ML16062A304

From kanterella
Jump to navigation Jump to search

TS 5.3.2 LAR Pre-Submittal Meeting Presentation - March 2, 2016
ML16062A304
Person / Time
Site: South Texas 
Issue date: 03/02/2016
From:
South Texas
To: Lisa Regner
Plant Licensing Branch IV
Regner L, NRR/DORL/LPLIV-1
References
CAC MF7361
Download: ML16062A304 (39)


Text

STPNOC Planned License Amendment Request:

Technical Specification 5.3.2, Control Rod Assemblies STP

Participants:

Michael Murray, Regulatory Affairs Manager Roland Dunn, Nuclear Fuel and Analysis Manager Michael Berg, Design Engineering Manager Duane Gore, Reactor Analysis Supervisor Charles Albury, Reactor Analysis Supervising Engineer Jose Rocha, Design Engineering I&C Supervisor Wendy Brost, Licensing Engineer STPNOC/NRC Pre-Submittal Meeting March 2, 2016

Objectives

  • Describe STPs path forward
  • Provide a description of the Unit 1 D-6 Control Rod Drive Mechanism (CRDM) issue
  • Provide overview of physical configuration changes to support future operation
  • Discuss impact on Chapter 15 Safety Analyses
  • Provide overview of expected License Amendment Request (LAR) content
  • Discuss planned submittal date and need date
  • Answer NRC questions 2

Current Configuration

  • Rod Cluster Control Assembly (RCCA) and associated drive shaft at core location D-6 have been removed
  • Flow restrictor and thimble plug installed
  • Control power to stationary, moveable, and lift coils for D-6 as well as display and alarm functions have been removed
  • Approved to operate Unit 1 in this condition through current fuel cycle (Cycle 20) 3

STPs Path Forward

  • Consequences and uncertainty associated with CRDM replacement are considered significant
  • Requires special tooling and processes that currently do not exist
  • RCS pressure boundary cutting and welding
  • Analyses demonstrates that STP can design future cores with 56 control rods maintaining appropriate safety margins
  • Path forward is a permanent change to the design and licensing basis of the Unit 1 reactor to operate with 56 Control Rods 4

Overview of Proposed Change

  • Requesting proposed amendment to allow Unit 1 to operate with 56 full-length control rod assemblies
  • Proposed change to TS 5.3.2 (change bar on right):

5

Overview of Proposed Change

  • There is no methodology change involved with this change to the TS
  • The proposed change would apply to Unit 1 only
  • TS design description that specifies 57 control rods will remain unchanged for Unit 2 6

Background -

CRDM Description 7

8 Background - Rod Holdout Lock Ring

  • Deformation in D-6 Rod Holdout lock ring
  • Initiated in 2012 during rod control sequencing while unlocking control rods
  • Source of sequencing issue has been addressed with a design change

Extent of Condition

  • Deformation on lockout ring is only seen on Unit 1 Rod D-6 CRDM
  • Extent of condition - other 56 rods unaffected
  • Visual inspection has been performed on other 56 CRDMs
  • CRDM monitoring (coil traces) indicate other 56 CRDMs are operating reliably
  • Plans for future monitoring
  • On startup: CRDM testing, rod drop timing testing
  • Continue to evaluate coil traces
  • Unit 2 CRDMs have been visually inspected and continue to be monitored and indicate reliable operation 9

Decision Inputs -

Repair Evaluation

  • First of a kind evolution in the US (butt weld instead of canopy seal weld)
  • Post-repair maintenance testing
  • Consequences and uncertainty associated with CRDM replacement are considered significant
  • Requires special tooling and processes that currently do not exist
  • RCS pressure boundary cutting and welding 10

Background -

Pressure Boundary 11

  • Components being removed are internal to the RCS pressure boundary
  • Pressure boundary:

butt weld between CRDM latch housing and rod travel housing

Control Rod Configuration

  • Rod D-6 is a Shutdown Bank rod normally positioned fully withdrawn at power
  • 29 Control Bank Rods
  • 28 Shutdown Bank Rods 12

Physical Configuration Changes to Support Future Operation (50.59)

  • Change the plant computer rod supervision program (software) to remove input from D-6 to rod deviation alarm
  • Spare in place the cabling for the D-6 CRDM, Digital Rod Position Indication (DRPI), and RHO cabling
  • Existing guide tube flow restrictor remains in place to maintain flow characteristics
  • Continuing to evaluate for any potential long-term effects of the D-6 removal design change 13

Thermal Hydraulic Impacts

  • Thimble plug will be removed to reduce fuel component handling during core refueling
  • Analysis performed to support removal
  • Causes very small increase in core bypass flow, remains bounded by safety analysis flow 14

