Board Notification 85-088:forwards CE Norelius 851005 Memo Advising That Licensee Does Not Intend to Pursue Issue of Exceeded freeze-wall Heave Due to Discontinuation of Const at Facility.No Further Reporting on Issue Planned
ML20151L241
Person / Time
Site: Midland
Issue date: 10/22/1985
From: Novak T
Office of Nuclear Reactor Regulation
To: Moore T, Rosenthal A
NRC ATOMIC SAFETY & LICENSING APPEAL PANEL (ASLAP)
Shared Package
ML20151L248 List:
References
TASK-AS, TASK-BN85-088, TASK-BN85-88 BN-85-088, BN-85-88, OL, OM, NUDOCS 8510240469
Download: ML20151L241 (1)


Text

In N005 rg

[ $3 ficqo

' ' , UNITED STATES

  • ! 'n NUCLEAR REGULATORY COMMISSION g WASHINGTON, D. C. 20555 l

October 22, 1985

%, .....,/

Docket Nos: 50-329 OM, OL 1 and 50-330 OM, OL MEMORANDUM FOR: Atomic Safety and Licensing Appeal Board '

for Midland Plant, Units 1 and 2 (l(. Rosenthal and T. Moore) -

FROM: Thomas M. Novak, Assistant Director i for Licensing i Division of Licensing '

Office of Nuclear Reactor Regulation

SUBJECT:

BOARD NOTIFICATION REGARDING FREEZE-WALL THAWING (BN-85-088)

In accordance with the NRC procedures for Board Notifications, the following information is being provided. This information is applicable to the Midland Plant, Units 1 and 2. The Midland OM-OL Licensing Board and parties are being informed by copy of this memorandum. ,

As noted in the enclosure, underground utility movement at the freeze-wall crossings during thawing was more than anticipated. Preliminary survey data from the four monitoring pits indicate that utility settlement exceeded freeze-wall heave in some cases. The adequacy of safety-related underground electrical duct banks and piping in the plant b6ckfill at the Midland site and the potential heaving and thawing influences of the freeze-wall were addressed in the Midland OM-OL hearing and its associated Partial Initial Decision (dated January 23, 1985) currently before the Appeal Board.

Because of the indefinite status of construction resumption, no further reporting on this issue is planned unless the project is reactivated.

Thomas M.-Novak, Assistant Director for Licensing Division of Licensing Office of Nuclear Reactor Regulation

Enclosure:

As stated cc; ACRS (10) C. Bachhoefer, ASLB ED0 J. Harbour, ASLB Parties to the Proceeding F. Cowan, ASLB See next page .

510240469