ML032260019

From kanterella
Revision as of 15:24, 21 March 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
July 2003 Monthly Operating Report for Peach Bottom, Units 2 & 3
ML032260019
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 08/04/2003
From: Stathes G
Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML032260019 (13)


Text

Exe konSM Exelon Nuclear Peach Bottom Atomic Power Station Telephone 717.456.7014 www.exeloncorp.com Nuclear 1848 Lay Road Delta, PA 17314-9032 August 4, 2003 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Docket Nos. 50-277 and 50-278 Gentlemen:

Enclosed is the monthly operating report for Peach Bottom Units 2 and 3 for the month of July 2003 forwarded pursuant to Technical Specification 5.6.4 under the guidance of Regulatory Guide 10.1, Revision 4.

Sincerely, L. Stathes Director, Site Engineering Peach Bottom Atomic Power Station GLS/PRR/CSL:cmg Qua CSL Enclosures cc:

H. J. Miller, Administrator, Region 1, USNRC A.C. McMurtray, USNRC, Senior Resident Inspector, PBAPS ccn 03-14068

->q

Peach Bottom Atomic Power Station Unit 2 July 1 through July 31, 2003 Narrative Summary of Operating Experiences Unit 2 began the month of July at 100% power.

At 2300 on July 1 9'h, Unit 2 reduced power to 93% for planned turbine testing, and to swap lube oil coolers on the 2C reactor feedpump turbine. The Unit returned to 100% power by 0200 on July 201.

At 1345 on July 22"d, Unit 2 automatically scrammed from 100% power, due to a generator lockout and resulting turbine trip. At 1358, a Group I isolation occurred due to rising steam tunnel temperatures. During the ensuing forced outage, both the scram and the Group I isolation were investigated. The cause of the scram has been identified to be foreign material in the ISO phase bus duct, which caused intermittent generator grounds. Following corrective actions, the Unit reached critical operation at 0614 on July 25t, and was synchronized with the grid at 1016 on July 26th. Due to previously identified leaking fuel, the power ascension was limited to approximately 0.7% per hour. The Unit reduced power to 50% for a follow-up load drop to set the final rod pattern on July 30'. The Unit returned to 100% power by 2300 on July 31'8.

Unit 2 ended the month of July at 100% power.

Peach Bottom Atomic Power Station Unit 3 July 1 through July 31, 2003 Narrative Summary of Operating Experiences Unit 3 began the month of July at 100% power.

At 2300 on July 5', Unit 3 reduced power to 72%, for a planned rod pattern adjustment. The Unit returned to 100% power by 0643 on July 6 .*

Unit 3 ended the month of July at 100% power.

Attachment to Monthly Operating Report for July 2003 Page 1 UNIT 2 REFUELING INFORMATION

1. Name of facility:

Peach Bottom Unit 2

2. Scheduled date for next refueling shutdown:

Reload 15 is scheduled for September 22, 2004.

3. Scheduled date for restart following refueling:

Restart following refueling forecast for October 7, 2004.

4. Will refueling or resumption of operation there after require a technical specification change or other license amendment?

Yes If answer is yes, what, in general, will these be?

a. Potential Cycle 16 Safety Limit MCPR Change.
5. Scheduled date(s) for submitting proposed licensing action and supporting information:

Nothing to report for this period.

6. Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

Nothing to report this period.

Docket No. 50-277 Attachment to Monthly Operating Report for July 2003 Page 2 UNIT 2 REFUELING INFORMATION (Continued)

7. The number of fuel assemblies (a) in the core, (b) in the spent fuel storage pool and (c) dry storage.

(a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2908 Fuel Assemblies, 58 Fuel Rods (c) Interim Spent Fuel Storage Installation - 680 fuel assemblies

8. The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.

9. The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:

Based on projected dry cask storage schedules and reload batch sizes, a full core discharge will remain available throughout plant life.

Docket No. 50-278 Attachment to Monthly Operating Report for July 2003 Page 1 UNIT 3 REFUELING INFORMATION Name of facility:

Peach Bottom Unit 3

2. Scheduled date for next refueling shutdown:

Reload 14 is scheduled for September 21, 2003.

3. Scheduled date for restart following refueling Restart following refueling forecast for October 9, 2003.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

Yes If answer is yes, what, in general, will these be?

a.) Potential Cycle 15 Safety Limit MCPR Change.

5. Scheduled date(s) for submitting proposed licensing action and supporting information.

a.) Submitted in June 2003.

6. Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

(a) The 3R14 reload will consist of approximately 284 GE-14 bundles. This will be the second reload of GE-14 fuel.

7. The number of fuel assemblies (a) in the core, (b) in the spent fuel storage pool and (c) dry storage.

(a) Core - 764 Fuel Assemblies (b) Fuel Pool - 2657 Fuel Assemblies, 6 Fuel Rods (c) Interim Spent Fuel Storage Installation - 680 fuel assemblies

8. The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.

Attachment to Monthly Operating Report for July 2003 Page 2 UNIT 3 REFUELING INFORMATION (Continued)

9. The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:

Based on projected dry cask storage schedules and reload batch sizes, a full core discharge will remain available throughout plant life.

OPERATING DATA REPORT DOCKET NO. 50-277 DATE AUGUST 5, 2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DMSION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 458-3245 OPERATING STATUS

1. UNIT NAME: PEACH BOTTOM UNIT 2
2. REPORTING PERIOD: - - - - - - - JULY,2003
3. DESIGN ELECTRICAL RATING (NET MWE):_1143 3. DESIGN ELECTRICAL

-11_3~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

MWE):

(NET RATING

- - - - - - - - - - - - - - - - - -L

4. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): - - - - - - - - - - - - - - - - - - - - - - - 7 - - - - _ _ 1182
5. MAXIMUM DEPENDABLE CAPACITY (NET MWE): _ _1116 THIS MONTH YR-TO-DATE CUMULATIVE
6. NUMBER OF HOURS REACTOR WAS CRITICAL 679.5 4,994.3 186,259.8
7. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
8. HOURS GENERATOR ON-LINE 651.5 4,954.5 181,834.4
9. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
10. NET ELECTRICAL ENERGY GENERATED (MWH) 695,816 5,424,964 179,310,730

OPERATING DATA REPORT (CONTINUED)

DOCKET NO. 50 - 277 DATE AUGUST 5,2003 THIS MONTH YR-TO-DATE CUMULATIVE

11. UNIT SERVICE FACTOR 87.6 % 97.4 % 71.3 %
12. UNIT AVAILABILITY FACTOR 87.6 % 97.4 % 71.3%
13. UNIT CAPACITY FACTOR (USING MDC NET) 83.8 % 95.6 % 65.3 %
14. UNIT CAPACITY FACTOR (USING DER NET) 81.8 % 93.3 % 84.1 %
15. UNIT FORCED OUTAGE RATE 12.4 % 2.6 % 9.5 %
16. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):

(717) 456-4248

17. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: (717) 4564248
18. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS): FORECAST ACHIEVED INITIAL CRITICALITY 09o16/73 INITIAL ELECTRICITY 02/18/74 COMMERCIAL OPERATION 07/05/74 PAGE 2 OF 2

UNIT SHUTDOWNS DOCKET NO. 50 - 277 UNIT NAME PEACH BOTTOM UNIT 2 DATE AUGUST 5,2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DMVtSION PEACH BOTTOM ATOMIC POWER STATION REPORT MONTH JULY. 2003 TELEPHONE (717) 45e-3245 METHOD OF CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN ACTION TO NO. DATE (1) (HOURS) (2) REACTOR (3) PREVENT RECURRENCE 2 030722 F 92.5 A 3 REACTOR POWER WAS REDUCED TO 0% DUE TO FOREIGN MATERIAL IN ISOPHASE BUS DUCTS CAUSED INTERMITTENT GENERATOR GROUNDS, TRIPPING UNIT. (SYSTEM SOD GENERATOR ISOPHASE BUS COOLING)

TOTAL HOURS 92.5 (1) (2) (3)

F - FORCED REASON METHOD S - SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL B - MAINTENANCE OR TEST 2- MANUAL SCRAM C - REFUELING 3 - AUTOMATIC SCRAM D - REGULATORY RESTRICTION 4 - OTHER (EXPLAIN)

E -OPERATOR TRAINING + LICENSE EXAMINATION F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)

H - OTHER (EXPLAIN)

OPERATING DATA REPORT DOCKET NO. 50- 278 DATE AUGUST 5,2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DIVISION PEACH BOTTOM ATOMIC POWER STATION TELEPHONE (717) 456-3245 OPERATING STATUS

1. UNIT NAME: _ _ __ _PEACH BOTTOM UNIT 3
2. REPORTING PERIOD: - - - - - - - - - - - - - - - - - - - - - - - - - -_ _ _ JU-LY 2003
3. DESIGNELECTRICALRATING(NETMWE): _ 1119
4. MAXIMUMDEPENDABLECAPACITY(GROSSMWE): - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -_ 1159
5. MAXIMUM DEPENDABLE CAPACITY (NET MWE): - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -_ _1093 THIS MONTH YR-TO-DATE CUMULATIVE
6. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 5,087.0 185,226.5
7. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
8. HOURS GENERATOR ON-LINE 744.0 5,087.0 181,320.8
9. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
10. NET ELECTRICAL ENERGY GENERATED (MWH) 814,841 5,654,863 177,770,829

OPERATING DATA REPORT (CONTINUED)

DOCKET NO. 50 - 278 DATE AUGUST 5,2003 THIS MONTH YR-TO-DATE CUMULATIVE II. UNIT SERVICE FACTOR 100.0% 100.0 % 72.3 %

12. UNIT AVAILABILITY FACTOR 100.0% 100.0% 72.3 %
13. UNIT CAPACITY FACTOR (USING MDC NET) 100.2 % 101.7% 67.1 %
14. UNIT CAPACITY FACTOR (USING DER NET) 97.9 % 99.3 % 65.3 %
15. UNIT FORCED OUTAGE RATE .0 % .0% 8.1 %
16. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):

(717) 456-4248

17. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: (717)4566-4248
18. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS): FORECAS' T. ACHIEVED INITIAL CRITICALITY 08107f74 INITIAL ELECTRICITY 09/01/74 COMMERCIAL OPERATION 12/23174 PAGE 2 OF 2

UNIT SHUTDOWNS DOCKET NO. 50- 278 UNIT NAME PEACH BOTTOM UNIT 3 DATE AUGUST 5, 2003 COMPLETED BY EXELON C. S. LEWIS PLANT ENGINEERING ENGINEERING DMSION PEACH BOTTOM ATOMIC POWER STATION REPORT MONTH JULY, 2003 TELEPHONE (717) 456-3245 METHOD OF CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN ACTION TO NO. DATE (1) (HOURS) (2) REACTOR (3) PREVENT RECURRENCE TOTAL HOURS (1) (2) (3)

F - FORCED REASON METHOD S - SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) I -MANUAL B - MAINTENANCE OR TEST 2- MANUAL SCRAM C - REFUELING 3 -AUTOMATIC SCRAM D - REGULATORY RESTRICTION 4 - OTHER (EXPLAIN)

E - OPERATOR TRAINING + LICENSE EXAMINATION F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)

H - OTHER (EXPLAIN)