05000286/FIN-2011002-04
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Inadequate Application of Sealant Resulted in Drain Blockage for the Turbine-Driven Auxiliary Feedwater Pump |
Description | The inspectors identified a NCV of very low safety significance (Green) of 10 CFR 50, Appendix B, Criterion XVl, Corrective Actions, because Entergy personnel did not identify and correct a condition adverse to quality with regard to packing leakoff reservoir drain line blockage for the 32 ABFP which likely existed for some timeframe between October 2010 and January 2011. Specifically, Entergy personneldid not identify and correct inappropriate application of sealant coupled with drain line blockage that resulted in inadequate drainage of the leakoff reservoir associated with the 32 ABFP. This condition most likely resulted in water intrusion into the pump's outboard bearing housing in January 2011. Entergy personnel entered this issue into their CAP as CR-lP3-2011-00018. Corrective actions included the performance of a higher-tier apparent cause evaluation for the oil/water mixture identified; flush, drain and refill of the affected bearing housing to remove residualwater contamination; and removal of the sealant on the pump leakoff reservoir drain to prevent recurrence. The finding was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected its objective of ensuring the availability and reliability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the water intrusion in the bearing housing as a result of the performance issue could adversely impact the bearing cooling function of the pump. The inspectors determined the finding was of very low safety significance (Green) in accordance with Table 4a of IMC 0609, Attachment 4, Determining the Significance of Reactor Inspection Findings for At-Power Situations. The inspectors concluded that the water intrusion in the 32 ABFP pump outboard bearing housing, while it caused unanticipated unavailability, did not result in a loss of operability or safety function of the 32 ABFP and was not risk significant with respect to external initiating events. This finding has a cross-cutting aspect in the area of Problem ldentification and Resolution associated with the attribute of the corrective action program because Entergy personnel did not thoroughly identify and correct drain line blockage indications for the turbine-driven ABFP. |
Site: | Indian Point |
---|---|
Report | IR 05000286/2011002 Section 1R15 |
Date counted | Mar 31, 2011 (2011Q1) |
Type: | NCV: Green |
cornerstone | Emergency Prep, Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.15 |
Inspectors (proximate) | C Newport E Gray J Noggle M Gray M Halter P Cataldo T O'Hara |
CCA | P.1, Identification |
INPO aspect | PI.1 |
' | |