Seismic and Structural Impacts

  • Dynamic analysis (seismic and loss of coolant accident forces) of the CRDM that was performed using the reactor equipment system model remains valid after removal of the D-6 control rod drive shaft and RCCA
  • Drive shaft does not provide stiffening function - free motion 15

Safety Analysis - Overview

  • Basis of Methodology
  • Description of Methodology
  • Impact of permanent removal of D-6 RCCA
  • Nuclear (Core) Design Analyses

Safety Analysis -

Basis of Methodology

  • STP Reload Safety Analysis uses NRC approved methodology:
  • WCAP 9272-P-A, Westinghouse Reload Safety Evaluation Methodology, July 1985 17 UFSAR Chapter 15 Bounding Safety Analyses Key Safety Parameters Chapter 15 Cycle-Specific Confirmatory Analyses

Safety Analysis -

Description of Methodology

  • Methodology establishes a bounding safety analysis
  • The performance and safety requirements are met through applicable acceptance limits, for example:
  • Minimum Departure from Nucleate Boiling Ratio (DNBR)
  • Maximum allowable fuel temperature
  • The bounding analyses are described in the UFSAR Chapter 15 18

Safety Analysis -

Safety Analysis Relationships 19 Non-LOCA Transient Analyses LOCA Analyses Key Safety Parameters Nuclear, Thermo-hydraulic, Fuel Rod Design Cycle-specific Analyses UFSAR Chapter 15 Bounding Analyses Chapter 15 Cycle-Specific Confirmatory Analyses

Safety Analysis - Methodology

  • Chapter 15 analyses are evaluated
  • Results presented in Chapter 15 are based on bounding reference core
  • Cycle-specific information is verified against reference core to ensure Chapter 15 results remain bounded 20

Impact on Safety Analyses 21

  • Power distribution within the reactor core during operation is negligibly impacted
  • Rod D-6 is a Shutdown Bank RCCA normally positioned withdrawn at power

Impact of D-6 Removal on Safety Analysis

  • The removal of Control Rod D-6 could impact key safety parameters assumed in the UFSAR Chapter 15 analysis:
  • Boron worth when all RCCAs are inserted
  • Rod worth of the adjacent RCCAs when all RCCAs are inserted
  • Trip reactivity as a function of time
  • Most positive moderator density coefficient (MDC) 22

Impact on Safety Analyses -

Shutdown Margin 23 Unit 1 Cycle Burnup (MWD/MTU)

RCCA Condition Calculated SDM (pcm)

Margin

(%)

17 20400 D-6 present 2708 108 D-6 removed 2276 75 18 19450 D-6 present 2430 87 D-6 removed 2089 61 19 19400 D-6 present 2273 75 D-6 removed 1968 51 20 18610 D-6 present 2432 87 D-6 removed 2173 67

Impact on Safety Analyses -

Boron Worth

  • Rod removal increases boron worth for the all-rods inserted condition
  • Analysis conservatively determines a boron worth with all rods out, therefore there is no impact with D-6 removed from the core 24

Impact on Safety Analyses -

Rod Worth of Adjacent RCCAs

  • Removal of Rod D-6 results in a small increase for the rod worth of the adjacent control rods with all RCCAs inserted, however
  • No impact to the fuel acceptance limits
  • Uncontrolled RCCA bank withdrawal from a subcritical or low power startup conditions and spectrum of rod ejection accidents because shutdown banks are withdrawn
  • Therefore D-6 will not add positive reactivity

Impact on Safety Analyses -

Rod Ejection Accident

  • Rod Ejection N-2 Subcriticality (EOC)
  • The safety limit for subcriticality is keff 0.999, which is met by determining N-2 rod worth is less than actual SDM + worst stuck rod worth
  • 0.9
  • A multi-cycle margin analysis was performed and demonstrates sufficient margin
  • Future cycles will be evaluated to ensure this limit can be met without RCCA D-6 present 26

Impact on Safety Analyses -

Rod Ejection Accident

  • Rod Ejection N-2 Subcriticality (EOC) 27 Unit 1 Cycle Burnup (MWD/MTU)

RCCA Condition N-2 Rod Worth (pcm)

Actual SDM+

WSRW

  • 0.9 (pcm)

Margin

(%)

17 20400 D-6 present 2342 3529 34 D-6 removed 2928 3292 11 18 19450 D-6 present 2273 3301 31 D-6 removed 2815 3053 8

19 19400 D-6 present 2337 3187 27 D-6 removed 2747 2937 6

20 18610 D-6 present 2175 3308 34 D-6 removed 2659 3096 14

Impact on Safety Analyses -

Trip Reactivity

  • Removal of Rod D-6 reduces the total trip reactivity and the trip reactivity as a function of rod position
  • A multi-cycle margin analysis was performed and demonstrates sufficient margin for total trip reactivity
  • Cycle-specific analyses will be performed to ensure trip reactivity values assumed in the bounding Chapter 15 safety analyses are satisfied 28

