Superintendent Shift Operations' Log, 1500-2300
ML030070113
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 01/08/2002
From: Huegel J, Mckeown C
Florida Power Corp
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2003-0059
Download: ML030070113 (1)


Text

44 CRYSTAL RIVER NUCLEAR PLANT SUPERINTENDENT SHIFT OPERATIONS' LOG vWR~~flk P~IK A ?P"s 2NnW cvmawy Tuesday, January 08,2002 Jack E. Huegel / Curtis McKeown 1500-2300 PLANT STATUS: Mode 1, 100 % Power, 2544 MWTH, 887 MWE Primary: 579 IF TAvE, 1596 ppmb, PZR 219" Secondary: OTSGs: 78/75 %, 1.2 Hga Vacuum, 51°F UHS Rx Bldg.: 113 IF Ave., -0.1 psig, AHF-1B (high) & AHF-1C (low) on CI mit Time* Item Description JH 1613 Relief Assumed the duties of the Superintendent Shift Operations [1433]. Curtis Mckeown assumed the duties of the Control Room Supervisor [1502].

cDm 1658 SP-158 Notified by R. Biddlemarkthat SP-158, Back-up System Meteorological Monitoring Instrumentation Calibration, has been completed satisfactorily [1525].

Additionally, SP-157A, Meteorological System Surveillance, (Daily) has been completed satisfactorily on MMP-1 [1637]. The actions of the ODCM 2.15 are no longer applicable [1650].

JEH 1701 Turtle Site security has reported the rescue of a live sea turtle on the intake bar racks

[1656]. The turtle has been transported to the Mariculture Center. The turtle is healthy and in a holding tank at the Mariculture Center IAW AI-57 1. This turtle is #64 in this biennial period. NCR 53719 has been generated.

JrlH 1754 SP-194A Calibration of EFIC Channel "A" Instrument Strings has been completed. Exit the following actions [1752]:

ITS 3.3.11, Condition A & D ITS 3.3.12, Condition B ITS 3.3.13, Condition A ITS 3.3.14, Condition A ITS 3.3.17, Condition A and FPP Table 6.9a for the following instruments:

Post-Accident Monitoring instruments: MS-106-PI, MS-106-PIR, MS-1 10-PI, MS-1 10-PIR, SP-17-LI, SP-17-LIR, SP-21-LI, SP-21-LIR, SP-25-LI, SP-25-LIR, SP-29-LI, and SP-29-LIR.

JEH 2212 SP-113G Power Range Nuclear Instrumentation Gain Adjustment has been performed on NI-5 through NI-8. The actions of ITS 3.3.1, Condition A, were applicable during the time the channels were in 'Bypass' for the performance of this surveillance.

"* A-RPS channel [2025-2102]

"* B-RPS channel [2104-2136]

"* C-RPS channel [1826-1927]

"* D-RPS channel [1930-1955]

SP-312A, Daily Heat Balance Power Comparison, and SP-312B, Monthly NI Imbalance Comparison, were completed satisfactorily following the calibration.

(No Additional Entries This Shift)

SSO Page Indicates time log entry was Mntated