ML043120007
ML043120007 | |
Person / Time | |
---|---|
Site: | Oyster Creek |
Issue date: | 10/28/2004 |
From: | John Nakoski NRC/NRR/DLPM/LPD2 |
To: | Crane C AmerGen Energy Co, Exelon Generation Co |
Nakoski J A, NRR/DLPM, 415-1068 | |
References | |
EA-03-086, TAC MC2948 | |
Download: ML043120007 (10) | |
Text
SAFEGUARDS INFORMATION October 28, 2004 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Generation Company, LLC AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
OYSTER CREEK GENERATING STATION - ADMINISTRATIVE CHANGE TO FACILITY OPERATING LICENSE IN CONJUNCTION WITH THE COMMISSION ORDER EA-03-086 REGARDING REVISED DESIGN BASIS THREAT (DBT); AND REVISIONS TO PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN (TAC NO. MC2948)
Dear Mr. Crane:
By letter dated April 28, 2004, the Exelon Generation Company and AmerGen Energy Company submitted a supplemental response in accordance with Order EA-03-086, the Order requiring compliance with the revised design basis threat, dated April 29, 2003 (DBT Order), for Oyster Creek Generating Station (Oyster Creek).Section III.A of the DBT Order required licensees to revise physical security plans (PSPs), training and qualification plans (T&Q Plans),
and safeguards contingency plans (SCPs) in order to provide protection against the revised DBT set forth in Attachment 2 to the DBT Order. These revised plans, along with an implementation schedule, were required to be submitted to the Nuclear Regulatory Commission (NRC or the Commission) for review and approval no later than April 29, 2004.
The NRC staffs review of the Oyster Creek PSP, SCP, and T&Q Plan submitted in your letter dated April 28, 2004, as supplemented on July 6, July 9, July 23, August 4, August 12, September 9, October 14, and October 21, 2004, has focused on ensuring that the necessary programmatic elements are contained in these plans in order to provide high assurance that activities involving special nuclear material are not inimical to the common defense and security and do not constitute an unreasonable risk to the public health and safety.
NOTICE: Enclosure 2 contains Safeguards Information. Upon separation from Enclosure 2, this letter and Enclosure 1 are DECONTROLLED.
SAFEGUARDS INFORMATION
C. Crane The NRC staff has determined that, subject to subsequent inspection and evaluation, these plans contain the necessary programmatic elements that, when effectively implemented, will provide the high assurance that Oyster Creek will be protected against the revised DBT. The NRC staff, therefore, approves the PSP, SCP, and T&Q Plan for Oyster Creek. Ultimately the effectiveness of these plans will be judged on your ability to meet regulatory requirements through facility implementing procedures and site practices. As such, your facility implementing procedures and practices will continue to be subject to future NRC review and inspection, including NRC-conducted force-on-force exercises.
In addition, the NRC staff noted that your PSP included alternatives to certain requirements of Title 10 of the Code of Federal Regulations (10 CFR) Section 73.55. In each case, the NRC staff found that the alternative measures provide an equivalent level of protection to that of the associated requirements and meet the high assurance objectives of 10 CFR 73.55(a). The NRC staff, therefore, approves the alternatives shown in the table below. The NRC staffs evaluation is discussed further in the enclosed Safety Evaluation (SE).
Approved Alternatives to NRC Regulations SE Section PSP Section Alternative to 10 CFR Description 3.6.2 6.2 73.55(c)(3) Isolation zones 3.9.4.3 9.4.3 73.55(d)(4) PA vehicle search requirements 3.9.4.4 9.4.4 73.55(d)(1) PA personnel search requirements 3.9.5.2 9.5 73.55(d)(4) PA access control requirements 3.10.1 10.1 73.55(c)(5) PA illumination requirements 3.10.3 10.3 73.55(e)(1) Security computer secondary power supply equipment room VA barrier, access control and alarm requirements 3.13.1 14.1 73.55(c)(1) Temporary reclassification of VAs to PA 73.55(d)(7)(i)(B) status (devitalization)
Finally, consistent with the DBT Order, conforming administrative changes to Facility Operating Licenses (FOLs) are required to ensure implementation of DBT Order requirements.
Therefore, an administrative license change to FOL No. DPR-16 is being made to incorporate the reference to the revised PSP, SCP, and T&Q Plan required by the DBT Order. This change complies with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in 10 CFR Chapter I.
Please replace the enclosed page to your FOL as indicated in Enclosure 1.
C. Crane A copy of our SE with regard to your security plans (designated as Safeguards Information) is provided in Enclosure 2.
Sincerely,
/RA/
John A. Nakoski, Section Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-219
Enclosures:
- 2. Safety Evaluation (Safeguards Information) cc w/encl 1 only: See Mailing List 1 cc w/encls 1 and 2: Richard Ewart, Security Manager
C. Crane A copy of our SE with regard to your security plans (designated as Safeguards Information) is provided in Enclosure 2.
