MONTHYEARNRC 2023-0013, Response to Regulatory Information Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-07-0707 July 2023 Response to Regulatory Information Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations NRC 2023-0006, Post-Exam Submittal Cover Letter2023-03-0101 March 2023 Post-Exam Submittal Cover Letter NRC 2023-0005, Report of Changes to Emergency Plan2023-02-21021 February 2023 Report of Changes to Emergency Plan NRC 2022-0032, Sixth 10-Year Interval Inservice Testing (1ST) Program Plan2022-09-30030 September 2022 Sixth 10-Year Interval Inservice Testing (1ST) Program Plan NRC 2022-0025, License Amendment Request 295, Beacon Power Distribution Monitoring System2022-09-26026 September 2022 License Amendment Request 295, Beacon Power Distribution Monitoring System NRC 2022-0019, Report of Changes to Emergency Plan2022-07-13013 July 2022 Report of Changes to Emergency Plan NRC 2022-0022, Response to Request for Supplemental Information (Rsi) Regarding License Amendment Request (LAR) 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2,2022-07-11011 July 2022 Response to Request for Supplemental Information (Rsi) Regarding License Amendment Request (LAR) 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, NRC 2022-0015, Fall 2021 Unit 2 (U2R38) Steam Generator Tube Inspection Report2022-04-27027 April 2022 Fall 2021 Unit 2 (U2R38) Steam Generator Tube Inspection Report NRC 2022-0014, 2021 Annual Monitoring Report2022-04-14014 April 2022 2021 Annual Monitoring Report NRC 2021-0012, Core Operating Limits Report (COLR) Unit 1 Cycle 41 (U 1 C41)2022-04-0707 April 2022 Core Operating Limits Report (COLR) Unit 1 Cycle 41 (U 1 C41) NRC 2022-0003, License Amendment Request 296, Application for Technical Specification Improvement to Eliminate Requirements for Post-Accident Systems Using the Consolidated Line Item Improvement Process2022-03-25025 March 2022 License Amendment Request 296, Application for Technical Specification Improvement to Eliminate Requirements for Post-Accident Systems Using the Consolidated Line Item Improvement Process NRC 2022-0006, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2022-02-22022 February 2022 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections NRC 2022-0004, Report of Changes to Emergency Plan2022-02-0909 February 2022 Report of Changes to Emergency Plan NRC 2022-0005, Refueling Outage U2R38 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2022-02-0101 February 2022 Refueling Outage U2R38 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2022-0001, Report of Changes to Emergency Plan2022-01-11011 January 2022 Report of Changes to Emergency Plan NRC 2021-0046, Core Operating Limits Report (COLR) Unit 2 Cycle 39 (U2C39) and Changes to Unit 1 COLR Unit 1 Cycle 40 (U1C40)2021-10-28028 October 2021 Core Operating Limits Report (COLR) Unit 2 Cycle 39 (U2C39) and Changes to Unit 1 COLR Unit 1 Cycle 40 (U1C40) NRC 2021-0031, Registration of Holtec Hi STORM Casks HI-STORM-37-054, HI-STORM-37-055, and HI-STORM-37-0562021-07-15015 July 2021 Registration of Holtec Hi STORM Casks HI-STORM-37-054, HI-STORM-37-055, and HI-STORM-37-056 NRC 2021-0027, Registration of Holtec Historm Casks HISTORM-37-051, HISTORM-37-052, and HISTORM-37-0532021-06-30030 June 2021 Registration of Holtec Historm Casks HISTORM-37-051, HISTORM-37-052, and HISTORM-37-053 NRC 2021-0028, Generic Letter 2004-02 Containment Sump Debris Transport Calculation Non-Conservatism2021-06-23023 June 2021 Generic Letter 2004-02 Containment Sump Debris Transport Calculation Non-Conservatism NRC 2021-0021, 2020 Annual Monitoring Report2021-04-29029 April 2021 2020 Annual Monitoring Report NRC 2021-0019, Response to Regulatory Information Summary 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to Regulatory Information Summary 2021-01 Preparation and Scheduling of Operator Licensing Examinations NRC-2021-0010, CFR 50.59 Evaluation and Commitment Change Summary Report2021-04-0202 April 2021 CFR 50.59 Evaluation and Commitment Change Summary Report NRC-2021-0011, Technical Specification Bases and Technical Requirement Manual Change Summary2021-04-0202 April 2021 Technical Specification Bases and Technical Requirement Manual Change Summary NRC 2021-0006, Report of Changes to Emergency Plan2021-03-18018 March 2021 Report of Changes to Emergency