MONTHYEARIR 05000002/20140022014-06-23023 June 2014 IR 05000002-14-002, 06/23/2014, University of Michigan Ford Nuclear Reactor, 591M Part 1 & 3 IR 05000002/20120022013-10-0404 October 2013 IR 05000002-12-002(DNMS), on 09/11/2013, University of Michigan Ford Reactor Inspection Report IR 05000000/20120012012-10-10010 October 2012 IR 0500000-12-001, 9/11/2012, University of Michigan - Ford Nuclear Reactor IR 05000002/20110012011-10-24024 October 2011 IR 05000002-11-001 and Notice of Violation, on 08/09-11/2011 - 10/12/2011, Univ of Mi Ford Nuclear Reactor IR 05000002/19500112011-04-29029 April 2011 Notification of Licensed Operator Initial Examination 05000250-11-3002,05000251-11-302 IR 05000002/20090032011-03-24024 March 2011 IR 05000002-09-003, on 09/14-16/2010, In-office Review Through 03/14/2011, University of Michigan - Ford Nuclear Reactor ML1032300972010-11-17017 November 2010 Oak Ridge Institute for Science and Education (Orise) Letter Report for Four Soil Samples from the University of Michigan Ford Reactor (IR 05000002/2009003) IR 05000002/19600102010-02-0909 February 2010 Notification of Licensed Operator Initial Examination - 05000259-10-301, 05000260-10-0301, 05000296-10-301 IR 05000002/20200902009-12-0404 December 2009 IR 05000220-090-10 and 05000410-09-010; Nine Mile Point Nuclear Station, LLC; on 10/5-22/2009; Nine Mile Point Nuclear Station, Units 1 and 2; Biennial Baseline Inspection of Identification and Resolution of Problems Report IR 05000002/19640092009-07-0909 July 2009 IR 05000264-09 on 06/22/09 - 06/26/09 for Dow Chemical Co IR 05000002/20090022009-06-19019 June 2009 IR 05000002-09-002 on 03/24/09 and 06/01/09 - 06/02/09 for Univ of Michigan - Ford Nuclear Reactor IR 05000002/19772782009-01-0606 January 2009 EA-08-298, Peach Bottom - Notice of Violation with Proposed Imposition of Civil Penalty - $65,000 (Peach Bottom Atomic Power Station - NRC Investigation Report No. 1-2008-001 and NRC Inspection Report Nos. 05000277-278/2007404; and 05000277 IR 05000002/20090012008-12-23023 December 2008 IR 05000002-09-01 on 12/10/08 - 12/11/2008 for Ford Nuclear Reactor; (DNMS) IR 05000002/20080012008-09-25025 September 2008 IR 05000002-08-01 (DNMS) on 08/28/08 for Ford Nuclear Reactor, Univ. of Michigan IR 05000002/20070012007-12-0606 December 2007 IR 05000002-07-001, on 06/28/2007 & 11/13-14/2007, Univ. of Michigan - Ford Nuclear Reactor Inspection IR 05000002/20060012006-12-27027 December 2006 IR 05000002-06-001; University of Michigan; 10/19/2006 - 11/28-29/2006; Ford Nuclear Reactor IR 05000002/20032032004-01-20020 January 2004 IR 05000002-03-203, on 10/20/03 - 10/22/03, Ford Nuclear Nuclear Reactor Facility IR 05000002/20022012003-01-27027 January 2003 IR 05000002-02-201, on 03/11/2002 - 03/12/2002 & 04/22/2002 - 04/25/2002, Ford Nuclear Reactor, Actions Related to Reportable Occurrence No. 23 IR 05000002/19992011999-05-27027 May 1999 Insp Rept 50-002/99-201 on 990503-06.No Violations Noted. Major Areas Inspected:Organizational Structure & Functions, Operations,Design Control,Review & Audit,Operator Requalification,Maint,Surveillance & Procedures IR 05000002/19980031998-12-11011 December 1998 Submits Suppl to Insp Rept 50-002/98-03 Conducted on 981016-20.Inspectors Reviewed Operating Log Book Entries from 970304-0828,to Verify That Reactor Staffing Met Min Requirements of TSs IR 05000002/19982031998-11-23023 November 1998 Insp Rept 50-002/98-203 on 981026-30.No Violations Noted. Major Areas Inspected:Refueling,Surveillance,Experiments, Environ Protection,Emergency Plan,Health Physics, Transportation & non-routine Event follow-up IR 05000002/19982021998-03-30030 March 1998 Informs That Open Predecisional Conference to Discuss Apparent Violations Identified in Rept 50-002/98-202 Has Been Scheduled for 980422 IR 05000002/19982011998-01-16016 January 1998 Insp Rept 50-002/98-201 on 980106-07.No Violations Noted. Major Areas Inspected:Plans,Procedures & Reviews 81401, Protection of Safeguards info,81810 Matl Control & Accounting of SNM & 85102 Fixed