MONTHYEARML14349A4952014-12-10010 December 2014 Proposed Change to Technical Specifications Concerning the Safety Limit Minimum Critical Power Ratio Project stage: Request ML15034A1062015-02-0303 February 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Acceptance Review ML15050A2452015-02-13013 February 2015 Response to Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Supplement ML15051A2832015-02-19019 February 2015 NRR E-mail Capture - Pilgrim - Acceptance Review Safety Limit Minimum Critical Power Ratio (MF5431) Project stage: Acceptance Review ML15051A0322015-02-25025 February 2015 Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: RAI ML15051A0232015-02-25025 February 2015 Request for Withholding Information from Public Disclosure (Tac No. MF5431) Project stage: Withholding Request Acceptance ML15051A0272015-03-0606 March 2015 Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station Project stage: Other ML15051A0242015-03-0606 March 2015 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination & Opportunity for a Hearing & Order Imposing Procedures for Document Access (MF5431) Project stage: Other NRC-2015-0053, Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station2015-03-0606 March 2015 Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station Project stage: Other ML15075A0332015-03-11011 March 2015 Response to NRC Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Response to RAI ML15037A5232015-03-27027 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15114A0212015-05-0606 May 2015 Issuance of Amendment Regarding the Minimum Critical Power Ratio License Amendment Request Project stage: Approval 2015-02-03
[Table View] |
|
---|
Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000293/20240022024-08-21021 August 2024 NRC Inspection Report No. 05000293/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24129A1042024-05-26026 May 2024 Preapplication Readiness Assessment Plan for the Holtec Decommissioning International License Termination Plan ML24136A2382024-05-14014 May 2024 Annual Radiological Environmental Operating Report for 2023 ML24135A3212024-05-14014 May 2024 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2023 IR 05000293/20240012024-05-0707 May 2024 NRC Inspection Report No. 05000293/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-010, Request for Preapplication Readiness Assessment of the Draft License Termination Plan2024-04-22022 April 2024 Request for Preapplication Readiness Assessment of the Draft License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000293/20230032024-02-29029 February 2024 NRC Inspection Report Nos. 05000293/2023003 and 05000293/2023004 L-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary – November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 And Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23300A0022023-10-27027 October 2023 10 CFR 72.48 Biennial Change Summary Report IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 ML23143A0872023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 L-22-036, Decommissioning Trust Fund Agreement2022-11-0808 November 2022 Decommissioning Trust Fund Agreement ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 And Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 2024-09-18
[Table view] |
Text
Entergy Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 John A. Dent, Jr.
Site Vice President February 13, 2015 U.S, Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Response to Request for Supplemental Information Needed For Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request (TAC NO.
MF5431)
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket No. 50-293 License No. DPR-35
REFERENCES:
- 1. Entergy Letter to NRC, "Proposed Change to Pilgrim Technical Specifications Concerning the Safety Limit Minimum Critical Power Ratio", dated December 10, 2014 (2.14.076)
- 2. NRC Letter to Entergy, "Pilgrim Nuclear Power Station -
Supplemental Information Needed For Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request (TAC NO. MF5431)", dated February 3, 2015 LETTER NUMBER: 2.15. 015
Dear Sir or Madam:
In Reference 1, Entergy proposed to amend Facility Operating License DPR-35 for the Pilgrim Nuclear Power Station (PNPS) by modifying Technical Specification Section 2.1.2. The application proposed to change the Safety Limit Minimum Critical Power Ratio (SLMCPR) in Technical Specification (TS) Section 2.1.2 from > 1.08 to > 1.1 0 for two recirculation loop operation and from Ž 1.11 to Ž_ 1.12 for single loop operation.
In Reference 2, the Nuclear Regulatory Commission (NRC) staff requested that Entergy provide the regulatory criteria used to determine that the license amendment request (LAR) is acceptable.
Entergy Nuclear Operations, Inc. Letter Number: 2.15.015 Pilgrim Nuclear Power Station Page 2 of 3 The applicable regulatory requirements and criteria are:
10 CFR 50.36, "Technical specifications", requires safety limits upon important process variables that are found to be necessary to reasonably protect the integrity of certain of the physical barriers that guard against the uncontrolled release of radioactivity. In this instance, the Safety Limit Minimum Critical Power Ratio (SLMCPR) ensures the integrity of the fuel cladding during normal and abnormal operations and to mitigate the transient and accident conditions.
10 CFR 50, Appendix A, GDC 10, "Reactor design" states "The reactor core and associated coolant, control, and protection systems shall be designed with appropriate margin to assure that specified acceptable fuel design limits are not exceeded during any condition of normal operation, including the effects of anticipated operational occurrences."
Fuel design limits can be exceeded ifthe core exceeds critical power. Critical power is a term used for the power at which the fuel departs from nucleate boiling and enters a transition to film boiling. For boiling water reactors (BWRs), the critical power is predicted using a correlation known as the GE (General Electric) critical quality boiling length correlation, or better known as the GEXL correlation. Due to core wide and operational variations, the margin to boiling transition is most easily described in terms of a critical power ratio (CPR), which is defined as the rod critical power as calculated by GEXL divided by the actual rod power. The more a CPR value exceeds 1.0, the greater the margin to boiling transition. The SLMCPR is calculated using a statistical process that takes into account operating parameters and uncertainties. The operating limit MCPR (OLMCPR) is equal to the SLMCPR plus a CPR margin for transients. At the OLMCPR, at least 99.9 percent of the rods avoid boiling transition during steady state operation and transients caused by a single operator error or equipment malfunction.
The proposed increase in the SLMCPR in PNPS TS Section 2.1.2 follows the requirements above and ensures the integrity of the fuel cladding.
This submittal contains no new regulatory commitments.
If you have questions regarding this subject, please feel free to contact Everett P.
Perkins at (508) 830-8323.
I declare under the penalty of perjury that the foregoing information is true and correct.
Executed on the 13th day of February, 2015 Sincerely, John A. Dent, Jr.
Site Vice President JAD/mew
Entergy Nuclear Operations, Inc. Letter Number: 2.15.015 Pilgrim Nuclear Power Station Page 3 of 3 cc:
U.S. Nuclear Regulatory Commission Mr. John Priest, Director ATTN: Dan Dorman Massachusetts Department of Public Health Regional Administrator, Region 1 Schraft Center Suite 1 M2A 2100 Renaissance Blvd, Suite 100 Radiation Control Program King of Prussia, PA 19406-2713 529 Main Street Charlestown, MA 02129 Ms. Nadiyah Morgan, Project Manager Mr. John Giarrusso, Jr.
Division of Operating Reactor Licensing Nuclear Preparedness Manager Office of Nuclear Reactor Regulation Mass. Emergency Management Agency U.S. Nuclear Regulatory Commission 400 Worcester Road One White Flint North O-8F4 Framingham, MA 01702 11555 Rockville Pike Rockville, MD 20852 NRC Senior Resident Inspector Pilgrim Nuclear Power Station Plymouth, MA 02360