05000247/FIN-2011004-02
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Marginally Designed Fuse Results in Fuse Failure and lnoperability of the Refueling Water Storage Tank |
Description | The inspectors identified a Green NCV of 10 CFR 50, Appendix B, Criterion Ill, Design Control, because Entergy personnel did not establish measures to assure that the design basis for sizing of a fuse was adequate and correctly translated into specifications, drawings, procedures, and instructions. Specifically, between November 29, 2005 and September 13, 2010, the fuse for four control room annuciator panels SASC was marginally sized which resulted in fatigue-induced fuse failure, associated loss of lighting to the annunciator panels, the loss of the refueling water storage tank (RWST) low low level alarms, and the inoperability of the RWST. Entergy personnel immediately replaced the fuse. This issue was entered into Entergy's CAP as CR-IP2-201 0-5713 and CR-IP2-2011-2967. This finding is more than minor because it is associated with the design control attribute of the Mitigating Systems cornerstone and adversely affected the objective to ensure the reliability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Specifically, the loss of the RWST low low level alarms impacts an alert function relied on by operations personnel to swap the suction of the safety injection pumps from the RWST to the containment sump during accident conditions. Using IMC 0609.04, Phase 1 -Initial Screening and Characterization of Findings, the inspectors determined this finding was of very low safety significance (Green) because the finding was related to a design or qualification deficiency confirmed to result in a loss of operability of the RWST low low level alarms; however, the finding did not represent a loss of safety system function because RWST level indication was available via redundant level instruments on the control room instrument panel that operators also normally rely on and are trained to use. Also the finding did not screen as potentially risk significant due to external initiating events. The finding has a crosscutting aspect in the area of problem identification and resolution associated with the corrective action program attribute because Entergy personnel did not thoroughly evaluate problems associated with the fuse for control room annunciator panels SA-SC, such that the resolution address causes and extent of conditions, as necessary. This includes properly classifying, prioritizing, and evaluating for operability and reportability conditions adverse to quality. |
Site: | Indian Point |
---|---|
Report | IR 05000247/2011004 Section 4OA3 |
Date counted | Sep 30, 2011 (2011Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71153 |
Inspectors (proximate) | J Noggle M Catts M Jennerich O Masnyk-Bailey P Finney S Barr S Hammann S Mccarver T O'Hara |
CCA | P.2, Evaluation |
INPO aspect | PI.2 |
' | |