ML17258A012

From kanterella
Revision as of 13:14, 18 May 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
10/24/2017, Presentation Slide Regarding Committee to Review Generic Requirements Meeting on Oconee Nuclear Station Cable Separation TIA
ML17258A012
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 09/26/2017
From: Benner E J, Lubinski J W
Division of Engineering, Division of Operating Reactor Licensing
To:
Johnston J D
References
Download: ML17258A012 (15)


Text

Committee to Review Generic Requirements Meeting on Oconee Nuclear Station Cable Separation TIASeptember 26, 2017John LubinskiDivision of EngineeringEric BennerDivision of Operating Reactor LicensingOffice of Nuclear Reactor Regulation Agenda*Background*Key CRGR Questions

  • Key Technical and Licensing Issues
  • Path Forward
  • Recommendation2 Background*CDBI at Oconee Nuclear Station (ONS) (7/27/2014) identified an unresolved item (URI) involving the licensing bases for cable configurations in recently installed underground raceways*The URI questioned whether ONS appropriately considered electrical system design requirements and licensing basis when implementing this modification under 50.59.*On October 16, 2014, Region II requested assistance from the Office of Nuclear Reactor Regulation (NRR) to provide answers to questions related to the URI in task interface agreement (TIA) 2014-05. 3 Background*On August 2, 2016, the draft TIA response was sent to Duke Power for a fact check and made publicly available. *As a part of the fact check Duke Power indicated a number of disagreements with NRC interoperation of both technical issues and the ONS licensing basis*Consistent with the recent CRGR recommendations to improve oversight in identifying potential backfitting issues, the proposed TIA response will be issued only after CRGR review4 Background*The non-safety related 13.8 kVacPSW cables were not part of the original licensing basis5Configuration priorto installing cables in common trenchConfigurationafter installing cables in common trenchSafety related 125V DC power/control cables and safety related 120V AC ESPS cables directly buried in ground with 'adequate' separation between the two trainsThe licensee rerouted directly buriedcables to trench # 3 and Manhole6 which included the following safety related and non-safety related cables: Safety related cables:-13.8 kVac Emergency power from KHU to Transformer CT4

-4.16 kVac CX Auxiliary Power from Transformer CT4 switchgear to KHU

-125 Vdc supervisory cables A

-125 Vdc control and power cable for A and B trainsNon-safety related cables:-13.8 kVac PSW Power Cables from KHU to Transformer CT6 and CT7

-13.8 kVac PSW Power Cables from Fant lineBoth trains of ESPS A and B are interconnected at KHSAnd ONS panels -configuration in panels did not change. Adequately separation from power cables (4.16kV and 13.8kV AC) such that a fault in one train would not adversely impact redundant trains (approximately 10 feet apart between redundant trains)Separation between medium voltage and low voltage power/control cables such that a single failure would not adversely impact redundant trainsSafety related 4.16kV and 13.8kV AC power cables directly buried with adequate separationBoth trains of ESPS A and B are interconnected at KHSAnd ONS panels Background6 Background7 Key CRGR Questions*The TIA response:-addresses site-specific licensing basis questions and applies only to ONS-does not communicate a new requirement or staff position

-does not increase, reduce, or modify existing requirements or NRC staff positions-is not a request for information

-is not a backfit*TIA response will support RII office actions to close out existing Unresolved Items.8 Key Technical and Licensing Issues*ONS licensing basis with respect to IEEE Std. 279 *Use of cable shielding vice cable armor

  • Evaluation of timing of single failure is not limited to the event start time*No distinction between passive and active electrical single failures*Treatment of non-safety related cables in the ONS licensing basis9 ONS licensing basis with respect to IEEE Std. 279 *NRC and ONS agree IEEE Std. 279-1968 is the licensing basis*NRC and ONS agree, based on August 5, 1974 Duke letter ("The Oconee ECCS actuation system conforms to the single failure requirements of IEEE 279-1971.") that the single failure requirements of IEEE Std. 279-1971 are the licensing basis.*ONS believes Section 4.2, IEEE Std. 279-1971, is the only section that is part of the licensing basis*NRC believes Sections 4.2, 4.7, 4.11, and 4.17, IEEE Std. 279-1971, are part of the licensing basis.*Even if NRC agreed with ONS on the applicability of IEEE Std. 279-1971 (i.e., only Section 4.2), the conclusions in the TIA regarding single failure would be the same.10 Use of cable shielding vice cable armor*Cable armor is a mechanically strong and flexible sheath which can be applied over a variety of cable cores to protect from failure of nearby cables -ONS licensing basis allows the use of interlocked armor cable to provide mechanical protection -Bronze tape is not equivalent to interlocked armor cable and cannot be credited to prevent consequential damage to nearby cables *Cable shielding of an electric power cable is the practice of confining the electric field of the cable to preclude excessive voltage stress on voids between conductor and insulation -Neither interlocked armor cable nor bronze tape provides cable shielding11 Evaluation of timing of single failure is not limited to the event start time*ONS licensing basis includes the single failure requirements of IEEE Std. 279-1971 and it does not allow restricting the timing of when single failures may occur. *Postulating the single failure immediately on demand of a component to function, the licensee failed to establish the most limiting single failure that could occur, as required12 No distinction between passive and active electrical single failures*ONS UFSAR Section 8.3.1.2, "Analysis," the licensee's current licensing basis, states, in part, that:-The basic design criterion for the electrical portion of the emergency electric power system of a nuclear unit, including the generating sources, distribution system, and controls is that a single failure of any component, passive or active, will not preclude the system from supplying emergency power when required.*NRC's position on the definition of single failure and how single failure was evaluated during the licensing of plants was discussed in SECY-77-439 -Single Failure Criterion to systems evaluation depends not only on the initiating event that invokes safety action of these systems, together with consequential failures, but also on active or passive electrical failures, which can occur independent of the event13 Treatment of non-safety related cables in the ONS licensing basis*Only safety related or Class 1E designated components are credited to mitigate design basis events. The single failure criteria requirements of IEEE Std. 279-1971 apply to Class 1E*The non-safety related power cables in Trench #3 and Manhole #6 are not credited in the ONS licensing basis for mitigating design basis events*However, the license must account for the impacts of worst-case credible failures of non-safety equipment on Class 1E circuits as required by IEEE Std. 279-1968 (Section X)*In addition the interconnected nature of the Class 1E DC systems in the ONS KHU start panels and the Keowee hydro-station KHU start panels present vulnerabilities where DC to DC interactions could disable the Keowee emergency power systems 14 Path Forward*Duke may request a public meeting with CRGR to present their perspectives*After CRGR endorsement, NRR will issue the TIA response to RII and make it available to the public*Region II will conduct exit meeting (addressing URI) with licensee and, as appropriate, will communicate apparent violations to Duke Energy.*Region II will evaluate Oconee's operability determinations for the affected systems and equipment*Region II will disposition the findings in accordance with IMC 0612, conduct appropriate follow-up inspections*The process would allow Duke an opportunity to dispute any violations, including providing any claims of backfitting.15