Site Physical Protection IR 05000002/19970011997-03-25025 March 1997 Insp Rept 50-002/97-01 on 970224-28.No Violations Noted. Major Areas Inspected:Organization,Operations & Maint, Procedures,Experiments,Emergency Preparedness,Audits & Reviews,Radiation Control & Surveillance Protection IR 05000002/19930041994-01-26026 January 1994 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-002/93-04 IR 05000002/19930051993-09-23023 September 1993 Insp Rept 50-002/93-05 on 930907-10.No Violations Noted. Major Areas Inspected:Radiation Controls,Environ Protection & Licensee Action on Previous Insp Findings IR 05000002/19930011993-02-0808 February 1993 Insp Rept 50-002/93-01 on 930119-22.Violations Noted But Not Cited.Major Areas Inspected:Review & Audit Functions,Lers, Emergency Planning,Radiation Controls,Environ Protection & Licensee Action on Previous Insp Findings IR 05000002/19890011989-04-24024 April 1989 Insp Rept 50-002/89-01 on 890413-14.No Violations, Deficiencies or Deviations Noted.Major Areas Inspected: Emergency Preparedness Program,Including Training, Notifications & Communications IR 05000002/19880021988-08-0303 August 1988 Insp Rept 50-002/88-02 on 880720-22.No Violations Noted. Major Areas Inspected:Records,Logs & Organization,Radiation Protection,Radwaste Mgt Control & Transportation Activities IR 05000002/19880011988-01-29029 January 1988 Insp Rept 50-002/88-01 on 880111-14.No Violations Noted. Major Areas Inspected:Records,Logs & Organization,Review & Audit Functions,Requalification Training,Procedures, Surveillance & Maint & Fuel Handling Activities IR 05000002/19870041988-01-0404 January 1988 Insp Rept 50-002/87-04 on 871215-16.No Violations, Deficiencies or Deviations Noted.Major Areas Inspected: Onsite Emergency Preparedness Program,Including Training, Communications & Review of Emergency Plan & Procedures IR 05000002/19870031987-07-0707 July 1987 Insp Rept 50-002/87-03 on 870615-17.Major Areas Inspected: Records,Logs,Organization,Radiation Protection,Radwaste Mgt Control,Transportation Activities & follow-up Actions on Previous Findings IR 05000002/19870011987-05-0404 May 1987 Exam Rept 50-002/87-01OL on 870414.Exam Results:Both Candidates Passed.Exams & Answer Keys Encl IR 05000002/19870021987-03-31031 March 1987 Partially Withheld Matl Control & Accountability Insp Rept 50-002/87-02 on 870316-19 (Ref 10CFR2.790).No Violations Noted.Major Areas Inspected: Matl Control & Accounting - Reactors IR 05000002/19860021986-10-31031 October 1986 Insp Rept 50-002/86-02 on 861016 & 17.No Violations, Deficiencies or Deviations Noted.Major Areas Inspected: Review of Emergency Plan & Procedures & Maint of Emergency Plan IR 05000002/19860011986-07-16016 July 1986 Insp Rept 50-002/86-01 on 860616-18.No Violations or Significant Safety Issues Noted.Major Areas Inspected: Records,Logs & Organization,Radiation Protection,Radwaste Mgt Control & Transportation Activities IR 05000002/19850041985-11-27027 November 1985 Insp Rept 50-002/85-04 on 851120-22.Violation Noted:Staff Organization Inconsistent W/Tech Specs IR 05000002/19850031985-10-25025 October 1985 Insp Rept 50-002/85-03 on 851002-04.Violations Noted:Release of Matl Not Readily Soluble or Dispersible to Sanitary Sys & Failure to Complete Quarterly Effluent Repts IR 05000002/19850021985-06-12012 June 1985 Insp Rept 50-002/85-02 on 850529-30.No Noncompliance or Deviations Noted.Major Areas Inspected:Onsite Emergency Preparedness Program 2014-06-23
[Table view] Category:Letter
MONTHYEARML15196A0292015-07-0606 July 2015 Termination of Quality Assurance Program Approval for Radioactive Material Packages No. 0348 ML15112A0832015-04-14014 April 2015 Amendment No. 12 to Indemnity Agreement No. E-24 University of Michigan Ford Nuclear Reactor ML14310A5882015-04-0202 April 2015 Ford License Termination Letter - Termination of Facility Operating License No. R-28 for the University of Michigan Ford Nuclear Reactor ML15030A3112015-01-22022 January 2015 Analytical Results for University of Michigan Soil ML15020A7252015-01-16016 January 2015 University of Michigan, Ford Nuclear Reactor, Storage Ports Soil Sample Results ML15029A5102015-01-14014 January 2015 University of Michigan, Ford Nuclear Reactor, Report on Reactor. Operations ML14099A1072014-03-28028 March 2014 Report on Reactor Operations University of Michigan Ford Nuclear Reactor ML14063A2072014-02-26026 February 2014 University of Michigan, Request for Termination of the Ford Nuclear Reactor ML13360A1802013-12-23023 December 2013 University of Michigan Ford Reactor Master Inspection Plan IR 05000002/20120022013-10-0404 October 2013 IR 05000002-12-002(DNMS), on 09/11/2013, University of Michigan Ford Reactor Inspection Report ML13235A0092013-08-19019 August 2013 University of Michigan, Ford Nuclear Reactor, Submittal of Final Status Survey - Background Count Rate Correction ML13205A1532013-07-11011 July 2013 University of Michigan - Ford Nuclear Reactor: Final Status Survey Report (Cover Letter) ML13051A0472013-02-14014 February 2013 University of Michigan - Ford Nuclear Reactor, Reportable Occurrence #24, Reactor Building Flood - Ruptured Fire Suppression Line, Technical Specification (Section 1.0 / Item 8) ML13029A5002013-01-24024 January 2013 University of Michigan, Submittal of 2012 Report on Reactor Operations ML12356A1352012-12-18018 December 2012 MIP- University of Michigan Ford Reactor Master Inspection Plan CY2013 ML13028A1012012-12-11011 December 2012 University of Michigan, Technical Specification Amendment Request Final Status Survey - Survey Design Package for Fnr Foundation Cavity ML12312A1302012-11-0202 November 2012 Ford Nuclear Reactor, Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.5.10.6 (Final Status Survey) ML12293A3022012-10-25025 October 2012 T. Alexander Ltr. Approval of Partial Final Site Survey Plan for University of Michigan Ford Nuclear Reactor IR 05000000/20120012012-10-10010 October 2012 IR 0500000-12-001, 9/11/2012, University of Michigan - Ford Nuclear Reactor ML12264A0642012-09-18018 September 2012 University of Michigan - Ford Nuclear Reactor Final Disposition of Fnr Storage Ports ML12264A5622012-09-17017 September 2012 University of Michigan - Ford Nuclear Reactor, Quality Assurance Plan for Final Status Survey Plan ML12199A0182012-07-13013 July 2012 University of Michigan, Request an Amendment to the Ford Nuclear Reactor Technical Specification Decommissioning Plan - Revised Section 4.0 (Final Status Survey ML12157A2662012-06-0101 June 2012 Ford Nuclear Reactor - Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.0 (Final Status Survey) ML12117A1182012-04-20020 April 2012 Occupational Safety & Environmental Health ML12124A3102012-04-20020 April 2012 University of Michigan, Report on Reactor Operations for January 1 to December 31, 2011 ML12095A3782012-02-14014 February 2012 University of Michigan Ltr Ford Nuclear Reactor- Decommissioning Plan- Additional Information for Section 4.0 (Final Status Survey Plan) Docket 50-2/ License R-28 ML12025A1252012-01-20020 January 2012 Ford Nuclear Reactor - Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.0 (Final Status Survey) ML1132606162011-11-21021 November 2011 IR 05000002-11-001; 08/09/2011, University of Michigan, Reply to a NRC Inspection Report Notice of Violation IR 05000002/20110012011-10-24024 October 2011 IR 05000002-11-001 and Notice of Violation, on 08/09-11/2011 - 10/12/2011, Univ of Mi Ford Nuclear Reactor ML11273A0262011-09-29029 September 2011 Fy 2012 University of Michigan Ford Nuclear Reactor Master Inspection Plan ML1124208522011-08-23023 August 2011 Orise Contract No. DE-AC05-06OR23100 Letter Report for Analytical Results for Three Soil Samples from the University of Michigan Ford Reactor, Ann Arbor, Michigan ML11199A0092011-07-12012 July 2011 Ford Nuclear Reactor - Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.0 (Final Status Survey Plan) (Response to NRC Comments Dtd June 1, 2011 on Initial Fnr - Technical Specification Amendment Submitted A IR 05000002/19500112011-04-29029 April 2011 Notification