Schedule and Response to PSEG Letter (LR-N07-0274) Dated October 23, 2007, Plans Related to Steam Dryer Evaluation Regarding Request for Extended Power Uprate
ML073300453
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 11/27/2003
From: John Lamb
NRC/NRR/ADRO/DORL/LPLI-2
To: Levis W
Public Service Enterprise Group
Lamb John G./NRR/DORL, 415-3100
References
LR-N07-0274, TAC MD3002
Download: ML073300453 (5)


Text

November 27, 2007 Mr. William Levis President and Chief Nuclear Officer PSEG Nuclear LLC-N09 Post Office Box 236 Hancocks Bridge, NJ 08038

SUBJECT:

HOPE CREEK GENERATING STATION - SCHEDULE AND RESPONSE TO PSEG LETTER (LR-N07-0274) DATED OCTOBER 23, 2007, PLANS RELATED TO STEAM DRYER EVALUATION REGARDING REQUEST FOR EXTENDED POWER UPRATE (TAC NO. MD3002)

Dear Mr. Levis:

By letter dated September 18, 2006, as supplemented on October 10 and October 20, 2006, February 14, February 16, February 28, March 13, April 18, April 30, May 10, May 18, June 22, August 3, August 17, August 31, September 11, October 10, October 23, and November 15, 2007, PSEG Nuclear, LLC (PSEG or licensee) submitted an amendment request for an extended power uprate (EPU) for Hope Creek Generating Station (Hope Creek). The proposed amendment would increase the authorized maximum power level by approximately 15 percent, from 3339 megawatts thermal (MWt) to 3840 MWt.

In PSEG letter (LR-N07-0274) to the U.S. Nuclear Regulatory Commission (NRC), dated October 23, 2007, PSEG submitted its plans related to the steam dryer evaluation for the proposed Hope Creek EPU. In the attachment to the PSEG letter (LR-N07-0274), PSEG documented its understanding of the key issues discussed at the closed meeting held on October 11, 2007, and PSEGs plans for additional steam dryer analysis and testing. PSEG plans to respond to the request for additional information questions by November 30, 2007. To account for bias and uncertainty in frequency response function amplitudes predicted by the finite element model for the Hope Creek steam dryer, PSEG plans to test a previously purchased, spare steam dryer and PSEG will be prepared to supply the results of the shaker table testing to the NRC staff by December 31, 2007.

The NRC staff agrees with your understanding of the key issues as documented in the PSEG letter (LR-N07-0274), dated October 23, 2007. Even though the NRC staff agrees with your understanding of the key issues, there is the possibility of additional questions, concerns, or issues resulting from your responses. Please note that the NRC staff assumes that your responses will be comprehensive and of high quality, and all questions will be answered to the NRC staffs technical satisfaction.

W. Levis Please note that at this time, the NRC staffs projected schedule for dispositioning the proposed Hope Creek EPU is June 2008. If you have any questions, I can be reached at (301) 415-3100.

Sincerely,

/ra/

John G. Lamb, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-354 cc: See next page

ML073300453 OFFICE LPL1-2/PM LPL1-2/LA LPL1-2/BC NAME JLamb ABaxter HChernoff DATE 11/27/07 11/27/07 11/27/07 Hope Creek Generating Station cc:

Mr. Thomas Joyce Mr. Paul Bauldauf, P.E., Asst. Director Senior Vice President - Operations Radiation Protection Programs PSEG Nuclear NJ Department of Environmental P.O. Box 236 Protection and Energy Hancocks Bridge, NJ 08038 CN 415 Trenton, NJ 08625-0415 Mr. Dennis Winchester Vice President - Nuclear Assessment Mr. Brian Beam PSEG Nuclear Board of Public Utilities P.O. Box 236 2 Gateway Center, Tenth Floor Hancocks Bridge, NJ 08038 Newark, NJ 07102 Mr. Carl Fricker Regional Administrator, Region I Vice President - Operations Support U.S. Nuclear Regulatory Commission PSEG Nuclear 475 Allendale Road P.O. Box 236 King of Prussia, PA 19406 Hancocks Bridge, NJ 08038 Senior Resident Inspector Mr. John Perry Hope Creek Generating Station Plant Manager - Hope Creek U.S. Nuclear Regulatory Commission PSEG Nuclear Drawer 0509 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. William Levis Mr. James Mallon President & Chief Nuclear Officer Manager - Licensing PSEG Nuclear LLC - N09 PSEG Nuclear P.O. Box 236 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Jeffrie J. Keenan, Esquire PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Michael Gaffney Manager - Hope Creek Regulatory Assurance PSEG Nuclear P.O. Box 236 Hancocks Bridge, NJ 08038 Township Clerk Lower Alloways Creek Township Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038