Plan NRC 2021-0005, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 2004-022021-02-11011 February 2021 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 2004-02 NRC 2021-0002, Refueling Outage U1 R39 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2021-01-21021 January 2021 Refueling Outage U1 R39 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2021-0003, Refueling 39 (U1 R39) Reactor Coolant Pump Analytical Evaluation Report2021-01-21021 January 2021 Refueling 39 (U1 R39) Reactor Coolant Pump Analytical Evaluation Report NRC 2021-0001, Report of Changes to Emergency Plan2021-01-13013 January 2021 Report of Changes to Emergency Plan NRC 2020-0044, Response to Request for Additional Information Request for Exemption from 10 CFR 73, Appendix B, Section VI Regarding Annual Force-On-Force Exercise2020-12-0808 December 2020 Response to Request for Additional Information Request for Exemption from 10 CFR 73, Appendix B, Section VI Regarding Annual Force-On-Force Exercise NRC 2020-0032, Application for Subsequent Renewed Facility Operating Licenses2020-11-16016 November 2020 Application for Subsequent Renewed Facility Operating Licenses NRC 2020-0039, Core Operating Limits Report (COLR) Unit 1 Cycle 40 (U1 C40)2020-11-0202 November 2020 Core Operating Limits Report (COLR) Unit 1 Cycle 40 (U1 C40) NRC 2020-0031, NextEra Energy Point Beach, LLC Response to Apparent Violation in NRC Inspection Report 05000266/2020012, 05000301/2020012: EA-20-0812020-10-0505 October 2020 NextEra Energy Point Beach, LLC Response to Apparent Violation in NRC Inspection Report 05000266/2020012, 05000301/2020012: EA-20-081 NRC 2020-0029, Supplement to License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-09-15015 September 2020 Supplement to License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0024, Response to Request for Additional Information Request for Exemption from Certain Operator Requalification Requirements2020-08-17017 August 2020 Response to Request for Additional Information Request for Exemption from Certain Operator Requalification Requirements NRC 2020-0020, License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-08-13013 August 2020 License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0023, NextEra Energy Point Beach, LLC - Revised Response to Regulatory Information Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations2020-08-12012 August 2020 NextEra Energy Point Beach, LLC - Revised Response to Regulatory Information Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations NRC 2020-0021, Response to NRC Inspection Report and Preliminary White Finding2020-08-12012 August 2020 Response to NRC Inspection Report and Preliminary White Finding NRC 2020-0018, Report of Changes to Emergency Plan2020-07-15015 July 2020 Report of Changes to Emergency Plan NRC-2020-0016, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-12012 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic NRC 2020-0012, Refueling Outage U2R37 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2020-05-20020 May 2020 Refueling Outage U2R37 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2020-0008, Report of Changes to Emergency Plan2020-04-0606 April 2020 Report of Changes to Emergency Plan NRC 2020-0007, Core Operating Limits Report (COLR) Unit 2 Cycle 28 (U2C38)2020-03-27027 March 2020 Core Operating Limits Report (COLR) Unit 2 Cycle 28 (U2C38) NRC 2020-0003, License Amendment Request 289: Tornado Missile Protection Licensing Basis2020-02-0606 February 2020 License Amendment Request 289: Tornado Missile Protection Licensing Basis NRC 2020-0001, Pressure Temperature Limits Report (PTLR)2020-01-0909 January 2020 Pressure Temperature Limits Report (PTLR) NRC 2019-0044, Report of Changes to Emergency Plan2019-11-0101 November 2019 Report of Changes to Emergency Plan NRC 2019-0036, Submittal of 2018 Update to Final Safety Analysis Report2019-10-18018 October 2019 Submittal of 2018 Update to Final Safety Analysis Report NRC 2019-0037, Technical Specification Bases Change Summary2019-10-18018 October 2019 Technical Specification Bases Change Summary NRC 2019-0034, Technical Requirements Manual Change Summary2019-10-18018 October 2019 Technical Requirements Manual Change Summary NRC 2019-0032, CFR 50.59 Evaluation and Commitment Change Summary Report2019-10-18018 October 2019 CFR 50.59 Evaluation and Commitment Change Summary Report NRC 2019-0042, NextEra Energy Point Beach, LLC, Relief Request 1-RR-13 and 2-RR-13, Response to Request for Additional Information2019-10-17017 October 2019 NextEra Energy Point Beach, LLC, Relief Request 1-RR-13 and 2-RR-13, Response to Request for Additional Information 2023-07-07
