Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARML22175A0702022-06-24024 June 2022 GNF-A License Amendment Request for 8 Wt. % U 235 (Leu+) Project stage: Request ML22227A0482022-08-15015 August 2022 GNF-A Semi-Annual Effluent Monitoring Report for January-June 2022 Project stage: Request ML22271A9362022-10-0404 October 2022 Requests for Supplemental Information for the Acceptance of Global Nuclear Fuel - Americas License Amendment Request for 8 Weight Percent Uranium-235 Project stage: Acceptance Review ML22278A1552022-10-0505 October 2022 Global Nuclear Fuel -Americas LLC - Response to NRC Environmental Protection Request for Supplemental Information Dated October 4, 2022 Project stage: Request ML22304A6712022-11-0202 November 2022 Acceptance of Global Nuclear Fuel - Americas License Amendment Request for 8 Weight Percent Uranium-235 Project stage: Acceptance Review ML23156A1832023-07-0303 July 2023 Request for Additional Information Regarding GNF-A License Amendment Request for 8 Weight Percent Uranium 235 Project stage: RAI ML23311A3832023-12-11011 December 2023 Amendment 18 to SNM-1097 (Publicly Available Version) Project stage: Other ML23311A3812023-12-11011 December 2023 Safety Evaluation Report for GNF-A Request for 8 Weight Percent Uranium 235 Project stage: Approval ML23311A3802023-12-11011 December 2023 Cover Letter - Safety Evaluation Report for GNF-A Request for 8 Weight Percent Uranium 235 Project stage: Approval 2022-06-24
[Table View] |
|
---|
Category:Letter
MONTHYEARML24017A1602024-01-31031 January 2024 Global Nuclear Fuel - Americas - Core Inspection Report 07001113-2023004 ML24030A5182024-01-30030 January 2024 Global Nuclear Fuel - Americas, LLC (GNF-A), Submittal of Revised ISA Summary Per 10CFR70.72(d) ML24008A2892024-01-10010 January 2024 Global Nuclear Fuel-Americas - NRC Inspection Report 07001113/2023006 ML24003A6832024-01-0404 January 2024 Global Nuclear Fuel - Americas, L.L.C. Material Control and Accounting Program Inspection Report 07001113-2023401 - Public ML23311A3802023-12-11011 December 2023 Cover Letter - Safety Evaluation Report for GNF-A Request for 8 Weight Percent Uranium 235 ML23283A3292023-11-30030 November 2023 NRC Issuance of Order Consenting to Indirect Transfer of Control of Ge/Geha/Gnfa Licenses ML23334A2222023-11-30030 November 2023 GE Hitachi Nuclear Energy - NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed ML23276B3952023-10-13013 October 2023 the U.S. Nuclear Regulatory Commission Staff Assessment of Ge/Geha/Gnfa Reponses to Acceptance Observations Application for the U.S. Nuclear Regulatory Commission Consent to Indirect Transfer of Licenses ML24005A2842023-09-18018 September 2023 23-004 M230129 GNF-A 2023 Biennial Exercise Supplement NRC Cover Letter 9-18-2023 ML23255A2902023-09-13013 September 2023 Global Nuclear Fuel Americas, L.L.C. Inspection Schedule for Calendar Year 2024 ML23230A3942023-08-18018 August 2023 GNF-A Semi-Annual Effluent Monitoring Report ML23229A5122023-08-17017 August 2023 GE-Hitachi Nuclear Energy Americas, LLC, Response to NRC Staff Observations Enclosed with NRC Acceptance Letter (Reference 2) Related to GE, Geha and GNF-A Application (Reference 1) ML23213A1452023-08-0202 August 2023 Global Nuclear Fuel Americas, LLC Core Inspection Report 07001113/2023002 ML23209A6762023-07-28028 July 2023 GNF-A Response to NRC Request for Additional Information ML23191A8592023-07-27027 July 2023 Acceptance Letter GE GNFA and Geha Application for NRC Consent to Indirect Transfer of Licenses ML24005A2782023-07-27027 July 2023 23-030 