of Licensed Operator Initial Examination 05000250-11-3002,05000251-11-302 ML11119A0042011-04-0808 April 2011 Ford Nuclear Reactor - Technical Specification Amendment Request Decommissioning Plan - Revised Section 4.0 (Final Status Survey Plan) IR 05000002/20090032011-03-24024 March 2011 IR 05000002-09-003, on 09/14-16/2010, In-office Review Through 03/14/2011, University of Michigan - Ford Nuclear Reactor ML1104101322011-02-14014 February 2011 Change in NRC Staff Project Management for the University of Michigan Ford Nuclear Reactor ML1032300972010-11-17017 November 2010 Oak Ridge Institute for Science and Education (Orise) Letter Report for Four Soil Samples from the University of Michigan Ford Reactor (IR 05000002/2009003) ML1027803212010-10-0101 October 2010 MIP- University of Michigan Ford Nuclear Reactor Fiscal Year 2011 IR 05000002/19600102010-02-0909 February 2010 Notification of Licensed Operator Initial Examination - 05000259-10-301, 05000260-10-0301, 05000296-10-301 ML0935210582009-12-17017 December 2009 Mip - University of Michigan Ford Nuclear Reactor-FY 2010 IR 05000002/20200902009-12-0404 December 2009 IR 05000220-090-10 and 05000410-09-010; Nine Mile Point Nuclear Station, LLC; on 10/5-22/2009; Nine Mile Point Nuclear Station, Units 1 and 2; Biennial Baseline Inspection of Identification and Resolution of Problems Report ML0931305262009-11-20020 November 2009 October 23, 2009 Summary of Open Meeting with the University of Michigan to Discuss Decommissioning Status of Ford Nuclear Reactor IR 05000002/19640092009-07-0909 July 2009 IR 05000264-09 on 06/22/09 - 06/26/09 for Dow Chemical Co IR 05000002/20090022009-06-19019 June 2009 IR 05000002-09-002 on 03/24/09 and 06/01/09 - 06/02/09 for Univ of Michigan - Ford Nuclear Reactor ML0915505952009-06-0101 June 2009 Orise, Letter Report for Analytical Results for Two Soil Samples and One Concrete Sample from the Ford Reactor at the University of Michigan, Ann Arbor, Mi IR 05000002/19772782009-01-0606 January 2009 EA-08-298, Peach Bottom - Notice of Violation with Proposed Imposition of Civil Penalty - $65,000 (Peach Bottom Atomic Power Station - NRC Investigation Report No. 1-2008-001 and NRC Inspection Report Nos. 05000277-278/2007404; and 05000277 IR 05000002/20090012008-12-23023 December 2008 IR 05000002-09-01 on 12/10/08 - 12/11/2008 for Ford Nuclear Reactor; (DNMS) ML0829806362008-10-22022 October 2008 University of Michigan Ford Nuclear Reactor Master Inspection Plan - Fiscal Year 2009 IR 05000002/20080012008-09-25025 September 2008 IR 05000002-08-01 (DNMS) on 08/28/08 for Ford Nuclear Reactor, Univ. of Michigan IR 05000002/20070012007-12-0606 December 2007 IR 05000002-07-001, on 06/28/2007 & 11/13-14/2007, Univ. of Michigan - Ford Nuclear Reactor Inspection 2015-07-06
[Table view] |
Text
ber 6, 2007
SUBJECT:
NRC INSPECTION REPORT 050-00002/07-01 (DNMS)
FORD NUCLEAR REACTOR
Dear Mr. Alexander:
On November 14, 2007, the NRC completed inspection activities at the Ford Nuclear Reactor.
The purpose of the inspection was to determine whether the decommissioning activities were conducted safely and in accordance with NRC requirements. Specifically, during onsite inspections on June 28 and November 13-14, 2007, the inspector evaluated decommissioning performance and radioactive waste management. At the conclusion of the on-site inspections on June 28 and November 14, 2007, the inspector discussed the inspection findings with the Reactor Manager.
This inspection consisted of an examination of decommissioning activities at the Ford Nuclear Reactor as they relate to safety and compliance with the Commissions rules and regulations.
Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection consisted of a selective examination of procedures and representative records, and interviews with personnel.
Based on the results of this inspection, the NRC did not identify any violations.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). The NRCs document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.
Sincerely,
/RA/
Patrick L. Louden, Chief Decommissioning Branch Docket No.50-002 License No. R-28
Enclosure:
Inspection Report 050-00002/07-01(DNMS)
REGION III==
Docket No.50-002 License No. R-28 Report No. 050-00010/07-01(DNMS)
Licensee: University of Michigan Facility: Ford Nuclear Reactor Location: Ann Arbor, Michigan Dates: June 28, 2007, and November 13-14, 2007 Inspector: William G. Snell, Senior Health Physicist Peter Lee, Ph.D., CHP, Health Physicist Approved by: Patrick L. Louden, Chief Decommissioning Branch Division of Nuclear Materials Safety Enclosure
EXECUTIVE SUMMARY University of Michigan - Ford Nuclear Reactor NRC Inspection Report 050-00002/07-01(DNMS)
This routine decommissioning inspection included a review of the licensees current performance related to decommissioning activities and radioactive waste management.
Research and Test Reactor Decommissioning The inspectors determined that the licensee had complied with NRC and Department of Transportation regulations for shipments of radioactive waste. The inspectors determined that the licensee continued to be effective in controlling personal exposures, and that the licensees program for the unrestricted release of equipment and materials was adequately implemented.
The licensee was adequately implementing the Review Committee to review decommissioning activities.
2 Enclosure
Report Details1 1.0 Research and Test Reactor Decommissioning (69013)
1.1 Inspection Scope The inspectors evaluated radioactive waste shipments, reviewed radioactive waste shipping documents, and interviewed the individual responsible for waste shipments, to ensure compliance with NRC and U.S. Department of Transportation (DOT) regulations.
The inspectors reviewed the external exposure records for licensee and contractor personnel performing core borings and cutting concrete blocks from the reactor wall, and reviewed the results of air sampling during the core borings and concrete block cutting.
The inspectors reviewed the procedures and survey reports from the free release of equipment and materials.
The inspectors reviewed the conduct of the licensees Review Committee.
1.2 Observations and Findings During November 2008, the licensee made several LSA-1 shipments of concrete blocks from the dismantlement of the reactor pool wall, and slurry from cutting the concrete blocks. The licensees shipping manifest showed that personnel packaged, labeled, and marked each shipping container according to the DOT and 10 CFR Part 71 transportation requirements. The licensee verified that the results of radiation and removable contamination levels were within applicable limits. The waste manifest included all required information. The inspectors observed two rail cars being readied for shipment of concrete blocks. The concrete blocks were adequately blocked and braced and the rail cars covered with tarps prior to shipment.
The highest external radiation dose received by an individual during 2007 was 153 mrem. The general air sampling during core boring and cutting the concrete blocks did not indicate workers received any positive internal exposures.
The licensee conducted the surveys in accordance with its procedures and did not indicate any positive result of contamination from the free release of equipment and materials.
The licensees Review Committee was established to review decommissioning activities as directed by the Decommissioning Plan. The Review Committee was required to have a minimum of three members, an unspecified number of alternates, and meet at least semiannually. The inspectors discussed the Review Committees performance with the Decommissioning Reactor Manager and reviewed the agenda from a June 27, 2007, Committee Meeting. All three permanent members of the Committee and four of the five current alternate members attended the June 27th meeting. The three permanent members are required to attend to have a quorum, and if a 100 percent agreement is not reached on an issue, that issue is tabled until the objecting members concerns have been satisfied. The Reactor Manager indicated another meeting was to be conducted in December to meet the semi-annual requirement for calendar year 2007.
A List of acronyms used in the report is included at the end of the Report Details.
3 Enclosure
1.3 Conclusion The inspectors determined that the licensee had complied with NRC and Department of Transportation regulations for shipments of radioactive waste. The inspectors determined that the licensee continued to be effective in controlling personal exposures, and that the licensees program for the unrestricted release of equipment and materials was adequately implemented.
The licensee was adequately implementing the Review Committee to review decommissioning activities.
2.0 Exit Meeting Summary The inspectors presented the inspection results to licensee management at the conclusion of the onsite inspections on June 28 and November 14, 2007. The licensee acknowledged the findings presented.
ATTACHMENT: SUPPLEMENTAL INFORMATION 4 Enclosure
SUPPLEMENTAL INFORMATION PARTIAL LIST OF PERSONS CONTACTED Licensee
- C. Becker, Decommissioning Reactor Manager
- Indicates presence at the exit meetings held on June 28 and November 14, 2007.
INSPECTION PROCEDURES USED IP 69013 Research and Test Reactor Decommissioning ITEMS OPENED, CLOSED, AND DISCUSSED Opened None Closed None Discussed None LIST OF ACRONYMS USED CFR Code of Federal Regulations DOT Department of Transportation LSA Low Specific Activity NRC Nuclear Regulatory Commission DOCUMENTS REVIEWED Documents used during the inspection were specifically identified in the Report Details, above.
Attachment