Sincerely,
/RA/
John A. Nakoski, Section Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-219
Enclosures:
- 2. Safety Evaluation (Safeguards Information) cc w/encl 1 only: See Mailing List 1 cc w/encls 1 and 2: Richard Ewart, Security Manager DISTRIBUTION (w/o Enclosure 2):
PUBLIC SPRT R/F OGC ACRS SLittle PTam DCollins (A) CHolden DLPM DPR GHill (2) TBoyce GMatakas, RI Accession No.: ML043120007 *See previous concurrence OFFICE SPRT/TL SPRT/PM SPRT/LA SPRT/PL OGC NSIR/SC NRR/SC NAME DHuyck RFretz CRaynor JPeralta SMorris JNakoski DATE 10/22/04 10/22/04 10/22/04 10/22/04 10/22/04 10/28/04 10/28/04 OFFICIAL RECORD COPY
Oyster Creek Nuclear Generating Station cc:
Chief Operating Officer Mayor of Lacey Township AmerGen Energy Company, LLC 818 West Lacey Road 4300 Winfield Road Forked River, NJ 08731 Warrenville, IL 60555 Senior Resident Inspector Senior Vice President - Nuclear Services U.S. Nuclear Regulatory Commission AmerGen Energy Company, LLC P.O. Box 445 4300 Winfield Road Forked River, NJ 08731 Warrenville, IL 60555 Director - Licensing and Regulatory Affairs Site Vice President - Oyster Creek AmerGen Energy Company, LLC Generating Station 200 Exelon Way, KSA 3-E AmerGen Energy Company, LLC Kennett Square, PA 19348 P.O. Box 388 Forked River, NJ 08731 Manager Licensing - Oyster Creek Exelon Generation Company, LLC Vice President - Mid-Atlantic 200 Exelon Way, KSA 3-E Operations Kennett Square, PA 19348 AmerGen Energy Company, LLC 200 Exelon Way, KSA 3-N Oyster Creek Generating Station Plant Kennett Square, PA 19348 Manager AmerGen Energy Company, LLC John E. Matthews, Esquire P.O. Box 388 Morgan, Lewis, & Bockius LLP Forked River, NJ 08731 1111 Pennsylvania Avenue, NW Washington, DC 20004 Regulatory Assurance Manager Oyster Creek Kent Tosch, Chief AmerGen Energy Company, LLC New Jersey Department of P.O. Box 388 Environmental Protection Forked River, NJ 08731 Bureau of Nuclear Engineering CN 415 Vice President, General Counsel and Trenton, NJ 08625 Secretary AmerGen Energy Company, LLC Vice President - Licensing and 2301 Market Street, S23-1 Regulatory Affairs Philadelphia, PA 19101 AmerGen Energy Company, LLC 4300 Winfield Road Pete Eselgroth, Region I Warrenville, IL 60555 U.S. Nuclear Regulatory Commission 475 Allendale Road Vice President - Operations Support King of Prussia, PA 19406-1415 AmerGen Energy Company, LLC 4300 Winfield Road Correspondence Control Desk Warrenville, IL 60555 AmerGen Energy Company, LLC P.O. Box 160 Regional Administrator, Region I Kennett Square, PA 19348 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415
AMERGEN ENERGY COMPANY, LLC OYSTER CREEK GENERATING STATION DOCKET NO. 50-219 ADMINISTRATIVE LICENSE CHANGE TO FACILITY OPERATING LICENSE License No. DPR-16
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. Consistent with Order EA-03-086, the Order requiring compliance with the revised design basis threat (DBT Order), issued on April 29, 2003, conforming administrative changes to Facility Operating Licenses (FOLs) are required to ensure implementation of DBT Order requirements. Therefore, an administrative license change to FOL No. DPR-16 is being made to incorporate the reference to the revised Physical Security Plan, Safeguards Contingency Plan, and Training and Qualification Plan required by the DBT Order. These changes comply with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this administrative license change can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this administrative license change will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this administrative license change is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Enclosure 1
- 2. Accordingly, the FOL is changed, as indicated in the attachment.
- 3. This administrative license change is effective as of its date of issuance and shall be implemented on or before October 29, 2004.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
John A. Nakoski, Section Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the FOL Date of Issuance: October 28, 2004
CHANGES TO FACILITY OPERATING LICENSE NO. DPR-16 DOCKET NO. 50-219 Replace the following page of Facility Operating License DPR-16 with the attached revised page as indicated. The revised page is identified by revision date and contains marginal lines indicating the area of change.
Remove Page Insert Page 4 4
The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdovvn in the event of a fire.
(4) AmerGen Energy Company, LLC, shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822), and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans1, which contain Safeguards Information protected under 10 CFR 73.21, is entitled: "Oyster Creek Nuclear Generating Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 0," submitted by letter dated October 21, 2004.
(5) Inspections of core spray spargers, piping and associated components will be performed in accordance with BW RVI P-18, "BW R Core Spray Internals Inspection and Flaw Evaluation Guidelines," as approved by NRC staff's Safety Evaluation Report date December 2, 1999.
(6) Long Range Planning Program - Deleted (7) Reactor Vessel Integrated Surveillance Program AmerGen Energy Company, LLC, is authorized to revise the Updated Final Safety Analysis Report (UFSAR) to allow implementation of the Boiling Water Reactor Vessel and lnternals Project reactor pressure vessel Integrated Surveillance Program as the basis for demonstrating compliance with the requirements of Appendix H to Title 10 of the Code of Federal Regulations Part 50, "Reactor Vessel Material Surveillance Program Requirements," as set forth in the licensee's application dated December 20, 2002, and as supplemented on May 30, September 10, and November 3, 2003.
1 The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.
Amendment No. 68, 81, 108 Revised by letter dated October 28, 2004