MONTHYEAR05000482/LER-2024-001-01, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-10-22022 October 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing ML24296B1902024-10-22022 October 2024 10 CFR 50.55a Requests for the Fifth Ten-Year Interval Inservice Testing Program 05000482/LER-2024-002, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-10-21021 October 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information ML24199A1712024-09-17017 September 2024 Issuance of Amendment No. 241 Revise Ventilation Filter Testing Program Criteria and Administrative Correction of Absorber in Technical Specification 5.5.11 ML24260A0712024-09-12012 September 2024 License Amendment Request for a Risk-Informed Resolution to GSI-191 IR 05000482/20240102024-09-10010 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000482/2024010 (Public) ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24248A0762024-09-0404 September 2024 Containment Inservice Inspection Program Third Interval, Second Period, Refueling Outage 26 Owner’S Activity Report ML24248A2492024-09-0404 September 2024 Inservice Inspection Program Fourth Interval, Third Period, Refueling Outage 26 Owner’S Activity Report ML24241A2212024-08-29029 August 2024 Notice of Enforcement Discretion for Wolf Creek Generating Station ML24240A2642024-08-27027 August 2024 Corporation - Request for Notice of Enforcement Discretion Regarding Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24227A5562024-08-14014 August 2024 Application to Revise Technical Specifications to Adopt TSTF-569-A, Revision 2, Revision of Response Time Testing Definitions IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24213A3352024-07-31031 July 2024 License Amendment Request to Revise Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)) (Fq Methodology), to Implement the Methodology from WCAP-17661-P-A, Revision 1. ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) IR 05000482/20240022024-07-18018 July 2024 Integrated Inspection Report 05000482/2024002 05000482/LER-2024-001, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-07-0202 July 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing IR 05000482/20244012024-07-0202 July 2024 Security Baseline Inspection Report 05000482/2024401 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24150A0562024-05-29029 May 2024 Foreign Ownership, Control or Influence (FOCI) Information – Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML23345A1602024-05-0909 May 2024 Revision of Safety Evaluation for Amendment No. 237 Request for Deviation from Fire Protection Requirements ML24089A2622024-04-29029 April 2024 Financial Protection Levels ML24118A0022024-04-27027 April 2024 Wolf Generating Nuclear Station - 2023 Annual Radiological Environmental Operating Report ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24113A1882024-04-19019 April 2024 Foreign Ownership, Control or Influence Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML24109A1212024-04-18018 April 2024 (WCGS) Form 5 Exposure Report for Calendar Year 2023 ML24109A1842024-04-18018 April 2024 Cycle 27 Core Operating Limits Report IR 05000482/20240012024-04-17017 April 2024 Integrated Inspection Report 05000482/2024001 ML24114A1442024-04-15015 April 2024 Redacted Updated Safety Analysis Report (WCGS Usar), Revision 37 ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information ML24098A0052024-04-0707 April 2024 2023 Annual Environmental Operating Report ML24089A1352024-03-29029 March 2024 10 CFR 50.46 Annual Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes ML24089A0972024-03-29029 March 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24074A3312024-03-14014 March 2024 Missed Quarterly Inspection Per 40 CFR 266 Subpart N ML24080A3452024-03-11011 March 2024 7 of the Wolf Creek Generating Station Updated Safety Analysis Report IR 05000482/20240122024-03-11011 March 2024 Fire Protection Team Inspection Report 05000482/2024012 ML24016A0702024-03-0808 March 2024 Issuance of Amendment No. 240 Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML24068A1992024-03-0707 March 2024 Changes to Technical Specification Bases - Revisions 93 and 94 ML24066A0672024-03-0505 March 2024 4-2022-024 Letter - OI Closure to Licensee ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners ML24059A1702024-02-28028 February 2024 Annual Fitness for Duty Program Performance Report, and Annual Fatigue Report for 2023 IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24026A0212024-02-27027 February 2024 Issuance of Amendment No. 239 Modified Implementation Date of License Amendment No. 238 ML24050A0012024-02-19019 February 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24036A0092024-02-14014 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0075 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 2024-09-06
[Table view] |
Text
WOLF CREEK 'NUCLEAR OPERATING CORPORATION John P. Broschak Vice President Engineering October 29, 2012 ET 12-0029 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
References:
- 1) Letter dated March 12, 2012, from E. J. Leeds and M. R. Johnson, USNRC, to M. W. Sunseri, WCNOC, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
- 2) NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," Revision 0, August 29, 2012 (ADAMS Accession Number ML12229A174)
- 3) Letter dated February 24, 2012, from A. R. Pietrangelo, Nuclear Energy Institute (NEI) to USNRC, "Industry Initiative on Procurement of Equipment for the Diverse and Flexible Coping Strategy (FLEX)" (ADAMS Accession No. ML12061A023)
- 4) NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX)
Implementation Guide," Revision 0, August 2012 (ADAMS Accession No. ML12242A378)
Subject:
Docket No. 50-482: Wolf Creek Nuclear Operating Corporation Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
Gentlemen:
On March 12, 2012, the Nuclear Regulatory Commission issued an order (Reference 1) to Wolf Creek Nuclear Operating Corporation (WCNOC). Reference 1 was immediately effective and directs WCNOC to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 to Reference 1.
Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) was issued August 30, 2012. The purpose of this letter is to provide the initial status report pursuant to Section IV, P.O. Box 411 / Burlington, KS 66839 / Phone: (620) 364-8831 An Equal Opportunity Employer M/F/HCNVET /ý 0 ý.
ET 12-0029 Page 2 of 3 Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms WCNOC has received Reference 2 and is in the process of evaluating the guidance for the purpose of establishing mitigation strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event as described in Attachment 2 to Reference 1.
Major activities completed during this reporting period:
- Additional portable equipment was ordered prior to the issuance of Reference 2, as described in an NEI letter to the NRC (Reference 3);
- A site-specific evaluation is in progress to establish the coping capabilities as defined in NEI 12 06, Revision 0 (Reference 4);
" Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.
Planned activities for the next six months:
- Development and submittal of the overall integrated plan.
Project milestones schedule through completion of installation and testing:
- A project milestones schedule will be provided with the overall integrated plan.
" Implementation of the order will be completed for Wolf Creek Generating Station prior to startup from Refueling Outage 20, which is scheduled to begin in January 2015.
Technical difficulties encountered that could affect the ability to provide WCNOC's February 28, 2013, submittal:
0 None at this time.
This letter contains no new commitments. If you have any questions concerning this matter, please contact me at (620) 364-4085, or Mr. Gautam Sen at (620) 364-4175.
Sincerely, P. Broschak JPB/rlt cc: E. E. Collins (NRC)
E. J. Leeds (NRC)
C. F. Lyon (NRC)
N. F. O'Keefe (NRC)
Senior Resident Inspector (NRC)
ET 12-0029 Page 3 of 3 STATE OF KANSAS )
) SS COUNTY OF COFFEY )
John P. Broschak, of lawful age, being first duly sworn upon oath says that he is Vice President Engineering of Wolf Creek Nuclear Operating Corporation; that he has read the foregoing document and knows the contents thereof; that he has executed the same for and on behalf of said Corporation with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.
By JoVP. Broschak Vi ePresident Engineering SUBSCRIBED and sworn to before me this 2q day of Oc---Jr ,2012.
GAYLE SHEPH7,7-A,.D NotaW'Public IM& Notary Public -tate of Kansas My Appt. Expires Expiration Date___________