Proposed Tech Specs Clarifying Operability Definition of HPSI Pump in Mode 3
ML20006F923
Person / Time
Site: Calvert Cliffs Constellation icon.png
Issue date: 02/14/1990
From:
BALTIMORE GAS & ELECTRIC CO.
To:
Shared Package
ML20006F922 List:
References
NUDOCS 9003010358
Download: ML20006F923 (2)


Text

-

EMERGENCY CORE COOLING SYSTEMS 0

ECCS SUBSYSTEMS - Tavg < 300 F L

LIMITING CONDITION FOR OPERATION i

3.5.3 As a minimum, one ECCS subsystem comprised of the following shall be OPERABLE:

a. One# OPERABLE high-pressure safety injection pump, and
b. An OPERABLE flow path capable of taking suction from the refueling water tank on a Safety Injection Actuation Signal and automatically transferring suction to the containment sump on a Recirculation Actuation Signal.

APPLICABILITY: ' MODES 3* and 4.

ACTIONi

a. With no ECCS subsystem OPERABLE, restore at least one ECCS subsystem to OPERABLE status within I hour or be in COLD SHUTDOWN within the next 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br />,
b. In the event the ECCS is actuated and injects water into the Reactor Coolant System, a Special Report shall be prepared and submitted to the Commission pursuant to Specification 6.9.2 ,

within 90 days describing the circumstances of tb3 actuation and the total accumulated actuation cycles to %e.

SURVEILLANCE RE0VIREMENTS _

i 4.5.3.1 The ECCS subsystem shall be demonstrated OPERABLE per the applicable Surveillance Requirements of 4.5.2.

4.5.3.2 All high pressure safety injection pumps, except the above

. required OPERABLE pump, shall be demonstrated inoperable at least once i per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> 0

whenever the temperature of one or more of the RCS cold legs is 5 275 F by verifying that the motor circuit breakers have been removed from their electrical power supply circuits.

  • With pressurizer pressure < 1750 psia.
  1. A maximum of one high-pressure safety injection pump shall be OPERABLE whenever the temperature of one or more of the RCS cold legs is s 2750F.

When Tavg s 350 F, the OPERABLE high pressure safety injection pump will be placed in Pull-to-Lock and will not start automatically. Manual use of the high pressure safety injection pump will be conducted in accordance with approved procedures.

9003010358 900214 PDR p

ADOCK 05000317 FDC

)%

v L CALVERT CLIFFS - UNIT 1 3/4 5 6 Amendment No. A4, 1

4 EMERGENCY CORE COOLING SYSTEMS i 0

ECCS SUBSYSTEMS - Tavg < 300 F LIMITING CONDITION FOR OPERATION 3.5.3 As a minimum, one ECCS subsystem comprised of the following shall be OPERABLE:

a. One8 OPERABLE high-pressure safety injection pump, and
b. An OPERABLE flow path capable of taking suction from the refueling water tank on a Safety Injection Actuation Signal and automatically transferring suction to the containment sump on a Recirculation Actuation Signal.

APPLICABILITY: MODES 3* and 4. ,

ACTION: ,

a. With no ECCS subsystem OPERABLE, restore at least one ECCS subsystem to OPERABLE status within I hour or be in COLD SHUTDOWN within the next 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br />,
b. In the event the ECCS is actuated and injects water into the -

Reactor Coolant System, a Special Report shall be prepared and submitted to the Commission pursuant to Specification 6.9.2 within 90 days describing the circumstances of the actuation and the total accumulated actuation cycles to date.

SURVEILLANCE RE0VIREMENTS 4.5.3.1 The ECCS subsystem shall be demonstrated OPERABLE per the ,

applicable Surveillance Requirements of 4.5.2.

4.5.3.2 All high pressure safety injection pumps, except the above '

required OPERABLE pump, shall be demonstrated inoperable at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> whenever the temperature of one or more of the RCS cold legs is s 275 0F by verifying that the motor circuit breakers have been removed from their electrical power supply circuits.

  • With pressurizer pressure < 1750 psia.
  1. A maximum of one high-pressure safety injection pump shall be OPERABLE -

whenever the temperature of one or more of the RCS cold legs is 1275 0F.

CALVERT CLIFFS - UNIT 2 3/4 5-6 Amendment No. U ,