M230100 GNF-A 2023 Biennial Exercise NRC Cover Letter 7-27-23 ML23195A0942023-07-14014 July 2023 GNF-A Written Follow-up Report Fire System Impairment ML23192A5162023-07-11011 July 2023 GNF-A Natrium Fuel Fabrication Facility Schedule Update ML23156A1832023-07-0303 July 2023 Request for Additional Information Regarding GNF-A License Amendment Request for 8 Weight Percent Uranium 235 ML23178A0992023-06-27027 June 2023 GNF-A Additional Response to Nrg Request for Supplemental Information - Decommissioning Funding Plan (DFP) ML23177A0892023-06-26026 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 2 ML23171A9762023-06-20020 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 1 ML23159A1342023-06-0808 June 2023 Global Nuclear Fuel - Americas, LLC, Physical Inventory Summary Reports ML23152A1162023-05-30030 May 2023 Application for Order Consenting to Indirect Transfer of Control with Respect to Reactor Licenses, Materials Licenses, and Export Licenses, and Notification Regarding Other Approvals ML23116A3212023-04-27027 April 2023 Public Meeting Summary Licensee Performance Review of Global Nuclear Fuel Americas, LLC, Docket Number 07001113 ML23116A1842023-04-26026 April 2023 GNF-A Response to NRC Request for Supplemental Information - Decommissioning Funding Plan (DFP) ML23089A2392023-04-10010 April 2023 Global Nuclear Fuel Americas, LLC, Triennial - 2022 Update to Decommissioning Funding Plan - Supplemental Information Needed - Enterprise Project Identification Number L-2022-DDP-0002 ML23104A4172023-03-31031 March 2023 GNF-AGEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML23065A0722023-03-0606 March 2023 Global Nuclear Fuel Americas (GNF-A), Supplemental Environmental Report Information and Request to Begin Construction ML23060A0862023-03-0303 March 2023 Global Nuclear Fuel - Americas, LLC Licensee Performance Review (Nuclear Regulatory Commission Inspection Report 07001113/2023005) ML23039A1512023-03-0303 March 2023 Cover Letter - Approval of GNF-A Er Exemption Request ML23058A2232023-02-27027 February 2023 GNF-A Semi-Annual Effluent Monitoring Report ML23044A4522023-02-13013 February 2023 Global Nuclear Fuel - Americas, L.L.C. (GNF-A), Submittal of Revision to GNF-A Radiological Contingency & Emergency Plan (Rc&Ep) ML23033A5422023-02-0202 February 2023 Global Nuclear Fuel - Americas, LLC - Submittal of FOCI Information Update ML23030A8022023-01-30030 January 2023 Submittal of GNF-A Natrium Fuel Fabrication Facility Pre-Application - Meeting Slides ML23027A0522023-01-27027 January 2023 Global Nuclear Fuel- Americas, LLC, Revised ISA Summary Per 10CFR70.72(d) ML23032A3722023-01-17017 January 2023 Concurrence from Nc Shpo - January 17 2023 ER-08-0036 ML23017A0102023-01-17017 January 2023 Global Nuclear Fuel-Americas, LLC - Core Inspection Report 07001113/2022004 ML23004A1962023-01-0404 January 2023 Global Nuclear Fuel Americas (GNF-A) Request for Exemption from Supplemental Environmental Report Timing Requirement of 10 CFR 51.60(a) ML22355A1622022-12-20020 December 2022 GNF-A Submittal of FOCI Information Update ML22346A0702022-12-12012 December 2022 GNF-A Written Follow-up Report - Fire System Impairment ML22346A2482022-12-12012 December 2022 Notice of Global Nuclear Fuel Americas, LLC (GNF-A) Facility Manager Change 2024-01-04
