MONTHYEARML24103A1042024-04-25025 April 2024 St. Lucie/Turkey Point 2023 Annual Assessment Meeting Slides ML24073A3372024-03-13013 March 2024 NextEra - NRC Slides for the Public Meeting on March 19, 2024 Regarding Emergency Plan Licensing Amendment ML23258A0262023-09-15015 September 2023 September 2023 Dseis Public Meeting - In-person Meeting Slides ML23258A0272023-09-15015 September 2023 September 2023 Dseis Public Meeting - Virtual Meeting Slides ML23177A0812023-06-28028 June 2023 Nd Pre-Submittal Meeting Regarding License Amendment Requests for Transition to 24-Month Fuel Cycles ML23124A3412023-05-0404 May 2023 FPL 2022 Public Meeting Slides ML22336A0262022-12-0707 December 2022 December 7 2022 24-Month Fuel Cycle Public Meeting Licensee Slides ML22251A1732022-09-0808 September 2022 Staff Presentation Slides for Turkey Point Di&C LAR Acceptance Review Public Meeting, September 13, 2022 ML22227A1302022-08-17017 August 2022 License Amendment Request Reactor Trip Breaker Completion Time Extension - Public Meeting August 17, 2022 (EPID L-2022-LRM-0061) (Slides) ML22172A2172022-06-22022 June 2022 LAR: Revise Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project (Non-Proprietary) ML22144A3902022-05-24024 May 2022 RCP Seal Solutions - May 24 2022 Slide Material (Public) ML22110A2172022-05-0303 May 2022 Annual Assessment Meeting ML22111A1782022-04-26026 April 2022 April 26, 2022 Public Meeting on Reactor Coolant Pump Seal Replacement - Florida Power and Light Slides ML22098A0932022-04-13013 April 2022 Nextera/Fpl Redacted Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request (Public Version) ML22098A0902022-04-13013 April 2022 Nextera/Fpl Non-Proprietary Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request (EPID L-2021-LRM-0007) (Slides) ML22101A2262022-04-11011 April 2022 NRC Staff Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request ML22063A1262022-03-0404 March 2022 Nextera/Fpl Presentation for March 7, 2022 Public Meeting Between NRC and Florida Power & Light Company to Discuss Planned Digital Instrumentation and Controls License Amendment Request for Turkey Point Nuclear Generating, Units 3 and 4 ML22054A1662022-02-23023 February 2022 ITS Public Meeting Material - NRC - Expectations for Licensee'S Responses to ITS Conversion LAR and RAIs ML22046A0462022-02-15015 February 2022 Icw Relief Request 10 Public Meeting Licensee Presentation ML22032A0022022-02-0202 February 2022 2/2/22 Slides Considerations for the Potential Use of a Multi-Stage Validation Approach to Support to Nuclear Power Plant Control Room Modifications Discussion of Concepts and NRC Licensing Considerations ML21285A0412021-10-13013 October 2021 Summary of September 29, 2021 Meeting with the U.S. Fish and Wildlife Service Regarding Crocodile Monitoring at Turkey Point ML21237A0092021-08-25025 August 2021 August 25, 2021 - Nextera/Fpl Presentation Slides for Public Meeting Concerning Proposed Alternative Repair to Unit 3 CCW Discharge Line ML21235A0932021-08-23023 August 2021 Licensee'S Non-Proprietary Presentation (1 of 2) for August 23 and 25, 2021 Public Meeting ML21232A0172021-08-20020 August 2021 Licensee'S Non-Proprietary Presentation (2 of 2) for August 23 and 25, 2021 Public Meeting ML21225A0012021-08-18018 August 2021 Preapplication Meeting Presentation Improved Technical Specifications Conversion ML21200A1472021-07-22022 July 2021 Nextera/Fpl Meeting Slides for July 22, 2021 Partially Closed Meeting Concerning Control Room Digital Modernization - Closed Public ML21200A1562021-07-22022 July 2021 Nextera/Fpl Meeting Slides for July 22, 2021 Partially Closed Meeting Concerning Control Room Digital Modernization - Open ML21159A1892021-06-0909 June 2021 Non-Proprietary - FPL NRC Presubmittal Meeting June 9th Closed Slides ML21159A1712021-06-0909 