07-15-2016 | On May 17, 2016, at 1630 hours0.0189 days <br />0.453 hours <br />0.0027 weeks <br />6.20215e-4 months <br /> while restoring from a plant modification related to installation of new protective relays designed to detect open phase conditions on the 6.9kV shutdown boards, the feeder breakers for the 6.9kV Shutdown Board 1B-B tripped resulting in a loss of bus voltage. The feeder breakers tripped due to actuation of the loss of voltage relays in the shutdown board protective relay trip logic circuit resulting in separation of offsite power from the 6.9kV Shutdown Board 1B-B. The 1B-B emergency diesel generator did not auto start during this event because it was out of service due to planned maintenance.
In response to the loss of power on the 6.9kV Shutdown Board 1B-B, the operators immediately entered Abnormal Operating Instruction, 0-A01-43.02, Loss of Unit 1 Train B Shutdown Boards, and manually started emergency diesel generators 1A-A, 2A-A, and 2B-B. All equipment operated properly. The emergency diesel generators were not required to be paralleled to their respective boards because offsite power was available.
Offsite power was restored to the 6.9kV Shutdown Board 1B-B at 1802 hours0.0209 days <br />0.501 hours <br />0.00298 weeks <br />6.85661e-4 months <br /> on May 17, 2016. Event Notification 51940 was issued May 17, 2016. This event is being reported pursuant to 10 CFR 50.73(a)(2)(iv)(A). |
---|
|
---|
Category:Letter
MONTHYEARML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML24008A2462024-01-18018 January 2024 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) ML23346A1382024-01-0303 January 2024 Regulatory Audit Summary Related to Request to Increase the Number of Tritium Producing Burnable Absorber Rods CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20234412023-12-21021 December 2023 Plantfinal Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) IR 05000390/20234042023-12-14014 December 2023 Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) ML23293A0572023-12-0606 December 2023 Issuance of Amendment Nos. 163 and 70 Regarding Adoption of TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23312A1432023-11-0808 November 2023 Submittal of Dual Unit Updated Final Safety Analysis Report (UFSAR) Amendment 5 CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23251A2002023-09-11011 September 2023 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Units 1 and 2 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 ML23233A0042023-08-28028 August 2023 Proposed Alternative to the Requirements of the ASME Boiler and Pressure Vessel Code for Upper Head Injection Dissimilar Metal Butt Welds IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 CNL-23-045, License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010)2023-08-0707 August 2023 License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010) CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06)2023-06-28028 June 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . ML23122A2322023-06-0707 June 2023 Issuance of Amendment Nos. 162 and 69 Regarding Change to Date in Footnotes for Technical Specification 3.7.11, Control Room Emergency Air Temperature Control System (Creatcs) CNL-23-044, Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out2023-06-0101 June 2023 Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 ML23131A1812023-05-23023 May 2023 Correction to Amendment No. 161 to Facility Operating License No. NPF-90 CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 ML23125A2202023-05-0505 May 2023 Issuance of Amendment No. 161 Regarding a Change to Footnotes for Technical Specification Table 1.1-1 Modes (Emergency Circumstances) IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 CNL-23-043, Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09)2023-05-0404 May 2023 Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09) CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23072A0652023-04-0505 April 2023 Units 1 and 2 Issuance of Amendment Nos. 364 and 358; 160 and 68 Regarding a Revision to Technical Specification 3.4.12 ML23073A2762023-04-0303 April 2023 Individual Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing (EPID L-2023-LLA-0029) (Letter) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report 2024-01-09
