Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARML22175A0702022-06-24024 June 2022 GNF-A License Amendment Request for 8 Wt. % U 235 (Leu+) Project stage: Request ML22227A0482022-08-15015 August 2022 GNF-A Semi-Annual Effluent Monitoring Report for January-June 2022 Project stage: Request ML22271A9362022-10-0404 October 2022 Requests for Supplemental Information for the Acceptance of Global Nuclear Fuel - Americas License Amendment Request for 8 Weight Percent Uranium-235 Project stage: Acceptance Review ML22278A1552022-10-0505 October 2022 Global Nuclear Fuel -Americas LLC - Response to NRC Environmental Protection Request for Supplemental Information Dated October 4, 2022 Project stage: Request ML22304A6712022-11-0202 November 2022 Acceptance of Global Nuclear Fuel - Americas License Amendment Request for 8 Weight Percent Uranium-235 Project stage: Acceptance Review ML23156A1832023-07-0303 July 2023 Request for Additional Information Regarding GNF-A License Amendment Request for 8 Weight Percent Uranium 235 Project stage: RAI ML23192A5162023-07-11011 July 2023 GNF-A Natrium Fuel Fabrication Facility Schedule Update Project stage: Request ML23209A6762023-07-28028 July 2023 GNF-A Response to NRC Request for Additional Information Project stage: Response to RAI ML23244A1812023-08-30030 August 2023 GNF-A 8 Weight Percent License Amendment Request - Materials Control & Accounting (Mc&A) Request for Additional Information Response Clarification Project stage: Request ML23291A1502023-10-26026 October 2023 GNF-A Environmental Assessment Project stage: Request ML23311A3832023-12-11011 December 2023 Amendment 18 to SNM-1097 (Publicly Available Version) Project stage: Other ML23311A3812023-12-11011 December 2023 Safety Evaluation Report for GNF-A Request for 8 Weight Percent Uranium 235 Project stage: Approval ML23311A3802023-12-11011 December 2023 Cover Letter - Safety Evaluation Report for GNF-A Request for 8 Weight Percent Uranium 235 Project stage: Approval ML23311A3792023-12-11011 December 2023 Amendment 18 and Safety Evaluation Report for GNF-A Request for 8 Weight Percent Uranium 235 Project stage: Request 2023-10-26
[Table View] |
|
---|
Category:Acceptance Review Letter
MONTHYEARML23202A0872023-08-0101 August 2023 Acceptance of GNF-A 2022 Triennial Update to Decommissioning Funding Plan ML22304A6712022-11-0202 November 2022 Acceptance of Global Nuclear Fuel - Americas License Amendment Request for 8 Weight Percent Uranium-235 ML19350B4582020-02-0606 February 2020 NRC Request for Supplemental Information from GNF-A Regarding the License Amendment Request to Increase Enrichment Limits to Less than or Equal to 8 Percent U-235 ML18150A4762018-06-0505 June 2018 GNFA LAR 14 Acceptance Review Transmittal 2023-08-01
[Table view] Category:Letter
MONTHYEARML24296A0712024-10-23023 October 2024 Global Nuclear Fuels - America – Core Inspection Report 07001113-2024003 ML24275A0342024-10-0101 October 2024 GNF-A Emergency Response Telephone Listing Dated 9/27/2024 ML24268A0382024-09-25025 September 2024 Approval Letter of Global Nuclear Fuel - Americas, LLC 2022 Triennial Update to Decommissioning Funding Plan ML24255A8022024-09-11011 September 2024 GNF-A DFP Supplemental Information ML24250A0482024-09-0606 September 2024 Global Nuclear Fuel Americas, LLC (GNF-A) NRC Licensee Contacts ML24240A0702024-08-26026 August 2024 GNF-A Submittal of FOCI Information Update ML24236A0222024-08-22022 August 2024 GNF-A Written Follow-up Report - Fire System Impairment ML24219A2632024-08-0606 August 2024 GNF-A Semi-Annual Effluent