ME0969 & ME0970, RAIs from ITSB, Amendment Request One-Time Extension of AOT in TS 3.8.1, Required Action A.3
ML091610096
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 06/02/2009
From: Bhalchandra Vaidya
Plant Licensing Branch 1
To: Coddington C, Filchner D, Hoffman C
Susquehanna
vaidya B, NRR/Dorl/lpl1-1, 415-3308
References
TAC ME0969, TAC ME0970
Download: ML091610096 (2)


Text

From: Bhalchandra Vaidya Sent: Tuesday, June 02, 2009 4:59 PM To: 'Coddington, Cornelius T'; 'ckhoffman@pplweb.com';

'dlfilchner@pplweb.com' Cc: Douglas Pickett; John Boska; Richard Guzman

Subject:

Susquehanna Units 1 and 2, ME0969 & ME0970, ITSB RAIs-Amd for T-20 Replacement, One-time Ext of AOT in Ts 3.8.1 The Technical Specification Branch (ITSB) has identified the need for the following additional information (RAIs) to complete its review of the application:

Request for Additional Information:

Susquehanna TS LCO 3.0.2 Bases State that Entering ACTIONS for [Corrective Maintenance]

must be done in a manner that does not compromise safety. PPL Susquehanna had requested and received two previous One-Time extensions for LCO 3.8.1 due to deficiencies in ST performance and operation from NRC Staff in 2002 & 2003.

1. Justify that PPL Susquehannas third one-time extension request of TS 3.8.1 from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 10 days, for ST replacement at power since 2002, represents plant corrective maintenance practices that are done in a manner that does not compromise safety.
2. Explain why a Third One-Time extension for replacing Station Transformers is not symptomatic of a design inadequacy with PPL Susquehanna in meeting the 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time as required by LCO 3.8.1, and
3. Why choosing to extend the completion time of LCO 3.8.1 does not constitute an operational convenience (per Susquehanna TS LCO 3.0.2 Bases) as a Third request in replacing damaged/degraded Station Transformers at PPL Susquehanna.

Please respond to these RAIs by COB June 30, 2009 in order so we can try to support the requested completion date.

Please let me know if you need a teleconference to discuss the RAIs.

Bhalchandra K. Vaidya Licensing Project Manager NRC/NRR/DORL/LPL1-1 (301)-415-3308 (O) bhalchandra.vaidya@nrc.gov E-mail Properties Mail Envelope Properties ()

Subject:

Susquehanna Units 1 and 2, ME0969 & ME0970, ITSB RAIs-Amd for T-20 Replacement, One-time Ext of AOT in Ts 3.8.1 Sent Date: 06/02/2009 4:34:51 PM

Received Date: 06/02/2009 4:58:00 PM From: Bhalchandra Vaidya Created By: Neelam.Bhalla@nrc.gov Recipients:

ctcoddington@pplweb.com ('Coddington, Cornelius T')

Tracking Status: None ckhoffman@pplweb.com ('ckhoffman@pplweb.com')

Tracking Status: None dlfilchner@pplweb.com ('dlfilchner@pplweb.com')

Tracking Status: None Douglas.Pickett@nrc.gov (Douglas Pickett)

Tracking Status: None John.Boska@nrc.gov (John Boska)

Tracking Status: None Richard.Guzman@nrc.gov (Richard Guzman)

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 13430 06/02/2009 Options Expiration Date:

Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: