Summary of 890208 Meeting W/Bechtel & Util Re Portrayal of Bechtel & Util Auditing of Nuclear Energy Svcs in Info Notice 88-035, Inadequate Licensee Performed Vendor Audits. List of Attendees Encl
ML20235M705
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 02/16/1989
From: Brach E
Office of Nuclear Reactor Regulation
To: Grimes B
Office of Nuclear Reactor Regulation
References
IEIN-88-035, IEIN-88-35, NUDOCS 8902280389
Download: ML20235M705 (2)


Text

-- __ _-- ___-_

, , _ g** "%g ' 9 h '

a 4 UNITED STATES p- g NUCLEAR REGULATORY COMMISSION

h j WASHING TON, D. C. 20555

%...../

FEB1e gggg MEMORANDUM FOR: Brian K. Grimes, Director Division of Reactor Inspection and Safeguards Office of Nuclear Reactor Regulation FR0!i: E. William Brach, Chief Vendor Inspection Branch Division of Reactor Inspection and Safeguards Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

FOR NRC/BECHTEL/GPU MEETING ON INFORMATION NOTICE 88-35 On February 8,1989, NRC management and staff met with Bechtel and General Public Utility (GPU) representatives to discuss the portrayal of Bechtel's  ;

and GPU's auditing of Nuclear Energy Services (NES) in Information Notice i 88-35, " Inadequate Licensee Performed Vendor Audits." The time of the meeting was changed from 2:00 pm to 12:30 pm the morning of February 8, 1989. The change was made to accommodate a last minute change to the schedule of the Director, NRR whose presence was requested by Bechtel. Bechtel presented information concerning the extent of their audits of NES, the audit findings, nonconformance reports issued, and corrective action requested of NES and taken by Bechtel. After discussion of the NRC inspection findings and Bechtel audit and inspection findings, it was determined that Bechtel's primary concern was the characterization of Bechtel's oversight of NES in the information notice.

It was then agreed that Bechtel would submit a letter to the NRC staff that described, for the record, their concern that the information notice had not accurately characterized their oversight of NES. '

br~ A B E. William rach, Chief l Division of Reactor Inspection and Safeguards Office of Nuclear Reactor Regulation

Enclosure:

List of Attendees e i

V i

j 8902280389 DR 990216 i n

^

ADOCK 05000219 PDC

= = _ _ _ - _ _ _ _ _ .

l' .h i~

l n' q ;-;

~*

G_ ' .,;

K.. LIST'0F ATTENDEES-j.-

[ . _ _

~Name Position Company Edward Baker - Section Chief, VIB LNRC

' Bill Brach Branch Chief, VIB NRC

~

Robert E. Rogan Director, L&NS- GPU Nuclear-

-James J. Byrne Manager, Tlil-2 Licensing - GPU Nuclear Dinesh C. Kansal Deputy Manager of QA ,

Bechtel s

T- V. Sarma

. . Project QA Engineer Bechtel

?.. Tom Murley Director, NRR NRC t i Frank Miraglia ADT, NRR NRC Sid Bernsen Manager of_.QA Bechtel a

.(r

k-y :

ENCLOSURE i

! {l. ' :.

1" l