Monitoring Report ML24205A1392024-07-25025 July 2024 Global Nuclear Fuels-America - Core Inspection Report 07001113/2024002 ML24184A1262024-07-0202 July 2024 Global Nuclear Fuel - Americas, LLC, Submittal of Response to NRC Request for Additional Information ML24180A0132024-06-28028 June 2024 GNF-A Fundamental Nuclear Material Control Plan ML24176A2742024-06-25025 June 2024 Global Nuclear Fuel – Americas, L.L.C. – Inspection Schedule for Calendar Year 2025 ML24172A0612024-06-20020 June 2024 GNF-A Comments on Buildings as IROFS - Meeting Slides ML24156A2032024-06-0404 June 2024 GNF-A Natrium Fuel Fabrication Facility Pre-Application - Meeting Slides ML24129A1832024-05-21021 May 2024 Global Nuclear Fuel - Americas LLC RAI to Support Review of Global Nuclear Fuel-Americas Updated Fuel Fabrication Facility Decommissioning Funding Plan ML24128A1602024-05-0707 May 2024 Submittal of Revision to GNF-A Radiological Contingency & Emergency Plan (Rc&Ep) ML24121A1652024-04-30030 April 2024 Global Nuclear Fuel - Americas, LLC - Annual Reporting ML24110A0432024-04-23023 April 2024 Global Nuclear Fuel - Americas - Core Inspection Report 07001113/2024001 ML24103A1992024-04-12012 April 2024 Submittal of Revision to GNF-A Radiological Contingency & Emergency Plan (Rc&Ep) ML24101A2372024-04-10010 April 2024 GNF-A Submittal of Emergency Response Telephone Listing Dated 4/2/2024 ML24074A3632024-03-15015 March 2024 Global Nuclear Fuels - Americas - NRC Inspection Report 07001113-2024006 ML24068A1302024-03-0808 March 2024 Global Nuclear Fuel - Request to Withdraw GNF-A Supplemental Environmental Report ML24017A1602024-01-31031 January 2024 Global Nuclear Fuel - Americas - Core Inspection Report 07001113-2023004 ML24030A5182024-01-30030 January 2024 Global Nuclear Fuel - Americas, LLC (GNF-A), Submittal of Revised ISA Summary Per 10CFR70.72(d) ML24008A2892024-01-10010 January 2024 Global Nuclear Fuel-Americas - NRC Inspection Report 07001113/2023006 ML24003A6832024-01-0404 January 2024 Global Nuclear Fuel - Americas, L.L.C. – Material Control and Accounting Program Inspection Report 07001113-2023401 - Public ML23311A3802023-12-11011 December 2023 Cover Letter - Safety Evaluation Report for GNF-A Request for 8 Weight Percent Uranium 235 ML23334A2222023-11-30030 November 2023 GE Hitachi Nuclear Energy - NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed ML23283A3292023-11-30030 November 2023 NRC Issuance of Order Consenting to Indirect Transfer of Control of Ge/Geha/Gnfa Licenses ML23276B3952023-10-13013 October 2023 The U.S. Nuclear Regulatory Commission Staff Assessment of Ge/Geha/Gnfa Reponses to Acceptance Observations Application for the U.S. Nuclear Regulatory Commission Consent to Indirect Transfer of Licenses ML24005A2842023-09-18018 September 2023 23-004 M230129 GNF-A 2023 Biennial Exercise Supplement NRC Cover Letter 9-18-2023 ML23255A2902023-09-13013 September 2023 Global Nuclear Fuel – Americas, L.L.C. – Inspection Schedule for Calendar Year 2024 ML23230A3942023-08-18018 August 2023 GNF-A Semi-Annual Effluent Monitoring Report ML23229A5122023-08-17017 August 2023 GE-Hitachi Nuclear Energy Americas, LLC, Response to NRC Staff Observations Enclosed with NRC Acceptance Letter (Reference 2) Related to GE, Geha and GNF-A Application (Reference 1) ML23213A1452023-08-0202 August 2023 Global Nuclear Fuel – Americas, LLC – Core Inspection Report 07001113/2023002 ML23209A6762023-07-28028 July 2023 GNF-A Response to NRC Request for Additional Information ML24005A2782023-07-27027 July 2023 23-030 M230100 GNF-A 2023 Biennial