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23156A1832023-07-0303 July 2023 Request for Additional Information Regarding GNF-A License Amendment Request for 8 Weight Percent Uranium 235 ML23089A2402023-04-10010 April 2023 Encl: GNF-A 2022 DFP Request for Supplemental Information ML23052A0132023-02-17017 February 2023 2023-001 - GNF-A - FP Document Request ML22271A9362022-10-0404 October 2022 Requests for Supplemental Information for the Acceptance of Global Nuclear Fuel - Americas License Amendment Request for 8 Weight Percent Uranium-235 ML22147A1222022-06-0808 June 2022 RAIs for GNF-A Safety Analytic Methods ML22042B3112022-02-0808 February 2022 2022-001 GNF NCS-RP Document Request ML21265A3072021-09-17017 September 2021 2. Requests for Additional Information ML21081A0432021-03-22022 March 2021 NRC Inspection Document Request - GNF-A (NCS1 & Trans - April 2021) ML20196L6602020-07-15015 July 2020 Letter - Request for Additional Information to Support GNF-A's Minimum Margin of Subcriticality to Support 8% Enrichment ML20092G7192020-05-0606 May 2020 NRC Letter - 2nd Round Request for GNF-A Supplemental Information to Support 8-percent Enrichment Amendment ML20079G1532020-03-15015 March 2020 Request for Additional Information - Exemption Request from 24-hour Reporting Requirement ML19266A6002019-09-20020 September 2019 Document Request Global Nuclear Fuels OPS-NCS-PPM-RP 2019004 ML18176A1672018-06-29029 June 2018 Gnf LAR 14 Enclosure ML1113003182011-06-0202 June 2011 Enclosurequest for Additional Information Regarding Parent Company Guarantee and Annual Financial Test for General Electric Hitachi (TAC No L33125) 2023-07-03
[Table view] |
Text
October 4, 2022 Doug Nay Facility Manager Global Nuclear Fuel Global Nuclear Fuel Americas Facility 3901 Castle Hayne Road P.O. Box 4780 Wilmington, NC 28402
SUBJECT:
GLOBAL NUCLEAR FUEL - AMERICAS, LLC, REQUESTS FOR SUPPLEMENTAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST FOR 8 WEIGHT PERCENT URANIUM-235 (ENTERPRISE PROJECT IDENTIFICATION NUMBER L-2022-LLA-0065)
Dear Doug Nay:
By letter dated June 24, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML22175A070), Global Nuclear Fuel - Americas (GNF-A) submitted an application to amend materials license SNM-1097. GNF-A requested a license amendment to permit nuclear fuel fabrication at material enrichment limits up to 8 weight percent Uranium-235.
The U.S. Nuclear Regulatory Commission (NRC) staff performed an acceptance review of your application to determine if the application contains sufficient technical information in scope and depth to allow the staff to complete the detailed technical review. This letter is to advise you that, based on our acceptance review, the application does not contain sufficient technical information. The information needed to continue our review is described in the enclosure to this letter. In order to schedule our technical review, this information should be provided within 30 business days of the date of this letter. If the information described is not received within that time, the application will not be accepted for review. This letter confirms our Microsoft Teams call on September 27, 2022, with respect to the supplemental information needed and the date for your submittal.
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter and the enclosure will be available electronically for public inspection in the NRC Public Document Room (PDR) or from ADAMS. The PDR is currently closed. You may submit your request to the PDR via email at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST),
Monday through Friday, except Federal holidays. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
D. Nay 2 If you have any questions regarding this communication, please contact me at 301-415-4053, or via email to jonathan.rowley@nrc.gov.
