Loss of Coolant Accident (SBLOCA) and Turbine Trip for high lift settings.

The Loss of Load transient assumes that steam is relieved by the MSSVs and Atmospheric Dump Valves (ADVs) [JI] following turbine stop valve closure at 100 percent power.

After the turbine trip, excess steam is relieved to the atmosphere until the Reactor Coolant System (RCS) [AB] pressure is below the ADV setpoint of 1020 psig.

The Once Through Steam Generators (OTSGs) [AB]

cannot be isolated until the lowest MSSV reset point is reached.

Since the as-found lift points of 1015.9 psig for PSV-2684 on the "B" header and 1016.3 psig for PSV-2697 on the "A" header are slightly below the ADV setpoint, the OTSGs would continue to relieve steam until these MSSVs closed. All other MSSV lift settings were above 1020 psig and, therefore, do not affect the Loss of Load results.

The analysis assumption, as stated in the Safety Analysis Report (SAR), is that the whole body dose consequence does not change based on steam relief since the major contributing isotopes are negligible; however, the thyroid dose consequence will change due to Iodine 131 release.

The analysis calculated thyroid dose of 12 mRem is due to an assumed one gpm primary to secondary leak rate with one percent failed fuel.

The cool down to the lowest MSSV reset point would allow more steam to be relieved to the atmosphere.

Since the condition of the ANO-1 core was "clean" (the RCS activity was 2.85E-1 pCi/ml) when the MSSVs were tested, the SAR analysis continues to be bounding.

Dose consequences for the Loss of All AC Power transient are not specifically considered.

The SAR states that this event is not part of the ANO-1 licensing basis.

In any case, the results would be similar.

The SGTR analysis assumes release of secondary inventory through the MSSVs at their nominal setpoints.

If the valve lift points are below those assumed in the analysis, a larger dose rate would be predicted.

Small increases in predicted dose rates are bounded by assumptions in the SAR where MSSVs are assumed to be open for some time after the reactor trip until the RCS is depressurized to below the lowest MSSV setpoint of 1050 psig when the affected OTSG is isolated.

The major conservative assumption is that the RCS curie content results from one percent failed fuel.

Since the RCS activity at the time of the MSSV testing was very low, the effect of the lower MSSV lift and reset points that would allow more primary coolant to leak into the secondary and to the environment is offset by the low actual RCS activity.

Due to the low RCS activity and only two MSSV lift points being below 1050 psig, the SAR SGTR analysis remains bounding.

The SBLOCA analysis assumes that the OTSGs are removing heat from the reactor core at a saturation pressure consistent with the MSSV with the lowest lift point.

If this accident had occurred with the as-found lift settings, the (17)

OTSG pressures would have been controlled at a lower pressure with enhanced heat removal as compared to the analysis.

Therefore, the SBLOCA analysis was not negatively affected by this condition The Turbine Trip analysis assumes that only seven of the eight MSSVs on each header are available to relieve steam.

Those valves assumed to be available on each header are a 1050 psig setpoint valve, two 1070 psig setpoint valves, two 1090 psig setpoint valves, and two 1100 psig setpoint valves, each with an opening tolerance of plus three percent applied.

Both PSV-2692 and PSV-2694 opened greater than three percent above their nominal setpoint.

Valve PSV-2692 can be assumed to be the valve that is not available for steam relief, and PSV-2694 opened within the setpoint of that assumed for the second 1100 psig nominal setpoint valve.

Since the opening setpoint of the seven valves assumed available in the analysis was greater than seven of the eight MSSVs tested, the plant would have behaved conservatively as compared to the analysis, and the analysis remains bounding for the as-found condition of the MSSVs on the "A" header.

Since seven of the eight valves on the "B" header lifted at less than the values assumed in the analysis, the analysis remains bounding for the as-found condition.

Based on these considerations, the MSSVs would have performed their required functions with the as-found lift points and no safety analysis results would have been invalidated.

Therefore, this condition is considered to have had minimal actual safety significance.

F.

Basis for Reportability On September 25, 2002, the second MSSV on the "B" header was found to have its as-found lift point outside of the plus or minus three percent of setpoint tolerance.

Guidance provided in Example (3) of Section 3.2.2 of NUREG-1022 Revision 2, "Event Report Guidelines -

10CFR50.72 and 50.73,"

states that the existence of similar discrepancies in multiple valves is an indication that the discrepancies may well have arisen over a period of time.

Since the failure mode evaluation does not support a conclusion that the documented lift point condition occurred at the time of discovery, this condition is reportable in accordance with 10CFR50.73(a)(2)(i)(B) as operation prohibited by Technical Specifications.

G.

Additional Information

The ANO-1 MSSVs are model Type 3707R six inch valves manufactured by Dresser Industries (Manufacturer Code D243).

There have been no previous similar events reported as Licensee Event Reports by ANO-1; however, until the implementation of Improved Technical Specifications in July 2002, an as-found lift point plus or minus three percent of the setpoint was not a TS requirement for MSSV operability.

Energy Industry Identification System (EIIS) codes are identified in the text as [XX].

I