Exercise NRC Cover Letter 7-27-23 ML23191A8592023-07-27027 July 2023 Acceptance Letter GE GNFA and Geha Application for NRC Consent to Indirect Transfer of Licenses ML23195A0942023-07-14014 July 2023 GNF-A Written Follow-up Report – Fire System Impairment ML23192A5162023-07-11011 July 2023 GNF-A Natrium Fuel Fabrication Facility Schedule Update ML23156A1832023-07-0303 July 2023 Request for Additional Information Regarding GNF-A License Amendment Request for 8 Weight Percent Uranium 235 ML23178A0992023-06-27027 June 2023 GNF-A Additional Response to Nrg Request for Supplemental Information - Decommissioning Funding Plan (DFP) ML23177A0892023-06-26026 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 2 ML23171A9762023-06-20020 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 1 ML23159A1342023-06-0808 June 2023 Global Nuclear Fuel - Americas, LLC, Physical Inventory Summary Reports ML23152A1162023-05-30030 May 2023 Application for Order Consenting to Indirect Transfer of Control with Respect to Reactor Licenses, Materials Licenses, and Export Licenses, and Notification Regarding Other Approvals ML23116A3212023-04-27027 April 2023 Public Meeting Summary Licensee Performance Review of Global Nuclear Fuel Americas, LLC, Docket Number 07001113 ML23116A1842023-04-26026 April 2023 GNF-A Response to NRC Request for Supplemental Information - Decommissioning Funding Plan (DFP) ML23089A2392023-04-10010 April 2023 Global Nuclear Fuel – Americas, LLC, Triennial - 2022 Update to Decommissioning Funding Plan - Supplemental Information Needed - Enterprise Project Identification Number L-2022-DDP-0002 ML23104A4172023-03-31031 March 2023 GNF-AGEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit 2024-09-06
[Table view] |
Text
Doug Nay, Facility Manager Global Nuclear Fuel Global Nuclear Fuel Americas Facility 3901 Castle Hayne Road P.O. Box 4780 Wilmington, NC 28402
SUBJECT:
ACCEPTANCE OF GLOBAL NUCLEAR FUEL - AMERICAS, LLC, LICENSE AMENDMENT REQUEST FOR 8 WEIGHT PERCENT URANIUM-235 (ENTERPRISE PROJECT IDENTIFICATION NUMBER L-2022-LLA-0065)
Dear Doug Nay:
The U.S. Nuclear Regulatory Commission (NRC) staff has received your submittal dated June 24, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML22175A070), and responses to the NRC staffs requests for supplemental information (RSI) dated October 5, 2022 (ML22278A155), requesting a license amendment to permit nuclear fuel fabrication with material enrichment limits up to 8 weight percent Uranium-235.
We have completed our acceptance review of your submittal and RSI responses. We have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Enterprise Project Identification Number (EPID) L-2022-LLA-0065. Please reference this EPID number and Docket Number 07001113 in any future correspondence associated with this request.
Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by October 31, 2023. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require approximately 1200 staff hours which corresponds to about $348,000.00 ($290.00/hr).
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).November 2, 2022 D. Nay 2 If you have any questions regarding this communication, please contact me at 301-415-4053, or via email to jonathan.rowley@nrc.gov.
Sincerely, Jonathan G. Rowley, Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 07001113 License No. SNM-1097 cc: gnfa@listmgr.nrc.gov Signed by Rowley, Jonathan on 11/02/22
ML22304A671 OFFICE NMSS/DFM/FFLB/PM NMSS/DFM/FFLB/LA NMSS/DFM/FFLB/BC(A)
NAME JRowley ELee JDowns for JZimmerman DATE 11/01/2022 11/01/2022 11/02/2022