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000391/LER-2017-0052018-01-25025 January 2018 Unplanned Emergency Core Cooling System Injection into the Reactor Coolant System due to Personnel Error, LER 17-005-00 for Watts Bar, Unit 2, Regarding Unplanned Emergency Core Cooling System Injection into the Reactor Coolant System due to Personnel Error 05000390/LER-2017-0152018-01-0808 January 2018 Failure to Enter Limiting Condition of Operation Action Statement Results in a Condition Prohibited by Technical Specifications, LER 17-015-00 for Watts Bar, Units 1 and 2, Regarding Failure to Enter Limiting Condition of Operation Action Statement Results in a Condition Prohibited by Technical Specifications 05000390/LER-2017-0142017-12-20020 December 2017 Main Control Room Boundary Door Left Open Leading to a Loss of Safety Function, LER 17-014-00 for Watts Bar, Unit 1, Regarding Main Control Room Boundary Door Left Open Leading to a Loss of Safety Function 05000390/LER-2017-0122017-10-23023 October 2017 Error in Plant Emergency Procedures Leads to a Condition Prohibited by the Technical Specifications, LER 17-012-00 for Watts Bar, Unit 1, Regarding Error in Plant Emergency Procedures Leads to a Condition Prohibited by the Technical Specifications 05000390/LER-2017-0112017-10-23023 October 2017 Failure to Enter Technical Specification 3.6.3 for Containment Isolation Valve, LER 17-011-00 for Watts Bar, Unit 1, Regarding Failure to Enter Technical Specification 3.6.3 for Containment lsolation Valve 05000390/LER-2017-0102017-10-10010 October 2017 Actuation of Turbine Driven Auxiliary Feedwater Pump Due to Loss of 6.9kV Shutdown Board, LER 17-010-00 for Watts Bar Nuclear Plant, Unit 1 Regarding Actuation of Turbine Driven Auxiliary Feedwater Pump Due to Loss of 6.9kV Shutdown Board 05000391/LER-2017-0042017-09-25025 September 2017 Manual Reactor Trip Due to Inoperable Rod Position Indication, LER 17-004-00 for Watts Bar Nuclear Plant, Unit 2 Regarding Manual Reactor Trip Due to Inoperable Rod Position Indication 05000390/LER-2017-0042017-08-31031 August 2017 Manual Reactor Trips Due to Failed Reactor Coolant Pump Power Transfer During Plant Startup, LER 17-004-01 for Watts Bar, Unit 1, Regarding Manual Reactor Trips Due to Failed Reactor Coolant Pump Power Transfer During Plant Startup 05000390/LER-2017-0082017-08-14014 August 2017 Shield Building Inoperability and Potential Loss of Safety Function Resulting from Spurious Equipment Operation, LER 17-008-00 for Watts Bar, Unit 1, Regarding Shield Building Inoperability and Potential Loss of Safety Function Resulting from Spurious Equipment Operation 05000390/LER-2017-0072017-08-0808 August 2017 Multiple Unreported Potential Loss of Safety Function Events Associated with Inoperable Single Train Systems Due to Misinterpretation of Reporting Guidance, LER 17-007-00 for Watts Bar, Unit 1, Regarding Multiple Unreported Potential Loss of Safety Function Events Associated with Inoperable Single Train Systems Due to Misinterpretation of Reporting Guidance 05000390/LER-2017-0062017-07-31031 July 2017 Structural Degradation of 161 kV Line Pole Leads to a Condition Prohibited by Technical Specifications, LER 17-006-00 for Watts Bar, Unit 1, Regarding Structural Degradation of 161 kV Line Pole Leads to a Condition Prohibited by Technical Specifications 