Sincerely, Signed by Rowley, Jonathan on 10/04/22 Jonathan G. Rowley, Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 07001113 License No. SNM-1097
Enclosure:
Request for Supplemental Information cc: gnfa@listmgr.nrc.gov
ML22271A936 OFFICE NMSS/DFM/PM NMSS/DFM/LA NMSS/DFM/BC NMSS/DFM/PM JZimmerman NAME JRowley ELee JRowley JDowns (acting)
DATE 9/30/2022 9/30/2022 10/03/2022 10/04/2022 REQUEST FOR SUPPLEMENTAL INFORMATION GLOBAL NUCLEAR FUEL - AMERICAS, LLC LICENSE AMENDMENT REQUEST FOR 8 WEIGHT PERCENT U-235 RSI-1 SAFETY - ENVIRONMENTAL PROTECTION Information Needed:
Provide descriptions with appropriate references to sections of current licensing basis documents (e.g., past license renewal documents) and the June 24, 2022, license amendment request (LAR) documents that requested changes to the 30B cylinder receipt, pad storage, incineration, decontamination facilities, liquid radwaste effluent treatment systems that would occur for uranium fuel fabrication at 8.0 weight percent Uranium-235 (U-235).
Deficiency:
The section entitled Environmental Protection of the Global Nuclear Fuel - Americas (GNF-A)
LAR submittal dated June 24, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22175A070), only steps through each item under Title 10 of the Code of Federal Regulations (10 CFR) Paragraph 51.60(b)(2) and makes general conclusions regarding the categorical exclusions of 10 CFR 51.22(c)(11) and environmental impacts under the submitted LAR. However, no detailed justifications are provided such as referring to the appropriate text in other portions of the LAR application or to the environmental impacts assessed under the prior license renewal to support the statements in the Environmental Protection section. According to other information provided in the LAR, changes are proposed to the criticality safety analysis and controls that may impact the 30B cylinder receipt, pad storage, incineration, decontamination facilities, and liquid radwaste effluent treatment systems.
Basis:
The U.S. Nuclear Regulatory Commission (NRC) staff needs additional information to make an acceptance determination with respect to environmental protection. The NRC staff must evaluate the changes and modifications proposed in the LAR and determine whether there are significant changes to effluent releases, environmental monitoring, and postulated accidents for a safety review of environmental protection.
RSI-2 ENVIRONMENTAL REPORT Information Needed:
The NRC staff needs additional information to complete its environmental review of the LAR.
Pages 3-3 through 3-7 of NUREG-1748, Environmental Review Guidance for Licensing Actions Associated with NMSS Programs, provide a discussion of the information that is needed for the development of an environmental assessment (EA) for a simple licensing action. Additionally, Chapter 6 of NUREG-1748 provides a detailed discussion of the information needed for each of the resource areas to include in your environmental report (ER).
The ER for the GNF-A license renewal application should be supplemented in accordance with the guidance in NUREG-1748. Specifically, the ER should include relevant information Enclosure
regarding changes that have occurred since the March 30, 2007, GNF-A Wilmington Environmental Report Supplement (ML071000137), provided with GNF-As 2007 license renewal application. Additionally, the ER should include any details on how the nuclear fuel conversion, fuel fabrication facility, and fuel support activities will be impacted due to the increased enrichment. This should include the impact on the 30B cylinder receipt, pad storage, incineration, decontamination facilities, and liquid radwaste effluent treatment systems as indicated in your letter dated June 24, 2022. In this discussion, please provide details on the changes to receive shipments of higher enriched U-235, modifications to store the higher enriched materials onsite, specific impacts to air and water due to effluents, and specific estimated values of increases in public and occupational dose, such that the NRC can complete an assessment of these impacts.
Deficiency:
In the LAR, GNF-A indicates that its request can be categorically excluded under 10 CFR 51.22(c)(11). However, the considerations noted by GNF-A include topics that the NRC staff must evaluate during the safety review. The NRC staff has not yet been provided sufficient information to conclude that this action can be categorically excluded.
Basis:
Section 51.60 of 10 CFR, Environmental report - materials licenses, outlines the information that should be provided by the licensee for the NRC staff to assess the significance of the environmental impacts of the proposed action and decide if a categorical exclusion or the preparation of an EA and finding of no significant impact is appropriate for this action.
2