MONTHYEARML24306A2192024-11-0101 November 2024 Results of the Steam Generator Tube Inservice Inspection During the 26th Refueling Outage to Reflect TSTF-577 Reporting Requirements IR 05000482/20244202024-10-31031 October 2024 Security Baseline Inspection Report 05000482/2024420 05000482/LER-2024-001-01, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-10-22022 October 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing ML24296B1902024-10-22022 October 2024 10 CFR 50.55a Requests for the Fifth Ten-Year Interval Inservice Testing Program 05000482/LER-2024-002, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-10-21021 October 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information ML24199A1712024-09-17017 September 2024 Issuance of Amendment No. 241 Revise Ventilation Filter Testing Program Criteria and Administrative Correction of Absorber in Technical Specification 5.5.11 ML24260A0712024-09-12012 September 2024 License Amendment Request for a Risk-Informed Resolution to GSI-191 IR 05000482/20240102024-09-10010 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000482/2024010 (Public) ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24248A2492024-09-0404 September 2024 Inservice Inspection Program Fourth Interval, Third Period, Refueling Outage 26 Owner’S Activity Report ML24248A0762024-09-0404 September 2024 Containment Inservice Inspection Program Third Interval, Second Period, Refueling Outage 26 Owner’S Activity Report ML24241A2212024-08-29029 August 2024 Notice of Enforcement Discretion for Wolf Creek Generating Station ML24240A2642024-08-27027 August 2024 Corporation - Request for Notice of Enforcement Discretion Regarding Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24227A5562024-08-14014 August 2024 Application to Revise Technical Specifications to Adopt TSTF-569-A, Revision 2, Revision of Response Time Testing Definitions ML24213A3352024-07-31031 July 2024 License Amendment Request to Revise Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)) (Fq Methodology), to Implement the Methodology from WCAP-17661-P-A, Revision 1. ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) IR 05000482/20240022024-07-18018 July 2024 Integrated Inspection Report 05000482/2024002 05000482/LER-2024-001, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-07-0202 July 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing IR 05000482/20244012024-07-0202 July 2024 Security Baseline Inspection Report 05000482/2024401 ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24150A0562024-05-29029 May 2024 Foreign Ownership, Control or Influence (FOCI) Information – Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML23345A1602024-05-0909 May 2024 Revision of Safety Evaluation for Amendment No. 237 Request for Deviation from Fire Protection Requirements ML24089A2622024-04-29029 April 2024 Financial Protection Levels ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24118A0022024-04-27027 April 2024 Wolf Generating Nuclear Station - 2023 Annual Radiological Environmental Operating Report ML24113A1882024-04-19019 April 2024 Foreign Ownership, Control or Influence Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML24109A1842024-04-18018 April 2024 Cycle 27 Core Operating Limits Report ML24109A1212024-04-18018 April 2024 (WCGS) Form 5 Exposure Report for Calendar Year 2023 IR 05000482/20240012024-04-17017 April 2024 Integrated Inspection Report 05000482/2024001 ML24114A1442024-04-15015 April 2024 Redacted Updated Safety Analysis Report (WCGS Usar), Revision 37 ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information ML24098A0052024-04-0707 April 2024 2023 Annual Environmental Operating Report ML24089A0972024-03-29029 March 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24089A1352024-03-29029 March 2024 10 CFR 50.46 Annual Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes ML24074A3312024-03-14014 March 2024 Missed Quarterly Inspection Per 40 CFR 266 Subpart N ML24080A3452024-03-11011 March 2024 7 of the Wolf Creek Generating Station Updated Safety Analysis Report IR 05000482/20240122024-03-11011 March 2024 Fire Protection Team Inspection Report 05000482/2024012 ML24016A0702024-03-0808 March 2024 Issuance of Amendment No. 240 Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML24068A1992024-03-0707 March 2024 Changes to Technical Specification Bases - Revisions 93 and 94 ML24066A0672024-03-0505 March 2024 4-2022-024 Letter - OI Closure to Licensee ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24059A1702024-02-28028 February 2024 Annual Fitness for Duty Program Performance Report, and Annual Fatigue Report for 2023 ML24026A0212024-02-27027 February 2024 Issuance of Amendment No. 239 Modified Implementation Date of License Amendment No. 238 2024-09-06
[Table view] |
Text
W LF CREEK 'NUCLEAR OPERATING CORPORATION November 27, 2012 John P. Broschak Vice President Engineering ET 12-0032 U. S. Nuclear Regulatory Commission Attn: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
Reference:
- 1) Letter dated March 12, 2012 from E. J. Leeds and M. R. Johnson, USNRC, to WCNOC, "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident"
- 2) Letter dated May 31, 2012 from D. L. Skeen, USNRC, to A. P.