05000390/LER-2017-0052017-07-10010 July 2017 Isolation of the 1 B-B Safety Injection Pump Leads to Condition Prohibited by Technical Specifications, LER 17-005-00 for Watts Bar re Isolation of the 1B-B Safety Injection Pump Leads to a Condition Prohibited by Technical Specifications 05000391/LER-2017-0032017-05-22022 May 2017 Automatic Start of Auxiliary Feedwater System Due to Main Condenser Failure, LER 17-003-00 for Watts Bar, Unit 2, Regarding Automatic Start of Auxiliary Feedwater System Due to Main Condenser Failure 05000391/LER-2017-0022017-05-12012 May 2017 Manual Reactor Trip as a Result of a Secondary Plant Transient, LER 17-002-00 for Watts Bar, Unit 2, Regarding Manual Reactor Trip as a Result of a Secondary Plant Transient 05000391/LER-2017-0012017-05-0303 May 2017 Containment Airlock Function Lost Due to Equalizing Valve Not Closing, LER 17-001-00 for Watts Bar, Unit 2, Regarding Containment Airlock Function Lost Due to Equalizing Valve Not Closing 05000390/LER-2017-0032017-03-0303 March 2017 Inadequate Operability Determination Leads to a Condition Prohibited by the Technical Specifications, LER 17-003-00 for Watts Bar, Unit 1, Regarding Inadequate Operability Determination Leads to a Condition Prohibited by the Technical Specifications 05000390/LER-2017-0022017-02-22022 February 2017 Incorrectly Hung Clearance Leads to a Condition Prohibited by the Technical Specifications, LER 17-002-00 for Watts Bar Nuclear Plant, Unit 1, Regarding: Incorrectly Hung Clearance Leads to a Condition Prohibited by the Technical Specifications 05000390/LER-2016-0112016-12-0909 December 2016 Loss of Centrifugal Charging Pump Due to Repeat Failure of Associated Room Cooler, LER 16-011-01 for Watts Bar Nuclear Plant, Unit 1 Regarding Loss of Centrifugal Charging Pump Due to Repeat Failure of Associated Room Cooler 05000391/LER-2016-0082016-10-28028 October 2016 Reactor Trip Resulting from Failure of 2B Main Bank Transformer, LER 16-008-00 for Watts Bar, Unit 2, Regarding Reactor Trip Resulting from Failure of 2B Main Bank Transformer 05000391/LER-2016-0052016-08-19019 August 2016 Main Feedwater Pump Trip on Loss of Condenser Vacuum Leads to Turbine Trip and Reactor Trip, LER 16-005-00 for Watts Bar, Unit 2, Regarding Main Feedwater Pump Trip on Loss of Condenser Vacuum Leads to Turbine Trip and Reactor Trip 05000390/LER-2016-0102016-08-0808 August 2016 Emergency Diesel Generator Crankcase Pressure Switches Not Analyzed to Withstand the Effects of a Tornado, LER-16-010-00 for Watts Bar Nuclear Plant, Units 1 and 2 Regarding Emergency Diesel Generator Crankcase Pressure Switches Not Analyzed to Withstand the Effects of a Tornado 05000391/LER-2016-0042016-08-0404 August 2016 Reactor Trip and Safety Injection Actuation Caused by Turbine Governor Valve Failure, LER 16-004-00 for Watts Bar, Unit 2, Regarding Reactor Trip and Safety Injection Actuation Caused by Turbine Governor Valve Failure 05000391/LER-2016-0032016-07-27027 July 2016 Turbine Driven Auxiliary Feedwater Pump Inoperable for Longer than Allowable Outage Time due to Governor Valve Spring Over-Tensioning, LER 16-003-00 for Watts Bar, Unit 2, Regarding Turbine Driven Auxiliary Feedwater Pump lnoperable for Longer Than Allowable Outage Time Due to Governor Valve Spring Over-Tensioning 05000390/LER-2016-0082016-07-15015 July 2016 Emergency Diesel Generator Manual Start Due to Loss of Voltage on the 6.9kV Shutdown Board 1B-B, LER 16-008-00 for Watts Bar, Unit 1, Regarding Emergency Diesel Generator Manual Start Due to Loss of Voltage on the 6.9kV Shutdown Board 1B-B 05000390/LER-2016-0092016-07-15015 July 2016 Failure to Complete Surveillance Requirements Causes a Condition Prohibited by the Technical Specifications, LER 16-009-00 for Watts Bar, Unit 1, Regarding Failure to Complete Surveillance Requirements Causes Conditions Prohibited by the