ML20198F454

From kanterella
Revision as of 02:15, 22 November 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Lists Schedule & Discusses Attendance for ACRS Subcommittee Meetings During Oct for Palo Verde,Wppss 3 & 5 & Floating Nuclear Plant
ML20198F454
Person / Time
Site: Palo Verde, 05000000, Satsop, Atlantic Nuclear Power Plant
Issue date: 09/30/1975
From: Parr O
Office of Nuclear Reactor Regulation
To: Boyd R
Office of Nuclear Reactor Regulation
References
CON-WNP-1089 NUDOCS 8605280514
Download: ML20198F454 (1)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION W ASHINGTON, D. C. 20555 SEP 3 01975 g 1.- / O R. S. Boyd, Acting Director, Division of Reactor Licensing, NRR THRU: R. C. DeYoung, Assistant Director, Light Water Reactors gg Group 1, DRL 7 OCTOBER ACRS SUBCOMMITTEE MEETINGS Three ACRS subcommittee meetings are scheduled during October for applications assigned to LWR 1-3:

Pala hrde October 20 gTPSS3/5) October 23 FNP October 29/30 I plan to attend the Palo Verde and WPPSS 3/5 subcommittee meetings along with the LPMs as both of these applications reference CESSAR and my recently assigned LPM (Villaiva) is not up to speed on CESSAR. Regarding the FNP subcommittee meeting I believe that DeYoung or myself should plan to attend along with Birkel due to the unique design concept.

b.

an D. Parr, Chief Light Water Reactors