" " December 22, 2008

James Vice President Operations Entergy Operations, Inc. Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150

SUBJECT: GRAND GULF NUCLEAR STATION- NRC SECURITY TEAM INSPECTION REPORT 05000416/2008402

Dear Mr. Douet:

On December 4, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Grand Gulf Nuclear Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on December 4, 2008, with Mr. M. Krupa, Director, Nuclear Safety Assurance, and other members of your staff.

This inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

This report documents one finding of very low security significance (i.e. Green as determined by the Physical Protection Significance Determination Process). This finding was determined to involve a violation of NRC requirements. The deficiency was promptly corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspectors left the site. Additionally, a licensee-identified violation which was determined to be of very low security Entergy Operations, Inc. - 2 - significance is listed in this report. However, because of the very low security significance and because they are entered into your corrective action program, the NRC is treating these violations as non-cited violations consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator Region IV; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Grand Gulf Nuclear Station Plant.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response, "Security-Related Information-Withhold Under 10 CFR 2.390," and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Sincerely,/RA/ Michael P. Shannon, Chief Plant Support Branch - 1 Division of Reactor Safety Dockets: 50-416 Licenses: NPF-29

Nonpublic

Enclosure:

Inspection Report 05000416/2008402

w/Attachment:

Supplemental Information Entergy Operations, Inc. - 3 - cc w/o enclosure: Senior Vice President Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Senior Vice President and COO Entergy Operations, Inc. P.O. Box 31995 Jackson, MS 39286-1995 Vice President, Oversight Entergy Services, Inc. P.O. Box 31995 Jackson, MS 39286-1995

Senior Manager Nuclear Safety & Licensing Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995 Manager, Licensing Entergy Operations, Inc. Grand Gulf Nuclear station P.O. Box 756 Port Gibson, MS 39150