[Table view] |
Text
NEXTera**
ENERGY~
September 12, 2013 NRC 2013-0087 Order No. EA-12-049 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Docket 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 NextEra Energy Point Beach, LLC's Request for Schedule Relaxation from NRC Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
References:
(1) NRC Order Number EA-12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012 (ML12056A045)
(2) NextEra Energy Point Beach, LLC's letter to USNRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 22, 2013 (ML13053A401)
This letter transmits a request for relaxation of the schedule requirements contained in Nuclear Regulatory Commission ("NRC" or "Commission") Order EA-12-049. On March 12, 2012, the NRC issued an Order (Reference 1) to NextEra Energy Point Beach, LLC. Reference 1 was immediately effective and directs NextEra Energy Point Beach, LLC to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event.
Section IV of NRC Order EA-12-049 (Reference 1) states that licensees proposing to deviate from requirements contained in NRC Order EA-12-049 may request that the Director, Office of Nuclear Reactor Regulation, relax those requirements.
In accordance with Section IV of NRC Order EA-12-049, NextEra Energy Point Beach, LLC is requesting that the Director, Office of Nuclear Reactor Regulation, relax the requirement for completion of full implementation for Point Beach Nuclear Plant Unit 1 as prescribed in Section IV.A.2 of NRC Order EA-12-049 as described in the attachment to this letter.
NextEra Energy Point Beach, LLC considers that, upon approval by the NRC, the alternative full implementation dates regarding NRC Order EA-12-049 proposed in the attachment will NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241
Document Control Desk Page 2 constitute a condition of the NRC Order EA-12-049 for Point Beach Nuclear Plant, Units 1 and 2. Therefore, there are no new regulatory commitments contained in this letter.
If you have any questions regarding this report, please contact Mr. Michael Millen, Licensing Manager, at (920) 755-7845.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on September 12, 2013.
Very truly yours, NextEra Energy Point Beach, LLC Lar yer Site Vice President
Attachment:
cc: Director, Office of Nuclear Reactor Regulation Administrator, Region Ill, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC Project Manager, Point Beach Nuclear Plant, USNRC
ATTACHMENT REQUEST FOR SCHEDULE RELAXATION OF NRC ORDER EA-12-049 REQUIREMENT IV.A.2 FOR POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 Relaxation Request:
Pursuant to the procedure specified in Section IV of Nuclear Regulatory Commission (NRC)
Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (Reference 1), Point Beach Nuclear Plant, Units 1 and 2, hereby submits a request for schedule relaxation from the Order requirements for completion of full implementation no later than two (2) refueling cycles after submittal of the overall integrated plan, as required in Condition C.1.a of the Order, or December 31, 2016, whichever occurs first.
Order Requirement from Which Relaxation is Requested:
NRC Order EA-12-049,Section IV.A.2 requires completion of full implementation of the Order requirements no later than two (2) refueling cycles after submittal of the overall integrated plan, as required by Condition C.1.a or December 31, 2016, whichever comes first. In accordance with the requirements of the Order, NextEra Energy Point Beach, LLC submitted the Point Beach Nuclear Plant, Units 1 and 2, Mitigation Strategies Overall Integrated Plan (Reference 2) on February 22, 2013. The Point Beach Nuclear Plant, Units 1 and 2, Mitigation Strategies Overall Integrated Plan milestone schedule identified the completion dates for full implementation of NRC Order EA-12-049 as October 2014 for Unit 1, and October 2015 for Unit 2, in order to satisfy the requirements of NRC Order EA-12-049.
Justification for Relaxation Request:
NRC Order EA-12-049 requires the development, implementation, and maintenance of guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Per Order EA-12-049, Point Beach Nuclear Plant Unit 1 first refueling outage started March 18, 2013. Point Beach Nuclear Plant Unit 1 second refueling outage and full completion date is October 2014, which effectively reduces implementation to 18 months. As described in the Overall Integrated Plan for Point Beach Nuclear Plant, Units 1 and 2 (Reference 2), some of these mitigation strategies are complex and require an outage on both Units to implement because of the Point Beach Nuclear Plant two unit design and common structures, systems, and components (SSCs), e.g.,
auxiliary feedwater unit cross connections. Modifications are being designed at risk based on mitigation strategies prior to receipt of a safety evaluation report (SER).
NRC issuance of an SER has been delayed due to complexities in generic strategies and limited Licensee and NRC resources to perform design and analysis activities, conduct reviews, and address requests for additional information. Implications of failure of Westinghouse SHIELD passive thermal shutdown seal (SDS) for reactor coolant pumps are being assessed.
Resolution of issues may require additional analytical work and/or changes in mitigation strategies that change implementation plans. Mitigation strategy programmatic controls, procedures and training will need to reflect that the final mitigating strategy functional requirements for Point Beach Nuclear Plant Unit 1, Point Beach Nuclear Plant Unit 2, and Page 1 of 2
ATTACHM ENT REQUEST FOR SCHEDULE RELAXATION OF NRC ORDER EA-12-049 REQUIREM ENT IV.A.2 FOR POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 common SSCs. Due to the integrated nature of the Point Beach Nuclear Plant mitigation strategies, partial functional scope compliance is not feasible.
Thus, it is not reasonable to achieve full implementation of the mitigation strategies for Point Beach Nuclear Plant Unit 1 in accordance with NRC Order EA-12-049, by the Order requirement date of no later than two (2) refueling cycles after submittal of the overall integrated plan, as required by Condition C.1.a or December 31, 2016, whichever comes first, since NRC issuance of an SER is essential to the full implementation of mitigation strategies required by NRC Order EA-12-049, as described above.
Accordingly, NextEra Energy Point Beach , LLC requests that the NRC Order EA-12-049,Section IV.A.2, full implementation requirement dates for Point Beach Nuclear Plant, Units 1 and 2, be relaxed to the following milestones:
Point Beach Nuclear Plant Unit 1 - May 2016 Point Beach Nuclear Plant Unit 2- October 2015 The schedule relaxation for Point Beach Nuclear Plant Unit 1 reduces risk to safety through the reduction in modification rework. Full implementation for Point Beach Nuclear Plant Unit 1 in May 2016 aligns with other NextEra Energy plants to permit resolution of generic issues while work continues on Point Beach Nuclear Plant low risk mitigation strategies and associated modifications, e.g., electrical and mechanical connections for portable equipment and hardened storage for portable equipment. The schedule relaxation for Point Beach Nuclear Plant Unit 1 results in extending the Point Beach Nuclear Plant site implementation seven months from October 2015 to May 2016, which continues to meet the December 31, 2016 backstop date of NRC Order EA-12-049.
==
Conclusion:==
As described above, compliance with NRC Order EA-12-049 schedule requirement for full completion of implementation of mitigation strategies would result in hardship or unusual difficulty without a compensating increase in the level of safety. Therefore, in accordance with the provisions of Section IV of the Order, we request relaxation of the requirement described in Section IV.A.2
References:
- 1. NRC Order Number EA-12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012
- 2. NextEra Energy Point Beach, LLC's letter to USNRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 22, 2013 Page 2 of 2