Impact on Safety Analyses -

Trip Reactivity (HZP)

  • End-of-Cycle (EOC) HZP Trip Reactivity Following Rod Ejection
  • Safety limit is 2000 pcm for HZP 29 Unit 1 Cycle Burnup (MWD/MTU)

RCCA Condition Trip Reactivity (pcm)

Margin

(%)

17 20400 D-6 present 3317 66 D-6 removed 2605 30 18 19450 D-6 present 3145 57 D-6 removed 2504 25 19 19400 D-6 present 2983 49 D-6 removed 2449 22 20 18610 D-6 present 3240 62 D-6 removed 2630 31

Impact on Safety Analyses -

Trip Reactivity (HFP)

  • Trip Reactivity (HFP)
  • The HFP Trip Reactivity value assumed in the Rod Ejection analysis is 4000 pcm 30 Unit 1 Cycle RCCA Condition Trip Reactivity (pcm)

Margin

(%)

17 BOC D-6 present 5211 30 D-6 removed 4716 18 EOC D-6 present 5433 36 D-6 removed 4854 21 18 BOC D-6 present 5037 26 D-6 removed 4543 14 EOC D-6 present 5268 32 D-6 removed 4719 18 19 BOC D-6 present 5071 27 D-6 removed 4574 14 EOC D-6 present 5038 26 D-6 removed 4489 12 20 BOC D-6 present 5112 28 D-6 removed 4625 16 EOC D-6 present 5256 31 D-6 removed 4663 17

Impact on Safety Analyses -

Moderator Density Coefficient (MDC)

  • The safety limit is 0.54 k/gm/cc
  • The most positive MDC is conservatively calculated assuming all rods in the core
  • Impact on the MDC calculation for removal of D-6 removal is very small
  • Cycle-specific nuclear design analysis confirms the safety limit is met 31

Impact on Safety Analyses -

LOCA Analyses

  • Assumptions
  • Flow restrictor in RCCA guide tube is in place
  • No explicit assumption on number of RCCAs
  • Assumptions
  • Flow restrictor in RCCA guide tube is in place
  • No reliance on insertion or number of RCCAs
  • Operation with D-6 removed does not impact the SBLOCA, LBLOCA and LOCA Forces provided that:
  • A flow restrictor remains installed at that location

Impact to UFSAR Chapter 15 Accident Analyses Summary

  • Bounding Chapter 15 Analyses reported in the UFSAR do not assume the number or configuration of RCCAs in the reactor core
  • Cycle-specific analyses performed in accordance with WCAP-9272 will confirm bounding Chapter 15 analyses reported in the UFSAR remain satisfied
  • Trip reactivity
  • Most positive MDC
  • Impact on DNBR will be evaluated on a cycle-specific basis in accordance with WCAP-9272 to confirm current safety analysis limits continue to be met
  • Postulated accidents dependent on core power distributions while at power are not impacted
  • Therefore, the removal of RCCA D-6 does not adversely impact the results presented in Chapter 15 33

Regulatory Evaluation

  • Requesting proposed amendment to allow Unit 1 to operate with 56 control rods
  • No other changes to STP TS required
  • Applicable General Design Criteria will be reviewed and are expected to be satisfied
  • These items will be discussed in the proposed LAR 34

Proposed LAR Content -

Technical Evaluation

  • System description
  • Current licensing basis
  • Impact on the safety analysis
  • Methodology overview
  • Impact on safety parameters
  • Impact on bounding UFSAR Chapter 15 accident analyses
  • Field work required to permanently remove Control Rod D-6 from service
  • Evaluation of potential design impacts
  • Thermal-hydraulic
  • Seismic and structural 35

Overview of Proposed Change

  • Proposed change to TS 5.3.2 (change bar on right):

36

Summary Conclusions

  • Utilizing current core design methodologies, future cores will be designed to remain within the criteria established in the current Chapter 15 Accident Analysis
  • TS will be changed to describe Unit 1 as having 56 control rods
  • No other TS affected
  • Instrumentation setpoints and trip settings will not be affected
  • No new operator actions are proposed
  • Input will be provided for No Significant Hazards Consideration determination 37

Proposed Schedule

  • Submit LAR to NRC March 17, 2016
  • Approval of the proposed amendment is requested by March 2, 2017
  • Prior to the beginning of refueling outage 1RE20
  • Implementation will be prior to restart of Unit 1 Cycle 21 38

Additional Questions and Action Recap 39