Technical Specifications 05000391/LER-2016-0022016-07-11011 July 2016 Turbine Driven Auxiliary Feedwater Pump Inoperable for Longer than Allowable Outage Time due to Turbine Speed Control Failure, LER 16-002-00 for Watts Bar, Unit 2, Regarding Turbine Driven Auxiliary Feedwater Pump Inoperable for Longer Than Allowable Outage Time Due to Turbine Speed Control Failure 05000390/LER-2016-0062016-06-30030 June 2016 Undersized Room Cooler Fan Shaft Results in Loss of Centrifugal Charging Pump, LER 16-006-00 for Watts Bar, Unit 1, Regarding Undersized Room Cooler Fan Shaft Results in Loss of Centrifugal Charging Pump 05000390/LER-2016-0072016-06-20020 June 2016 Technical Specification Action Not Met for Rod Position Indication, LER 16-007-00 for Watts Bar Nuclear Plant, Unit 1 Regarding Technical Specification Action Not Met for Rod Position Indication 05000391/LER-2016-0012016-06-13013 June 2016 Loss of Automatic Containment Isolation for the Steam Generator Blowdown Sampling Lines, LER 16-001-00 for Watts Bar, Unit 2, Regarding Loss of Automatic Containment Isolation for the Steam Generator Blowdown Sampling Lines 05000390/LER-2016-0042016-05-23023 May 2016 Automatic Reactor Trip Due to Actuation of Over Temperature Delta Temperature Bistables, LER 16-004-00 for Watts Bar, Unit 1, Regarding Automatic Reactor Trip Due to Actuation of Over Temperature Delta Temperature Bistables 05000390/LER-2016-0052016-05-13013 May 2016 Both Trains of Unit 1 Emergency Gas Treatment System Inoperable During Unit 2 Testing, LER 16-005-00 for Watts Bar, Unit 1, Regarding Both Trains of Unit 1, Emergency Gas Treatment System Inoperable During Unit 2, Testing 05000390/LER-2016-0032016-05-10010 May 2016 Technical Specification Surveillance Requirement Not Met During Emergency Core Cooling System Venting, LER 16-003-00 for Watts Bar, Unit 1, Regarding Technical Specification Surveillance Requirement Not Met During Emergency Core Cooling System Venting 05000390/LER-2016-0022016-05-0404 May 2016 Technical Specification Action Not Met for Inoperable Containment Isolation Valve, LER 16-002-00 for Watts Bar, Unit 1, Regarding Technical Specification Action Not Met for Inoperable Containment Isolation Valve 05000390/LER-2016-0012016-03-0909 March 2016 Channel Mode Switch in Incorrect Position Renders Lower Containment Atmosphere Particulate Radiation Monitor Inoperable, LER 16-001-00 for Watts Bar, Unit 1, Regarding Channel Mode Switch in Incorrect Position Renders Lower Containment Atmosphere Particulate Radiation Monitor Inoperable ML1134703432011-12-13013 December 2011 Withdrawal of License Event Report 390/2011-003, Mode Change Without Meeting Limiting Condition for Operation (LCO) 3.7.5 2018-01-08
[Table view] |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
I. PLANT OPERATING CONDITIONS BEFORE THE EVENT
Watts Bar Nuclear Plant (WBN) Unit 1 was in Mode 1 at 100 percent rated thermal power. Unit 2 was in Mode 3 at zero percent rated thermal power.
II. DESCRIPTION OF EVENT
A. Event
On May 17, 2016, a clearance was issued in preparation of installing new protective relays designed to detect open phase (OP) conditions on the 6.9 kV Shutdown Board 1B-B {EIIS:BU}, which is part of the on- site electrical distribution system [EllS:EA}. The work scope required that the OP relays {EIIS:46} be tied in parallel with the existing loss of voltage (LOV), degraded voltage (DV), and overvoltage (OV) relays. The OP relays, including the LOV, DV, and the OV relays are electronic relays that sense the 3 phase 6.9kV bus voltage through a common step down potential transformer (PT). The electronic relays require dc power to operate. This power is provided by the vital dc control circuit which is the same power supply that is used to energize the protective relay trip logic circuit for the 6.9kV Shutdown Board 1B-B.
