Request for Changes to Emergency Action Levels
ML053080015
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 11/14/2005
From: Stang J
Plant Licensing Branch III-2
To: Gaffney M
Nuclear Management Co
stang J, NRR/DLPM, 415-1345
References
TAC MC5005
Download: ML053080015 (3)


Text

November 14, 2005 Mr. Michael G. Gaffney Site Vice President Kewaunee Nuclear Power Plant Nuclear Management Company, LLC N490 Highway 42 Kewaunee, WI 54216-9511

SUBJECT:

KEWAUNEE NUCLEAR POWER PLANT - REQUEST FOR CHANGES TO EMERGENCY ACTION LEVELS (TAC NO. MC5005)

Dear Mr. Gaffney:

By letters dated October 26, 2004 (ML051440256), and June 3, 2005 (ML051650269), the Nuclear Management Company, LLC (NMC) requested approval of changes associated with the Kewaunee Nuclear Power Plant for Emergency Action Levels (EALs). In July 2005, Dominion Energy Kewaunee Inc. (DEK), became the licensee for the Kewaunee Nuclear Power Plant. As a result of this change, by letter dated September 20, 2005, DEK responded to requests for additional information from the U.S. Nuclear Regulatory Commission (NRC) staff and resubmitted the entire EAL package to include the name and acronyms changes associated with changing the licensee. The intent of the September 20, 2005, submittal, was to supersede October 26, 2004, and June 3, 2005 submittals. Therefore, the NRC considers the October 26, 2004, and June 3, 2005, requests for approval of EAL changes to be superseded by the DEK September 20, 2005, submittal. Therefore, action under TAC No. MC5055 is complete.

If you have any questions regarding this matter please call me at (301) 415-1345.

Sincerely,

/RA/

John F. Stang, Sr. Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-305 cc: See next page

ML053080015 OFFICE NRR/LPLIII-1/PM NRR/LPLIII-1/LA NRR/LPLIII-1/BC NAME JStang THarris LRaghavan DATE 11/14/05 11/8/05 11/14/05 Kewaunee Nuclear Power Plant cc:

John Paul Cowan David Zellner Executive Vice President & Chairman - Town of Carlton Chief Nuclear Officer N2164 County B Nuclear Management Company, LLC Kewaunee, WI 54216 700 First Street Hudson, WI 54016 Mr. Jeffery Kitsembel Electric Division Plant Manager Public Service Commission of Wisconsin Kewaunee Nuclear Power Plant PO Box 7854 N490 Highway 42 Madison, WI 53707-7854 Kewaunee, WI 54216-9511 Manager, Regulatory Affairs Kewaunee Nuclear Power Plant N490 Highway 42 Kewaunee, WI 54216-9511 David Molzahn Nuclear Asset Manager Wisconsin Public Service Corporation 600 N. Adams Street Green Bay, WI 54307-9002 Resident Inspectors Office U. S. Nuclear Regulatory Commission N490 Hwy 42 Kewaunee, WI 54216-9511 Regional Administrator Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Jonathan Rogoff Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Larry L. Weyers Chairman, President and CEO Wisconsin Public Service Corporation 600 North Adams Street Green Bay, WI 54307-9002