NRC Staff Slides South Texas Project Risk-Informed Generic Safety Issue - 191, December 16, 2013
ML13352A124
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 12/16/2013
From: Balwant Singal
Plant Licensing Branch IV
To: Koehl D
South Texas
Singal B
References
GSI-191
Download: ML13352A124 (4)


Text

NRC Staff slides South Texas Project Risk-Informed Generic Safety Issue - 191 December 16, 2013 1

Agenda

  • Introductions
  • Description of major changes in November 13, 2013 submittal (ML3323A128).
  • NRC review plan and schedule.
  • Identify next steps and path forward.
  • Public questions of staff
  • Adjourn 2

Draft Milestone Schedule Item Target Date Provide draft RAIs to PM 2/10/2014 PM issues final RAIs to licensee 3/3/2014 Licensee response to round 1 RAIs (30 day review) 4/9/2014 Staff & licensee meet with ACRS subcommittee for 1st time 5/14/2014 Staff reviews round 1 RAIs for 90 days; provides PM with draft SE & round 2 RAIs 7/8/2014 Licensee responds to round 2 RAIs (30 day review) 8/7/2014 Staff conducts audit ~45 days after response to round 2 RAIs 9/21/2014 Staff issues draft environmental assessment (EA) 10/6/2014 Staff issues no significant hazards determination 10/6/2014 Staff and licensee meet with ACRS subcommittee for 2nd time 11/15/2014 3

Draft Milestone Schedule Item Target Date Address all public comments on draft EA and issue final EA 12/20/2014 Staff provides PM with complete SE input or draft SE with round 3 RAIs 2/2/2015 Licensee responds to round 3 RAIs (30 day review) 3/4/2015 Technical staff issues complete draft SE to DORL 6/2/2015 Staff & licensee meet with ACRS subcommittee for 3rd time 7/1/2015 Staff and licensee meet with full ACRS 8/5/2015 ACRS issues final letter 9/16/2015 DORL issues final SE 11/13/2015 Staff provides PM with complete SE input or draft SE with round 3 RAIs 2/2/2015 4