Upon completion of work, the 6.9kV Shutdown Board 1B-B clearance was approved for removal. During restoration of dc control power, it was noted that the B-phase relays for the LOV (phase B-C), DV (phase B- C) and OV (phase A-C), did not reset while the other relays did. After trouble shooting, the decision was made to pull PK Test Block 1-PK-211-B17/4 to isolate the ac sensing voltage from the newly installed OP relays and eliminate any associated wiring as a possible cause for inability to reset the above relays. The PK test block is an isolation device for disconnecting the new OP relays from the PT secondary circuit.
Upon removal of the PK test block at 1630, the 6.9kV Shutdown Board 1B-B immediately de-energized.
The loss of power was caused by the LOV relays that initiate the trip sequence to separate offsite power from the 6.9kV Shutdown Board. The 1B-B emergency diesel generator (EDG) did not auto start during this event because it was out of service due to planned maintenance.
In response to the loss of power on the 6.9kV Shutdown Board 1B-B, the operators immediately entered Technical Specifications (TS) Limiting Condition of Operation (LCO) 3.8.9, Distribution System - Operating, Action Condition A. The operators also entered Abnormal Operating Instruction, 0-A0143.02, Loss of Unit 1 Train B Shutdown Boards, and manually started EDGs 1A-A, 2A-A, and 2B-B. All equipment operated properly. The EDGs were not required to be paralleled to the boards because offsite power was available.
Offsite power was restored to the 6.9kV Shutdown Board 1B-B at 1802 hours0.0209 days <br />0.501 hours <br />0.00298 weeks <br />6.85661e-4 months <br /> on May 17, 2016.
This event is being reported pursuant to 10 CFR 50.73(a)(2)(iv)(A),for any event or condition that resulted in manual or automatic actuation of the emergency ac electrical power system as listed in 10 CFR 50.73(a)(2)(iv)(B), paragraph (8).
B. Inoperable Structures, Components, or Systems that Contributed to the Event There were no additional structures, components or systems that contributed to this event.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
CONTINUATION SHEET
3. LER NUMBER
Watts Bar Nuclear Plant, Units 1 and 2 05000390 2016 008 - 00 C. Dates and Approximate Times of Occurrences Date Time (EDT) Event 05/17/16 1428 Clearance lifted to allow restoring protective relays to service.
05/17/16 1630 Loss of 6.9kV Shutdown Bd. 1B-B.
05/17/16 1630 Entered TS LCO 3.8.9, Action Condition A, One or more AC electrical power distribution subsystems inoperable.
05/17/16 1630 Entered 0-A01-43.02, Loss of Unit 1 train B Shutdown Boards.
05/17/16 1630 Manually started EDGs 1A-A, 2A-A and 2B-B.
05/17/16 1630 Entered TS LCO 3.8.4, Action Condition A, One vital DC electrical subsystem inoperable.
05/17/16 1630 Entered TS LCO 3.7.11, Action Condition A, One CREATCS train inoperable.
05/17/16 1632 Entered TS LCO 3.7.8, Action Condition A, One ERCW train inoperable.
05/17/16 1802 Offsite power restored to 6.9kV Shutdown Bd. 1B-B.
D. Manufacturer and Model Number of Components that Failed There were no component failures.
E. Other Systems or Secondary Functions Affected
No other systems or functions were affected.
F. Method of discovery of each Component or System Failure or Procedural Error The event was self-evident at the time the 6.9kV Shutdown Board 1B-B lost power.
G. Failure Mode and Effect of Each Failed Component During restoration of dc control power, it was noted that the B-phase relays for the LOV (phase B-C), DV (phase B-C) and OV (phase A-C), did not reset while the other relays did. After trouble shooting, the decision was made to pull PK Test Block 1-PK-211-B17/4 to isolate the ac sensing voltage from the newly installed OP relays and eliminate any associated wiring as a possible cause for inability to reset the above relays. This action created a voltage transient on the PT secondary that caused the remaining LOV relays to trip. Once the protective relay trip logic for the LOV relays was satisfied the 6.9kV Shutdown Board 1B-B tripped isolating the bus from offsite power. This event was attributed to vulnerabilities in board restoration procedures due to reliance on the same dc control power fuses to isolate control power to both the sensing relays and the protective relay trip logic circuit.