Heymer, NEI, "Endorsement of Electric Power Research Institute (EPRI) Draft Report 1025286, 'Seismic Walkdown Guidance'"
Subject:
Docket No. 50-482: Wolf Creek Nuclear Operating Corporation 180-Day Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.3 (Seismic) of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Gentlemen:
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Reference 1 to Wolf Creek Nuclear Operating Corporation (WCNOC). Enclosure 3 of Reference 1 contains specific Requested Actions, Requested Information, and Required Responses associated with Near-Term Task Force (NTTF) Recommendation 2.3 (Seismic). This letter provides WCNOC's 180-day response to Reference 1 for NTTF Recommendation 2.3 (Seismic) for Wolf Creek Generating Station (WCGS).
For NTTF Recommendation 2.3 (Seismic), Enclosure 3, item 2 of Reference 1 requires that within 180 days of the NRC's endorsement of the walkdown process (Reference 2), WCNOC will submit its final response.
P.O. Box 411 / Burlington, KS 66839 / Phone: (620) 364-8831 An Equal Opportunity Employer M/F/HCNET
ET 12-0032 Page 2 of 3 The enclosure to this letter contains WCNOC's final response to Reference 1, Enclosure 3, "Recommendation 2.3: Seismic." The enclosure includes a list of any areas that were unable to be inspected due to inaccessibility and a schedule for when the walkdown will be completed.
Regulatory commitments made by WCNOC in this response are identified in the attachment to this letter. If you have any questions concerning this matter, please contact me at (620) 364-4085, or Mr. Gautam Sen at (620) 364-4175.
Sincerely,
- John P. Broschak JPB/rlt
Attachment:
List of Regulatory Commitments
Enclosure:
WCAP-17678-NP, Revision 0, "Wolf Creek Generating Station Post-Fukushima NTTF 2.3 Seismic Walkdown Submittal Report" cc: E. E. Collins (NRC), w/a, w/e E. J. Leeds (NRC), w/a, w/e C. F. Lyon (NRC), w/a, w/e N. F. O'Keefe (NRC), w/a, w/e Senior Resident Inspector (NRC), w/a, w/e
ET 12-0032 Page 3 of 3 STATE OF KANSAS ))ss COUNTY OF COFFEY )
John P. Broschak, of lawful age, being first duly sworn upon oath says that he is Vice President Engineering of Wolf Creek Nuclear Operating Corporation; that he has read the foregoing document and knows the contents thereof; that he has executed the same for and on behalf of said Corporation with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.
.nt Engineering SUBSCRIBED and sworn to before me this 21 day of A/otlpbelr ,2012.
GAYLE SHEPHEARD1 Notar ublic C Notary Public - State of Kansas My Appt. Expires Expiration Date
Attachment to ET 12-0032 Page 1 of 1 LIST OF REGULATORY COMMITMENTS The following table identifies those actions committed to by Wolf Creek Nuclear Operating Corporation in this document. Any other statements in this letter are provided for information purposes and are not considered regulatory commitments. Please direct questions regarding these commitments to Mr. Gautam Sen, Manager Regulatory Affairs at Wolf Creek Generating Station, (620) 364-4175.
REGULATORY COMMITMENT DUE DATE The walkdown and area walk-bys of equipment inaccessible during the Prior to startup from scheduled at-power walkdown dates will be performed prior to startup Refueling Outage 19 from the next refueling outage, presently scheduled for Spring 2013.
Supplemental inspections of 6 electrical cabinets to conform to EPRI/NRC Prior to startup from guidance of FAQ 4.20 will be performed prior to startup from the next Refueling Outage 19 refueling outage, presently scheduled for Spring 2013.