IR 05000002/2008001
| ML082690735 | |
| Person / Time | |
|---|---|
| Site: | University of Michigan |
| Issue date: | 09/25/2008 |
| From: | Christine Lipa NRC/RGN-III/DNMS/DB |
| To: | Alexander T University of Michigan |
| References | |
| IR-08-001 | |
| Download: ML082690735 (6) | |
Text
September 25, 2008
SUBJECT:
NRC INSPECTION REPORT 050-00002/08-01(DNMS) - FORD NUCLEAR REACTOR
Dear Mr. Alexander:
On August 28, 2008, the NRC completed inspection activities at the Ford Nuclear Reactor. The purpose of the inspection was to determine whether the decommissioning activities were conducted safely and in accordance with NRC requirements. Specifically, the inspector evaluated decommissioning performance and radioactive waste management. At the conclusion of the on-site inspection on August 28, 2008, the inspector discussed the inspection findings with the Reactor Manager.
This inspection consisted of an examination of decommissioning activities at the Ford Nuclear Reactor as they relate to safety and compliance with the Commissions rules and regulations.
Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection consisted of a selective examination of procedures and representative records, and interviews with personnel.
Based on the results of this inspection, the NRC did not identify any violations.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). The NRCs document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.
Sincerely,
/RA/
Christine Lipa, Chief
Decommissioning Branch Division of Nuclear Materials Safety
Docket No.50-002 License No. R-28
Enclosure:
Inspection Report 050-00002/08-01(DNMS)
REGION III==
Docket No.50-002
License No.
R-28
Report No.
050-00002/08-01(DNMS)
Licensee:
University of Michigan
Facility:
Ford Nuclear Reactor
Location:
Ann Arbor, Michigan
Dates:
August 28, 2008
Inspector:
William G. Snell, Senior Health Physicist
Approved by:
Christine Lipa, Chief Decommissioning Branch Division of Nuclear Materials Safety
Enclosure
EXECUTIVE SUMMARY
University of Michigan - Ford Nuclear Reactor NRC Inspection Report 050-00002/08-01(DNMS)
This routine decommissioning inspection included a review of the licensees current performance related to decommissioning activities and radioactive waste management.
Research and Test Reactor Decommissioning
The inspector determined that the licensee was making good progress towards completing decontamination and dismantlement activities. No radiological concerns were identified during a facility tour and observation of work in progress.
Enclosure
Report Details1
1.0 Research and Test Reactor Decommissioning (69013)
1.1 Inspection Scope
The inspector reviewed the remaining major decommissioning activities and evaluated current work activities.
1.2 Observations and Findings
After about six months of minimal dismantlement activity, recent budget request approvals have enabled decommissioning activities to proceed at a fast pace. Currently scheduled work includes the removal of a concrete column, removal or decontamination of over 350 linear feet of piping embedded in concrete, removal of an estimated 335 linear feet of piping buried under the first floor, removal of an estimated 127 linear feet of piping buried below or contained within the basement floor slab, decontamination of the hot and cold sumps, decontamination of the transfer chute, and the remediation of storage ports and associated vent lines. The licensees goal is to complete these activities by the end of November 2008. The disposal of radioactive waste generated from these actions will occur after all the work is completed.
The primary activity in progress during the inspection was the cutting of a floor slab with a large diameter concrete diamond saw. Observation of the diamond saw work and a tour of the facility determined that work areas were adequately established to ensure the control of radioactive material, step-off pads were in use, areas were roped off and labeled, personal protective clothing was adequate, and radioactive waste was being appropriately stored.
1.3 Conclusion
The inspector determined that the licensee was making good progress towards completing decontamination and dismantlement activities. No radiological concerns were identified during a facility tour and observation of work in progress.
2.0 Exit Meeting Summary
The inspectors presented the inspection results to licensee management at the conclusion of the onsite inspection on August 28, 2008. The licensee acknowledged the findings presented.
ATTACHMENT: SUPPLEMENTAL INFORMATION
1 A List of acronyms used in the report is included at the end of the Report Details.
Attachment
SUPPLEMENTAL INFORMATION
PARTIAL LIST OF PERSONS CONTACTED
Licensee
- C. Becker, Decommissioning Reactor Manager
- Indicates presence at the exit meeting held on August 28, 2008.
INSPECTION PROCEDURES USED
IP 69013 Research and Test Reactor Decommissioning
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened None
Closed None
Discussed None
LIST OF ACRONYMS USED
DNMS Division of Nuclear Material Safety NRC
Nuclear Regulatory Commission
DOCUMENTS REVIEWED
Documents used during the inspection were specifically identified in the Report Details, above.