H. Operator Actions
1. Operators entered TS LCO 3.8.9, Distribution System, Condition A, One or more AC electrical power distribution subsystems inoperable, for Units 1 and 2 with a Completion Time of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Watts Bar Nuclear Plant, Units 1 and 2
3. LER NUMBER
2016 - 00 2. Operators entered Abnormal Operating Instruction, 0-A01-43.02, Loss of Unit 1 Train B Shutdown Boards, and manually started EDGs 1A-A, 2A-A, and 2B-B. All equipment operated properly. The EDGs were not required to be paralleled to the boards because offsite power was available.
3. Operators entered TS 3.8.4, Condition A, One vital DC electrical subsystem inoperable, for Units 1 and 2 due to Battery Board II voltage below 128VDC following loss of power. Operators transferred Battery Charger II normal power supply to the alternate supply within the required 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Completion Time.
4. Operators entered TS 3.7.11, Condition A, One CREATCS train inoperable for Units 1 and 2. Entry was due to high oil temperature alarm on the B-train Main Control Room (MCR) Chiller following loss of power. Operators transferred control room cooling functions to the A-train MCR Chiller.
5. Operators entered TS 3.7.8, Condition A, One ERCW train inoperable for Units 1 and 2. Operators place B-train ERCW pumps E-B and G-B in the Stop Pull to Lock Position following loss of power to the 6.9kV Shutdown Bd. 1B-B. However, B-train ERCW pumps F-B and H-B were available because these pumps are powered by the 6.9kV Shutdown Bd. 2B-B which did not lose offsite power and the EDG 2B-B was operable.
III. CAUSE OF THE EVENT
A. The cause of each component or system failure or personnel error, if known.
There was no component or system failure or personnel error.
B. The cause(s) and circumstances for each human performance related root cause.
The cause was attributed to inadequate restoration procedures due to reliance on the same dc control power fuses to isolate control power to both the sensing relays and the protective relay trip logic circuit.
IV. ANALYSIS OF THE EVENT
As described in Section II.G, the LOV relays initiated the trip sequence to separate the offsite power circuits from the 6.9kV Shutdown Board 1B-B due to cycling dc and ac sensing voltage to the protective relays.
When dc control power was restored, the B-phase LOV, DV, and OV relays were in the tripped state with the protective relay trip logic circuit enabled. When the PK test block was pulled during trouble shooting to remove the ac sensing voltage to the OP relays it created a voltage transient on the PT secondary circuit which caused the remaining LOV relays to trip. Once the 2 out of 3 trip logic for the LOV relays was satisfied the feeder breakers to the 6.9kV Shutdown Board 1B-B tripped isolating the bus from offsite power.
Based on discussion with the relay vendor the preferred sequence for restoring dc control power for the protective relays is to remove PK Test Block 1-PK-211-B7/7 from the protective relay trip logic circuit, restore dc control power (i.e., install dc control fuses), and then a final step to restore ac sensing voltage (i.e., install PT primary fuses). The above PK test block should not be reinstalled until all protective relays are verified reset (i.e., not tripped).
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Watts Bar Nuclear Plant, Units 1 and 2
3. LER NUMBER
2016 - 00
V. ASSESSMENT OF SAFETY CONSEQUENCES
A. Availability of systems or components that could have performed the same function as the components and systems that failed during the event.
