ML15334A397

From kanterella
Jump to navigation Jump to search

TS 5 3 2 Emergency LAR Pre-Submittal Meeting Presentation
ML15334A397
Person / Time
Site: South Texas STP Nuclear Operating Company icon.png
Issue date: 11/30/2015
From: Lisa Regner
Plant Licensing Branch IV
To:
Regner L, NRR/DORL/LPLIV-1
References
TAC MF7116
Download: ML15334A397 (29)


Text

STPNOC Planned License Amendment Request:

Technical Specification 5.3.2, Control Rod Assemblies STP

Participants:

Michael Murray, Regulatory Affairs Manager Roland Dunn, Nuclear Fuel and Analysis Manager Michael Berg, Design Engineering Manager Wendy Brost, Licensing Engineer STPNOC/NRC Pre-Submittal Meeting December 1, 2015

Objectives

  • Provide a description of the Unit 1 D-6 Control Rod Drive Mechanism (CRDM) issue
  • Provide overview of planned implementation actions
  • Provide overview of expected License Amendment Request (LAR) content
  • Discuss planned submittal date and need date
  • Answer NRC questions 2

Presentation Outline

  • Overview of Proposed Change
  • Background
  • Plant Changes Required
  • Impact on Safety Analyses
  • Regulatory Evaluation
  • Summary Conclusions
  • Proposed Schedule
  • Additional Questions and Recap 3

Problem Statement

  • Control Rod D-6 could not be reliably withdrawn during startup testing 4

Overview of Proposed Change

  • Requesting proposed amendment to allow Unit 1 to resume operation with 56 full-length control rod assemblies
  • Proposed change to TS 5.3.2 (change bar on right):

5

Overview of Proposed Change

  • There is no methodology change involved with this change to the TS
  • The proposed change would last through the end of Unit 1 Cycle 20
  • One cycle of operation
  • TS requirement to contain 57 control rods will remain unchanged for Unit 2 6

Control Rod Configuration

  • Rod D-6 is a Shutdown Bank rod normally positioned fully withdrawn at power
  • 29 Control Bank Rods
  • 28 Shutdown Bank Rods 7

Background -

CRDM Description 8

9 Background - Rod Holdout Lock Ring

  • Deformation in D-6 Rod Holdout lock ring
  • Initiated in 2012 during rod control sequencing while unlocking control rods
  • Source of sequencing issue has been addressed with a design change

Background -

Condition of Control Rod D-6

  • D-6 unable to be moved using normal methods during troubleshooting
  • CRDM for Rod D-6 has been visually inspected and compared to another CRDM
  • Confirming that this issue is confined to the CRDM for Rod D-6 10

Extent of Condition

  • Deformation on lockout ring is only seen on Unit 1 Rod D-6 CRDM
  • Extent of condition - other 56 rods unaffected
  • Visual inspection has been performed on other 56 CRDMs
  • CRDM monitoring (coil traces) indicate other 56 CRDMs are operating reliably
  • Plans for future monitoring
  • On startup: CRDM testing, rod drop timing testing
  • Continue to evaluate coil traces
  • Unit 2 CRDMs have been monitored and indicate reliable operation 11

Background -

Pressure Boundary 12

  • Components being removed are internal to the RCS pressure boundary
  • Pressure boundary:

butt weld between CRDM latch housing and rod travel housing

D-6 CRDM Replacement

  • In-situ CRDM replacement would be a first-of-a-kind activity in United States
  • Requires special tooling that does not currently exist
  • Lengthy preparation required for building mockup, testing, developing/obtaining tools 13

Plant Changes Required

  • Remove Rod Cluster Control Assembly (RCCA) and associated drive shaft at core location D-6
  • Some plant changes to Digital Rod Position Indication (DRPI) and Rod Control systems are required
  • Install guide tube flow restrictor and fuel assembly thimble plug to maintain core and vessel thermal hydraulic characteristics
  • Revise Reload Safety Evaluation to include impact of control rod removal on nuclear design and safety analyses
  • Revise affected procedures and design documents 14