June 2021 FPL NRC Presubmittal Meeting June 10th Week Open Session ML21109A0052021-04-19019 April 2021 2020 - Stl - Tpn Combined EOC Presentation ML21096A0772021-04-0808 April 2021 FPL Slides for Meeting with FPL-Turkey Point Units 3 and 4 Concerning Digital Instrumentation and Control Modification ML21096A0612021-04-0808 April 2021 FPL Slides for Meeting with FPL-Turkey Point Units 3 and 4 Concerning Digital Instrumentation and Control Modification - Open ML21076A6152021-03-22022 March 2021 NRC Pre-Submittal Meeting, St. Lucie and Turkey Point Nuclear Plants - Improved Technical Specification Conversion - March 22, 2021 (EPID L-2021-LRM-0032) (Presentation) ML21047A2102021-02-16016 February 2021 NRC Presubmittal Meeting Telecon February 18, 2021 Open Meeting - FPL Safety System Replacement Project LAR - Nonproprietary ML21011A2382021-01-11011 January 2021 Slides for January 13, 2021 Presubmittal Meeting with NextEra Concerning Digital I&C Closed Non-Proprietary ML20338A0472020-12-0909 December 2020 December 9, 2020 FPL Slides Rps/Esfas Nuclear Instrumentation ML20266G2202020-09-15015 September 2020 Slide Presentation for September 15, 2020 Public Meeting Concerning CCW Headers ML20135F6652020-05-14014 May 2020 Stl - Tpn Combined EOC Presentation ML19116A2582019-05-0101 May 2019 Tp Dseis Meeting 05-01-19 Spanish Slides L-2018-136, L-2018-136-Attachment 53 Enclosure 1 - Slides and Presentations2018-08-0808 August 2018 L-2018-136-Attachment 53 Enclosure 1 - Slides and Presentations ML18150A2402018-05-30030 May 2018 Slides for Turkey Point Public Scoping Meeting on May 31 2018 - English ML18144A1242018-05-24024 May 2018 Summary of Public Meeting Concerning Annual Assessment of Turkey Point Nuclear Generating Station Unit 3 and Unit 4, for Period of January 1, 2017 December 31, 2017 ML18141A3072018-05-21021 May 2018 18 - SLR Status ML17310B2322017-11-0707 November 2017 Presentation Slides - NextEra Energy/Fpl - GSI-191 Issue Resolution, Pre-submittal Meeting, September 20, 2017 ML14174A4022014-06-24024 June 2014 6/24/2014, Pre-Submittal Meeting Slide for St. Lucie and Turkey Point Re. License Amendment Request Adoption of TSTF-505 Risk-Informed Completion Time ML14156A2212014-06-0404 June 2014 Public Meeting Summary - Turkey Point Nuclear Generating Station Docket Nos. 50-250 and 50-251 ML13164A3122013-06-13013 June 2013 Summary of Category 3 Public Meeting - Annual Assessment - Turkey Point Nuclear Plant Units 3 and 4 ML1205805322012-02-27027 February 2012 Public Meeting Summary - Turkey Point - Meeting Slides ML11178A0682011-06-23023 June 2011 Meeting Slides, Turkey Point Nuclear Plant, Units 3 and 4, Extended Power Uprate (Epu), NRC and FPL Public Meeting ML1114507462011-05-25025 May 2011 Annual Assessment Meeting - Presentation Slides 2024-04-25
[Table view] |
Text
NRC CY2005 Annual Assessment Meeting TURKEY POINT Homestead, Florida May 17, 2006 Enclosure 2
Purpose of Todays Meeting
- A public forum for discussion of Turkey Point performance
- NRC will address Turkey Point performance issues identified in the annual assessment letter
- Turkey Point management will be given the opportunity to respond to the information in the letter and inform the NRC of new or existing programs to maintain or improve their performance
Agenda
- Review of Reactor Oversight Process
- National Summary of Plant Performance
- Discussion of Turkey Point Plant Performance Results
- Turkey Point Management Response and Remarks
- NRC Available to Address Public Questions
Region II Organization William Travers Regional Administrator Loren Plisco Deputy Regional Administrator Charles Casto Victor McCree Director Division of Reactor Projects Director Division of Reactor Safety Joseph Shea Harold Christensen Deputy Director Deputy Director Joel Munday Regional Specialists Branch Chief Turkey Point Project Engineer Resident Inspectors Son Ninh Scott Stewart Tim Kolb