The design bases for the 6.9kV shutdown boards are that two shutdown boards within the same load group must be available to mitigate an accident on one unit and maintain the other non-accident unit in hot standby (Mode 3). There are two load groups A and B. Load group A is supported by 6.9kV Shutdown Boards 1A-A and 2A-A. Load group B is supported by 6.9kV Shutdown Boards 1B-B and 2B-B. Since a minimum of one load group (i.e., Shutdown Board 1A-A and 2A-A) was Operable, the design bases as defined in Chapters 8 and 15 of the Updated Final Safety Analysis Report (UFSAR) for the 6.9kV Shutdown Boards were met.
B. For events that occurred when the reactor was shut down, availability of systems or components needed to shutdown the reactor and maintain safe shutdown conditions, remove residual heat, control the release of radioactive material, or mitigate the consequences of an accident Not applicable. At the time of event WBN Unit 1 was in Mode 1 at 100 percent rated thermal power.
WBN Unit 2 was in Mode 3.
C. For failure that rendered a train of a safety system inoperable, an estimate of the elapsed time from the discovery of the failure until the train was returned to service.
The 6.9kV Shutdown Board 1B-B was inoperable for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and 32 minutes before offsite power was restored.
VI. CORRECTIVE ACTIONS
This event was entered into the Tennessee Valley Authority Corrective Action Program and is being tracked under Condition Report (CR) 1172243.
A. Immediate Corrective Actions
Operators entered Abnormal Operating Instruction, 0-A01-43.02, Loss of Unit 1 Train B Shutdown Boards, and manually started EDGs 1A-A, 2A-A, and 2B-B. All equipment operated properly. The EDGs were not required to be paralleled to their respective shutdown boards because offsite power was available.
B. Corrective Actions to Prevent Recurrence
WBN will revise General Operating Instruction 0-001-7, Generic Equipment Operating Guidelines, to include general guidance for disabling and restoring the 6.9kV protective relay trip logic circuits.
VII. ADDITIONAL INFORMATION
A. Previous similar events at the same plant comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Watts Bar Nuclear Plant, Units 1 and 2
3. LER NUMBER
2016 - 00 No previous similar events have occurred because the protective relays are not normally de-energized for any preventative maintenance. The configuration of de-energizing the relays was a requirement for installing the new open phase relays.
B. Additional Information
None.
C. Safety System Functional Failure Consideration
This event did not result in a safety system functional failure because as a minimum load group A (i.e., Shutdown Board 1A-A and 2A-A) were available to mitigate the design bases events described in the UFSAR for either Unit 1 or 2.
D. Scrams with Complications Consideration There was no scram associated with this event.
VIII. COMMITMENTS
None.
|
---|
|
|
| | Reporting criterion |
---|
05000390/LER-2016-010 | Emergency Diesel Generator Crankcase Pressure Switches Not Analyzed to Withstand the Effects of a Tornado LER-16-010-00 for Watts Bar Nuclear Plant, Units 1 and 2 Regarding Emergency Diesel Generator Crankcase Pressure Switches Not Analyzed to Withstand the Effects of a Tornado | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000390/LER-2016-001 | Channel Mode Switch in Incorrect Position Renders Lower Containment Atmosphere Particulate Radiation Monitor Inoperable LER 16-001-00 for Watts Bar, Unit 1, Regarding Channel Mode Switch in Incorrect Position Renders Lower Containment Atmosphere Particulate Radiation Monitor Inoperable | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000390/LER-2016-011 | Loss of Centrifugal Charging Pump Due to Repeat Failure of Associated Room Cooler LER 16-011-01 for Watts Bar Nuclear Plant, Unit 1 Regarding Loss of Centrifugal Charging Pump Due to Repeat Failure of Associated Room Cooler | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000391/LER-2016-001 | Loss of Automatic Containment Isolation for the Steam Generator Blowdown Sampling Lines LER 16-001-00 for Watts Bar, Unit 2, Regarding Loss of Automatic Containment Isolation for the Steam Generator Blowdown Sampling Lines | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000391/LER-2016-002 | Turbine Driven Auxiliary Feedwater Pump Inoperable for Longer than Allowable Outage Time due to Turbine Speed Control Failure LER 16-002-00 for Watts Bar, Unit 2, Regarding Turbine Driven Auxiliary Feedwater Pump Inoperable for Longer Than Allowable Outage Time Due to Turbine Speed Control Failure | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000390/LER-2016-002 | Technical Specification Action Not Met for Inoperable Containment Isolation Valve LER 16-002-00 for Watts Bar, Unit 1, Regarding Technical Specification Action Not Met for Inoperable Containment Isolation Valve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000391/LER-2016-003 | Turbine Driven Auxiliary Feedwater Pump Inoperable for Longer than Allowable Outage Time due to Governor Valve Spring Over-Tensioning LER 16-003-00 for Watts Bar, Unit 2, Regarding Turbine Driven Auxiliary Feedwater Pump lnoperable for Longer Than Allowable Outage Time Due to Governor Valve Spring Over-Tensioning | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000390/LER-2016-003 | Technical Specification Surveillance Requirement Not Met During Emergency Core Cooling System Venting LER 16-003-00 for Watts Bar, Unit 1, Regarding Technical Specification Surveillance Requirement Not Met During Emergency Core Cooling System Venting | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000391/LER-2016-004 | Reactor Trip and Safety Injection Actuation Caused by Turbine Governor Valve Failure LER 16-004-00 for Watts Bar, Unit 2, Regarding Reactor Trip and Safety Injection Actuation Caused by Turbine Governor Valve Failure | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000390/LER-2016-004 | Automatic Reactor Trip Due to Actuation of Over Temperature Delta Temperature Bistables LER 16-004-00 for Watts Bar, Unit 1, Regarding Automatic Reactor Trip Due to Actuation of Over Temperature Delta Temperature Bistables | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000391/LER-2016-005 | Main Feedwater Pump Trip on Loss of Condenser Vacuum Leads to Turbine Trip and Reactor Trip LER 16-005-00 for Watts Bar, Unit 2, Regarding Main Feedwater Pump Trip on Loss of Condenser Vacuum Leads to Turbine Trip and Reactor Trip | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000390/LER-2016-005 | Both Trains of Unit 1 Emergency Gas Treatment System Inoperable During Unit 2 Testing LER 16-005-00 for Watts Bar, Unit 1, Regarding Both Trains of Unit 1, Emergency Gas Treatment System Inoperable During Unit 2, Testing | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000391/LER-2016-006 | Turbine Driven Auxiliary Feedwater Pump Auto Start on Lo-Lo Steam Generator Level Following Planned Unit Trip | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000390/LER-2016-006 | Undersized Room Cooler Fan Shaft Results in Loss of Centrifugal Charging Pump LER 16-006-00 for Watts Bar, Unit 1, Regarding Undersized Room Cooler Fan Shaft Results in Loss of Centrifugal Charging Pump | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000391/LER-2016-007 | Manual Reactor Trip Due to Loss of Main Feedwater | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000390/LER-2016-007 | Technical Specification Action Not Met for Rod Position Indication LER 16-007-00 for Watts Bar Nuclear Plant, Unit 1 Regarding Technical Specification Action Not Met for Rod Position Indication | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000390/LER-2016-008 | Emergency Diesel Generator Manual Start Due to Loss of Voltage on the 6.9kV Shutdown Board 1B-B LER 16-008-00 for Watts Bar, Unit 1, Regarding Emergency Diesel Generator Manual Start Due to Loss of Voltage on the 6.9kV Shutdown Board 1B-B | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000391/LER-2016-008 | Reactor Trip Resulting from Failure of 2B Main Bank Transformer LER 16-008-00 for Watts Bar, Unit 2, Regarding Reactor Trip Resulting from Failure of 2B Main Bank Transformer | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000390/LER-2016-009 | Failure to Complete Surveillance Requirements Causes a Condition Prohibited by the Technical Specifications LER 16-009-00 for Watts Bar, Unit 1, Regarding Failure to Complete Surveillance Requirements Causes Conditions Prohibited by the Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|