Thermal Hydraulic, Seismic and Structural Impacts

  • Insertion of guide tube flow restrictor and thimble plug device maintain flow characteristics equivalent to previous configuration
  • Dynamic analysis (seismic and loss of coolant accident forces) of the CRDM that was performed using the reactor equipment system model remains valid after removal of the D-6 control rod drive shaft and RCCA
  • Drive shaft does not provide stiffening function - free motion 15

Impact on Safety Analyses

  • Rod D-6 is a Shutdown Bank RCCA
  • Accidents where at-power core power distribution is a key factor are not affected
  • Evaluated Rod D-6 removal impacts
  • Boron worth when all RCCAs are inserted
  • Rod worth of adjacent RCCAs when all RCCAs are inserted
  • Trip reactivity as a function of time
  • Most positive Moderator Density Coefficient (MDC) 16

Impact on Safety Analyses -

Available Shutdown Margin

  • UFSAR Chapter 15 safety analyses remain bounding
  • Actual shutdown margin reduced from 2.43% to 2.18% for Modes 1 and 2 at End of Life (EOL)
  • 1.3% limit for Modes 1 and 2 currently specified in COLR Section 2.3.1 is met 17

Impact on Shutdown Margin (EOL Values Below) 18

Impact on Safety Analyses -

Boron Worth

  • Rod removal impacts boron worth for the all-rods inserted condition
  • Analysis conservatively determines a boron worth with all rods out, therefore there is no impact with D-6 removed from the core 19

Impact on Safety Analyses -

Rod Worth of Adjacent Rods

  • Removal of Rod D-6 slightly increases the rod worth of the adjacent control rods with all RCCAs inserted
  • Potential impact to results of uncontrolled RCCA bank withdrawal from a subcritical or low power startup conditions and spectrum of rod ejection accidents
  • Change in rod worth is considered and is bounded by the current analysis 20

Impact on Safety Analyses -

Trip Reactivity

  • Removal of Rod D-6 reduces the trip reactivity as a function of rod insertion position
  • The revised trip reactivity insertion vs. position remains greater than values required by the UFSAR Chapter 15 analysis
  • There is no adverse impact to analyses for events where a reactor trip occurs 21

Impact on Safety Analyses -

Moderator Density Coefficient (MDC)

  • The most positive MDC is conservatively calculated assuming all rods in the core
  • Updated MDC without rod D-6 remains bounded by the limiting value assumed in the Chapter 15 safety analysis 22

Impact to UFSAR Chapter 15 Accident Analyses

  • Postulated accidents dependent on core power distributions while at power are not impacted
  • Therefore, the removal of RCCA D-6 does not adversely impact the results presented in Chapter 15 23

Regulatory Evaluation

  • Requesting proposed amendment to allow Unit 1 to resume operation with 56 fuel assemblies for Unit 1 Cycle 20
  • No other changes to STP TS required
  • Applicable General Design Criteria have been reviewed and are satisfied
  • These items will be discussed in the proposed LAR 24

Overview of Proposed Change

  • Proposed change to TS 5.3.2 (change bar on right):

25

Summary Conclusions

  • Appropriate safety margins maintained with 56 rods
  • One fuel cycle change (Unit 1 Cycle 20)
  • Why is this TS change needed?
  • As previously discussed, first of a kind change in the United States for CRDM replacement requiring a pressure boundary weld
  • Significant planning and remote tooling development is required to ensure no unforeseen impact to RCS pressure boundary and associated components 26

Summary Conclusions

  • TS change does not involve a methodology change
  • Instrumentation setpoints and trip settings will not be affected
  • No new operator actions are proposed
  • Installation of flow restrictor and thimble plug -

negligible impact on thermal hydraulics

  • Input will be provided for No Significant Hazards Consideration determination 27

Proposed Schedule

  • Submit LAR to NRC December 4, 2015
  • Approval of the proposed amendment is requested by December 11, 2015 to support Unit 1 entry into Mode 5 and resume operation
  • Planned implementation of LAR actions within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />
  • Change will remain in effect for the duration of Unit 1 Cycle 20 28

Additional Questions and Action Recap 29