MONTHYEARML0417002862004-06-16016 June 2004 Request for Additional Information Exelon Generation Company and Amergen Energy Company Physical Security Plans Sections 10-19 (TAC Nos. MC2890, MC2891, MC2897, MC2898, MC2904, MC2915, MC2916, MC2932, MC2933, MC2934, MC2935, MC2948, MC2953. Project stage: RAI ML0418101252004-06-25025 June 2004 Request for Additional Information Exelon Generation Company and Amergen Energy Company Physical Security Plans Sections 1-9 (TAC Nos. MC2890, MC2891, MC2897, MC2898, MC2904, MC2915, MC2916, MC2932, MC2933, MC2934, MC2935, MC2948, MC2953, M Project stage: RAI ML0420200232004-07-0909 July 2004 Request for Additional Information Exelon Generation Company and Amergen Energy Company Training and Qualification Plans Project stage: RAI ML0421003482004-07-23023 July 2004 Request for Additional Information Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan (TAC Nos. MC2890, MC2891, MC2897, MC2898, MC2904, MC2932, MC2933, MC2934, MC2935, MC2948, MC2953, MC2954, MC2961, MC2962, MC2981, Project stage: RAI RS-04-119, (Exelon) and Amergen Energy Co, LLC (Amergen), Response to Request for Additional Information Related to the Safeguards Contingency Plans and Section 9.4.1 of the Physical Security Plans2004-08-12012 August 2004 (Exelon) and Amergen Energy Co, LLC (Amergen), Response to Request for Additional Information Related to the Safeguards Contingency Plans and Section 9.4.1 of the Physical Security Plans Project stage: Response to RAI ML0425900092004-09-10010 September 2004 Implementation Status of Independent Spent Fuel Storage Installation Interim Compensatory Measures Project stage: Other ML0431200072004-10-28028 October 2004 Administrative Change to Facility Operating License in Conjunction with the Commission Order EA-03-086 Regarding Revised Design Basis Threat (Dbt); and Revisions to Physical Security Plan, Training and Qualification Plan, and Safeguard... Project stage: Other ML0432201242004-11-19019 November 2004 Correction of Administrative Changes to Facility Operating License No. DPR-16 Project stage: Other 2004-06-25
[Table View] |
|
---|
Category:Letter
MONTHYEARML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22214A1732022-08-0202 August 2022 Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML22207B8382022-07-26026 July 2022 NRC Confirmatory Order EA-21-041 ML22130A6882022-05-10010 May 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G L-22-026, Occupational Radiation Exposure Data Report - 20212022-04-29029 April 2022 Occupational Radiation Exposure Data Report - 2021 ML22118A6122022-04-28028 April 2022 Annual Radioactive Environmental Operating Report for 2021 ML22118A5822022-04-28028 April 2022 Annual Radioactive Effluent Release Report for 2021 ML22091A1062022-04-0101 April 2022 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) L-22-022, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec.2022-03-25025 March 2022 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec. ML22069A3762022-03-10010 March 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML22032A0582022-03-0808 March 2022 EA-21-139; EA-150: Oyster Creek Nuclear Generating Station - NRC Investigation Report Nos.. 1-2021-002 & 1-2021-014 ML22060A2202022-03-0202 March 2022 NRC Office of Investigations Case No. 1-2021-009 ML22049B2452022-02-19019 February 2022 Late Low Level Radwaste Shipment Report Pursuant to 10 CFR 20 Appendix G IR 05000219/20214022022-01-26026 January 2022 EA-21-041: Confirmatory Order Related to Oyster Greek Nuclear Generating Station - NRC Investigation Report I-2020-007; NRC Inspection Report Nos. 05000219/2021402 & 07200015/2021401 ML22025A3422022-01-25025 January 2022 and Big Rock Point - Changes to Site Organization ML22025A2182022-01-25025 January 2022 Late LLRW Shipments Investigation Report Pursuant to 10 CFR 20, Appendix G ML22021B5512022-01-21021 January 2022 Compensatory Measures Not Implemented Per Site'S Physical Security Plan Due to Multiplexer (Mux) Power Supply Failure L-21-134, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations2021-12-17017 December 2021 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations ML21349A5192021-12-15015 December 2021 Commitment Change Summary Report ML21285A1912021-11-30030 November 2021 Nrc'S Analysis of Holtec Decommissioning International'S Decommissioning Funding Status Report for Oyster Creek Nuclear Generating Station and Pilgrim Nuclear Power Station, Docket Nos 50-219 and 50-293 IR 05000219/20210032021-11-16016 November 2021 NRC Inspection Report No. 05000219/2021003 L-21-118, Changes to Signature Authority & Addressee for Holtec Decommissioning International, LLC Correspondence Re to Oyster Creek Nuclear Generating Station, Pilgrim Nuclear Power Station, Indian Point Nuclear Generating Units 1, 2, 3, & Palisades2021-11-0909 November 2021 Changes to Signature Authority & Addressee for Holtec Decommissioning International, LLC Correspondence Re to Oyster Creek Nuclear Generating Station, Pilgrim Nuclear Power Station, Indian Point Nuclear Generating Units 1, 2, 3, & Palisades IR 05000219/20214042021-08-26026 August 2021 NRC Independent Spent Fuel Storage Security Inspection Report No. 07200015/2021402 and Security Decommissioning Inspection Report 05000219/2021404 - (Public) 2024-01-09
[Table view] |
Text
November 19, 2004 Mr. Christopher M. Crane President and Chief Nuclear Officer AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
OYSTER CREEK NUCLEAR GENERATING STATION - CORRECTION OF ADMINISTRATIVE CHANGES TO FACILITY OPERATING LICENSE NO. DPR-16 (TAC NO. MC2948)
Dear Mr. Crane:
On October 28, 2004, the Nuclear Regulatory Commission (NRC) staff issued the subject document to, among other things, change Operating License (OL) No. DPR-16 for Oyster Creek Nuclear Generating Station to reflect the Design Basis Threat Order of April 29, 2003.