NRC Performance Goals PRIMARY GOALS Ensure protection of the public health and safety and the environment Ensure the secure use and management of radioactive materials OTHER GOALS
- Ensure openness in NRC regulatory process
- Ensure that NRC actions are effective, efficient, realistic, and timely
- Ensure excellence in NRC management to carry out the NRCs strategic objective
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response
Examples of Baseline Inspections z Equipment Alignment ~80 hrs/yr z Triennial Fire Protection ~200 hrs every 3 yrs z Operator Response ~125 hrs/yr z Emergency Preparedness ~80 hrs/yr z Rad Release Controls ~110 hrs every 2 yrs z Worker Radiation Protection ~90 hrs/yr z Corrective Action Program ~250 hrs every 2 yrs z Corrective Action Case Reviews ~60 hrs/yr
Performance Thresholds Safety Significance Green: Very low safety issue White: Low-to-moderate safety issue Yellow: Substantial safety issue Red: High safety issue NRC Inspection Efforts Green: Only Baseline Inspections White: May increase NRC oversight Yellow: Increased NRC oversight Red: Increased NRC oversight and other NRC actions
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions
National Summary of Plant Performance Status at End of CY 2005 Licensee Response 84 Regulatory Response 12 Degraded Cornerstone 4 Multiple/Repetitive Degraded Cornerstone 3 Unacceptable 0 Total 103
Turkey Point CY2005 Inspection Activities
- 3593 hours0.0416 days <br />0.998 hours <br />0.00594 weeks <br />0.00137 months <br /> of inspection related activities
- Resident inspector daily inspections
- Engineering modifications inspection
- Radiation protection inspections
- Reactor head replacement and containment repair inspections
- Reactor operator initial exam
Turkey Point CY2005 Assessment Results
- Both units performance was within the Licensee Response Column of the NRCs Action Matrix for the first two quarters of the calendar year.
- Unit 4 transitioned into the regulatory response column in the third quarter and both units in the fourth quarter.
Turkey Point CY2005 Assessment Results
- All inspection findings were classified as very low safety significance (Green).
- All performance indicators (PI) were Green with two exceptions - (1) The Unplanned Scrams per 7000 Critical Hours PI for unit 4 crossed the White threshold in the Initiating Events Cornerstone in the third quarter; (2) The Heat Removal System Unavailability PI for both units crossed the White threshold in the Mitigating System Cornerstone in the fourth quarter.
Turkey Point Assessment Summary
- Florida Power and Light Company operated Turkey Point in a manner that preserved public health and safety
- All cornerstone objectives were met
- NRC plans baseline inspections and a 95001 supplemental inspection at Turkey Point for the remainder of CY 2006.
Turkey Point CY2006 Scheduled Inspection Activities
- Resident inspector daily inspections
- Problem identification and resolution inspection
- Radiation protection inspections
- Licensed operator requalification program inspection
- Component design bases inspection
- Containment sump special inspection
- Supplemental inspection for White PI
NRC CY2005 Annual Assessment Meeting TURKEY POINT Homestead, Florida May 17, 2006
Contacting the NRC z Report an emergency (301) 816-5100 (call collect) z Report a safety concern:
(800) 695-7403 Allegation@nrc.gov z General information or questions www.nrc.gov Select What We Do for Public Affairs
Reference Sources z Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html z Public Electronic Reading Room http://www.nrc.gov/reading-rm.html z Public Document Room 1-800-397-4209 (Toll Free)