ISFSI Transmittal of Revisions to Emergency Plan Report of Changes
ML19070A118
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 03/04/2019
From: Mark D. Sartain
Dominion Energy Nuclear Connecticut
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
Shared Package
ML19070A153 List:
References
19-101
Download: ML19070A118 (2)


Text

Dominion Energy Nuclear Connecticut, Inc.

5000 Dominion Boulevard, Glen Allen, VA 23060 Dominion Energy.com

!i\e pr Dominion Energy March 4, 2019 U.S. Nuclear Regulatory Commission Serial.No.: 19-101 Attention: Document Control Desk NRA/TJS: RO Washington, D.C. 20555

  • Docket Nos.: 50-245/336/423 72-47 License Nos.: DPR-21/65 NPF-49 DOMINION ENERGY NUCLEAR CONNECTICUT, INC.

MILLSTONE POWER STATION UNITS 1, 2, 3 AND ISFSI REVISIONS TO MILLSTONE POWER STATION EMERGENCY PLAN REPORT OF CHANGES Pursuant to 10 CFR 50.54(q)(5) and 10 CFR 72.44(f), attached are change analysis summaries for Revisions 58 and 59 to the Millstone Power Station (MPS) Emergency Plan. Revision 58 became effective on February 1, 2019 and Revision 59 became effective February 20, 2019. These revisions incorporated changes that did not require prior NRC approval and do not implement actions that reduce the effectiveness of the MPS Emergency Plan. The Emergency Plan continues to meet the standards of 10 CFR 50.47(b).

If you have any questions or require additional information, please contact Mr. Thomas Szymanski at (804) 273-3065.

  • Sincerely, Mark D. Sartain Vice President - Nuclear Engineering and Fleet Support Attachments:
1. Millstone Power Station Emergency Plan, Rev. 58, 10 CFR 50.54(q)(5) Summary
2. Millstone Power Station Emergency Plan, Rev. 59, 10 CFR 50.54(q)(5) Summary Commitments made by this letter: None Axt-f5 f\J M55 2/,t, rJ t (L_

/JMS5

Serial No.19-101 Docket Nos. 50-245/336/423, 72-47 Page 2 of 2 cc: U.S. Nuclear Regulatory Commission, Region I 2100 Renaissance Blvd Suite 100 King of Prussia, PA 19406-2713 ATTN: Document Control Desk Director, Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Mr. R. Guzman (without attachment)

NRC Senior Project Manager (Units 2 and 3)

U.S. Nuclear Regulatory Commission, Mail Stop 08 C-2 One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Mr. T. H. Carter (without attachment)

NRC Senior Project Manager (Unit 1)

U.S. Nuclear Regulatory Commission, Mail Stop T-8 F5 Two White Flint North 11545 Rockville Pike Rockville, MD 20852-2738 Mr. J. N. Nguyen (without attachment)

NRC Senior Project Manager (ISFSI)

U. S. Nuclear Regulatory Commission, Mail Stop 4834 Two White Flint North 11545 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station