Subsequent to the issuance, Mr. Thomas Loomis of your staff pointed out a number of errors in the revised OL page 4. We agree that several administrative errors had been inadvertently made. Enclosed please find a corrected page 4, with side bars highlighting the areas of correction. We apologize if these errors caused you any inconvenience.
Sincerely,
\RA\
Peter S. Tam, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-219
Enclosure:
OL page 4 cc w/encl: See next page
November 19, 2004 Mr. Christopher M. Crane President and Chief Nuclear Officer AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
OYSTER CREEK NUCLEAR GENERATING STATION - CORRECTION OF ADMINISTRATIVE CHANGES TO FACILITY OPERATING LICENSE NO. DPR-16 (TAC NO. MC2948)
Dear Mr. Crane:
On October 28, 2004, the Nuclear Regulatory Commission (NRC) staff issued the subject document to, among other things, change Operating License (OL) No. DPR-16 for Oyster Creek Nuclear Generating Station to reflect the Design Basis Threat Order of April 29, 2003.
Subsequent to the issuance, Mr. Thomas Loomis of your staff pointed out a number of errors in the revised OL page 4. We agree that several administrative errors had been inadvertently made. Enclosed please find a corrected page 4, with side bars highlighting the areas of correction. We apologize if these errors caused you any inconvenience.
Sincerely,
\RA\
Peter S. Tam, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-219
Enclosure:
OL page 4 cc w/encl: See next page DISTRIBUTION:
PUBLIC OGC PD1-1 R/F GHill (2) RLaufer WBeckner PTam SLittle ACRS PEselgroth, RI Accession Number: ML043220124 OFFICE PD1-1/PM PD1-1/LA PDI-1/SC NAME PTam SLittle RLaufer DATE 11/18/04 11/18/04 11/19/04 OFFICIAL RECORD COPY
The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the l event of a fire.
(4) AmerGen Energy Company, LLC, shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822), and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans1, which contain Safeguards Information protected under 10 CFR 73.21, is entitled:
Oyster Creek Nuclear Generating Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 0, submitted by letter dated October 21, 2004.
(5) Inspections of core spray spargers, piping and associated components will be performed in accordance with BWRVIP-18, BWR Core Spray Internals l Inspection and Flaw Evaluation Guidelines, as approved by NRC staffs Final l Safety Evaluation Report dated December 2, 1999. l (6) Long Range Planning Program - Deleted (7) Reactor Vessel Integrated Surveillance Program AmerGen Energy Company, LLC, is authorized to revise the Updated Final Safety Analysis Report (UFSAR) to allow implementation of the Boiling Water Reactor Vessel and Internals Project reactor pressure vessel Integrated Surveillance Program as the basis for demonstrating compliance with the requirements of Appendix H to Title 10 of the Code of Federal Regulations Part l 50, Reactor Vessel Material Surveillance Program Requirements, as set forth in the licensees application dated December 20, 2002, and as supplemented on May 30, September 10, and November 3, 2003.
1 The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.
Amendment No. 173, 217, 242, 244 l Revised by letter dated October 28, 2004 Corrected by letter dated 11/19/04 l
Oyster Creek Nuclear Generating Station cc:
Chief Operating Officer Mayor of Lacey Township AmerGen Energy Company, LLC 818 West Lacey Road 4300 Winfield Road Forked River, NJ 08731 Warrenville, IL 60555 Senior Resident Inspector Senior Vice President - Nuclear Services U.S. Nuclear Regulatory Commission AmerGen Energy Company, LLC P.O. Box 445 4300 Winfield Road Forked River, NJ 08731 Warrenville, IL 60555 Director - Licensing and Regulatory Affairs Site Vice President - Oyster Creek AmerGen Energy Company, LLC Generating Station 200 Exelon Way, KSA 3-E AmerGen Energy Company, LLC Kennett Square, PA 19348 P.O. Box 388 Forked River, NJ 08731 Manager Licensing - Oyster Creek Exelon Generation Company, LLC Vice President - Mid-Atlantic 200 Exelon Way, KSA 3-E Operations Kennett Square, PA 19348 AmerGen Energy Company, LLC 200 Exelon Way, KSA 3-N Oyster Creek Generating Station Plant Kennett Square, PA 19348 Manager AmerGen Energy Company, LLC John E. Matthews, Esquire P.O. Box 388 Morgan, Lewis, & Bockius LLP Forked River, NJ 08731 1111 Pennsylvania Avenue, NW Washington, DC 20004 Regulatory Assurance Manager Oyster Creek Kent Tosch, Chief AmerGen Energy Company, LLC New Jersey Department of P.O. Box 388 Environmental Protection Forked River, NJ 08731 Bureau of Nuclear Engineering CN 415 Vice President, General Counsel and Trenton, NJ 08625 Secretary AmerGen Energy Company, LLC Vice President - Licensing and 2301 Market Street, S23-1 Regulatory Affairs Philadelphia, PA 19101 AmerGen Energy Company, LLC 4300 Winfield Road Pete Eselgroth, Region I Warrenville, IL 60555 U.S. Nuclear Regulatory Commission 475 Allendale Road Vice President - Operations Support King of Prussia, PA 19406-1415 AmerGen Energy Company, LLC 4300 Winfield Road Correspondence Control Desk Warrenville, IL 60555 AmerGen Energy Company, LLC P.O. Box 160 Regional Administrator, Region I Kennett Square, PA 19348 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415