MONTHYEARML13120A1052013-04-26026 April 2013 Response to Request for Information: Near-Term Task Force Recommendation 2.1, Seismic Reevaluation Project stage: Response to RAI ML13259A0442013-09-12012 September 2013 Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - 1.5 Year Response for CEUS Sites Project stage: Response to RAI ML14051A1072014-02-12012 February 2014 Update to Response to NRC Request for Information Pursuant to 10CFR50.54(f) Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - 1.5 Year Response for CEUS Sites Project stage: Response to RAI ML14125A3672014-03-12012 March 2014 Drawing LRA-M-2032-1, Rev. Aj, Sump Pump Diagram Radwaste System Project stage: Request BVY 14-019, Notification of Revised Regulatory Commitments Associated with Request for Information Per 10 CFR50.54(f) Regarding Recommendations 2.1, 2.3, & 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident .2014-03-12012 March 2014 Notification of Revised Regulatory Commitments Associated with Request for Information Per 10 CFR50.54(f) Regarding Recommendations 2.1, 2.3, & 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident . Project stage: Request SBK-L-14052, NextEra Energy Seabrook, LLC Seismic Hazard and Screening Report (CEUS Sites) Response to NRC Request for Information Per 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-2014-03-27027 March 2014 NextEra Energy Seabrook, LLC Seismic Hazard and Screening Report (CEUS Sites) Response to NRC Request for Information Per 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ich Project stage: Response to RAI NL-14-0343, Seismic Hazard and Screening Report for CEUS Sites2014-03-31031 March 2014 Seismic Hazard and Screening Report for CEUS Sites Project stage: Request NRC-14-0017, DTE Electric Companys Seismic Hazard and Screening Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accide2014-03-31031 March 2014 DTE Electric Companys Seismic Hazard and Screening Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Response to RAI NRC 2014-0024, NextEra Energy Point Beach, LLC - Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the F2014-03-31031 March 2014 NextEra Energy Point Beach, LLC - Seismic Hazard and Screening Report (CEUS Sites), Response NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukush Project stage: Request NL-14-0344, Seismic Hazard and Screening Report for CEUS Sites2014-03-31031 March 2014 Seismic Hazard and Screening Report for CEUS Sites Project stage: Request CNL-14-038, Tennessee Valley Authoritys Seismic Hazard & Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Recommendation 2.1 of Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Acci2014-03-31031 March 2014 Tennessee Valley Authoritys Seismic Hazard & Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Recommendation 2.1 of Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accide Project stage: Response to RAI RNP-RA/14-0013, Seismic Hazard Evaluation, Response to NRC 10 CFR 50.54(f) Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)Regarding Recommendations 2.1, 2.3 and 9.3 of the Near-Term Task Force Review of2014-03-31031 March 2014 Seismic Hazard Evaluation, Response to NRC 10 CFR 50.54(f) Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)Regarding Recommendations 2.1, 2.3 and 9.3 of the Near-Term Task Force Review of Project stage: Request ML14099A1962014-03-31031 March 2014 Constellation Energy Nuclear Group, LLC - Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Project stage: Response to RAI ML14092A4162014-03-31031 March 2014 Response to March 12, 2012 Information Request Seismic Hazard and Screening Report (CEUS Sites)For Recommendation 2.1 Project stage: Request L-MT-14-045, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10CFR50.54(f), Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2014-05-14014 May 2014 Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10CFR50.54(f), Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Response to RAI RA-14-071, Supplemental Information Regarding Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites) - Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Tas2014-08-21021 August 2014 Supplemental Information Regarding Seismic Hazard and Screening Report (Central and Eastern United States (CEUS) Sites) - Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Project stage: Supplement ML14307B7072014-12-10010 December 2014 Supplemental Information Related to Development of Seismic Risk Evaluations for Information Request Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-T Project stage: Other ML14349A4952014-12-10010 December 2014 Proposed Change to Technical Specifications Concerning the Safety Limit Minimum Critical Power Ratio Project stage: Request ML15034A1062015-02-0303 February 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Acceptance Review ML15050A2452015-02-13013 February 2015 Response to Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Supplement ML15051A2832015-02-19019 February 2015 NRR E-mail Capture - Pilgrim - Acceptance Review Safety Limit Minimum Critical Power Ratio (MF5431) Project stage: Acceptance Review ML15051A0232015-02-25025 February 2015 Request for Withholding Information from Public Disclosure (Tac No. MF5431) Project stage: Withholding Request Acceptance ML15051A0322015-02-25025 February 2015 Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: RAI NRC-2015-0053, Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station2015-03-0606 March 2015 Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station Project stage: Other ML15051A0242015-03-0606 March 2015 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination & Opportunity for a Hearing & Order Imposing Procedures for Document Access (MF5431) Project stage: Other ML15051A0272015-03-0606 March 2015 Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station Project stage: Other ML15075A0332015-03-11011 March 2015 Response to NRC Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Response to RAI ML15037A5232015-03-27027 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15114A0212015-05-0606 May 2015 Issuance of Amendment Regarding the Minimum Critical Power Ratio License Amendment Request Project stage: Approval 2014-08-21
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. John A. Dent, Jr.
Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 February 25, 2015
SUBJECT:
PILGRIM NUCLEAR POWER STATION-REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (TAC NO. MF5431)
Dear Mr. Dent" By letter dated December 10, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14349A495), you submitted an affidavit dated September 17, 2014, executed by Mr. Lukas Trosman of Global Nuclear Fuel - Americas, LLC, (GNF-A) requesting that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390:
Global Nuclear Fuels Report, GNF-001N8659-R1-P, "GNF Additional Information Regarding the Requested Changes to the Technical Specification SLMCPR
[Safety Limit Minimum Critical Power Ratio], Pilgrim Cycle 21" A nonproprietary copy of this document has been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the NRC Library under ADAMS Accession No. ML14349A496.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GNF-A's competitors without license from GNF-A constitutes a competitive economic' advantage over other companies; and Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
We have reviewed your application and the material in accordance with the requirements of 1 O CFR 2.390 and, on the basis of the statements in the affidavit have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-1016.
Docket No. 50-293 cc: Distribution via Listserv Mr. Lukas Trosman Sincerely, N (jiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Engineering Manager, Reload Design and Analysis Global Nuclear Fuel - Americas, LLC 3901 Castle Hayne Road Wilmington, NC 28401