ML020600100
ML020600100 | |
Person / Time | |
---|---|
Site: | PROJ0690 |
Issue date: | 03/01/2002 |
From: | Charemagne Grimes NRC/NRR/DRIP/RLEP |
To: | Lochbaum D, Alexis Nelson Nuclear Energy Institute, Union of Concerned Scientists |
Kang P, NRR-RLSB, 415-2279 | |
References | |
SIP Test Sample upto2-6-04 NEI 95-10, Rev 3 | |
Download: ML020600100 (6) | |
Text
March 1, 2002Mr. Alan NelsonNuclear Energy Institute 1776 I Street, NW., Suite 400 Washington, DC 20006-3708Mr. David LochbaumUnion of Concerned Scientists 1707 H Street, NW., Suite 600 Washington, DC 20006-3919
SUBJECT:
PROPOSED STAFF GUIDANCE ON SCOPING OF EQUIPMENT RELIED ONTO MEET THE REQUIREMENTS OF THE STATION BLACKOUT (SBO) RULE (10 CFR 50.63) FOR LICENSE RENEWAL (10 CFR 54.4(a)(3))
Dear Messrs. Nelson and Lochbaum:
On February 14, 2002, the Nuclear Regulatory Commission (NRC) staff met with NuclearEnergy Institute (NEI) and other industry representatives to continue discussion of the subject issue from our earlier meetings that were held on January 10 and 15, 2002. At the February 14 meeting, the staff agreed to re-state the above subject staff guidance to articulate further the staff position on scoping of SBO equipment in accordance with the requirements of the license renewal rule 10 CFR 54.4(a)(3) and the SBO rule (10 CFR 50.63). The staff also agreed to forward the revised staff guidance to NEI and Union of Concerned Scientists within 2 weeks.The staff has revised the proposed staff guidance to incorporate the discussion on theboundary of the recovery equipment that should be within the scope. If you agree with this proposed staff guidance as revised, it is also possible that comparable changes might need to be made to NEI 95-10, Revision 3, "Industry Guidance for Implementing the Requirements of 10 CFR Part 54 - The License Renewal Rule." If you have any questions regarding this matter, please contact Peter Kang at 301-415-2779.Sincerely, /RA/Christopher I. Grimes, Program DirectorLicense Renewal and Environmental Impacts Division of Regulatory Improvement Programs Office of Nuclear Reactor RegulationProject 690
Enclosure:
As stated cc w/encl: See next page Mr. Alan NelsonNuclear Energy Institute 1776 I Street, NW., Suite 400 Washington, DC 20006-3708Mr. David LockbaumUnion of Concerned Scientists 1707 H Street, NW., Suite 600 Washington, DC 20006-3919
SUBJECT:
PROPOSED STAFF GUIDANCE ON SCOPING OF EQUIPMENT RELIED ONTO MEET THE REQUIREMENTS OF THE STATION BLACKOUT (SBO) RULE (10 CFR 50.63) FOR LICENSE RENEWAL (10 CFR 54.4(a)(3))
Dear Messrs. Nelson and Lochbaum:
On February 14, 2002, the Nuclear Regulatory Commission (NRC) staff met with NuclearEnergy Institute (NEI) and other industry representatives to continue discussion of the subject issue from our earlier meetings that were held on January 10 and 15, 2002. At the February 14 meeting, the staff agreed to re-state the above subject staff guidance to articulate further the staff position on scoping of SBO equipment in accordance with the requirements of the license renewal rule 10 CFR 54.4(a)(3) and the SBO rule (10 CFR 50.63). The staff also agreed to forward the revised staff guidance to NEI and Union of Concerned Scientists within 2 weeks.The staff has revised the proposed staff guidance to incorporate the discussion on theboundary of the recovery equipment that should be within the scope. If you agree with this proposed staff guidance as revised, it is also possible that comparable changes might need to be made to NEI 95-10, Revision 3, "Industry Guidance for Implementing the Requirements of 10 CFR Part 54 - The License Renewal Rule." If you have any questions regarding this matter, please contact Peter Kang at 301-415-2779.Sincerely, /RA/Christopher I. Grimes, Program Director License Renewal and Environmental Impacts Division of Regulatory Improvement Programs Office of Nuclear Reactor RegulationProject 690
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION
- See next page C:\Program Files\Adobe\Acrobat 4.0\PDF Output\SBO ltr to NEI (02-25-02).wpd *See Previous ConcurrenceOFFICE NSE:RLEP:DRIP LA SC:RLEP:DRIPNAMEPKang*SLittle*PTKuo*DATE2 /27/022/27/022 /27/02 OFFICEDEOGC PD:RLEP:DRIPNAMEJCalvo*RHoeflingCIGrimes DATE 2/27/02 2/28/02 3/01/02OFFICIAL RECORD COPY DISTRIBUTION
- HARD COPY RLEP RFE. HyltonE-MAIL:PUBLICJ. Johnson W. Borchardt D. Matthews F. Gillespie C. Grimes J. Strosnider (RidsNrrDe)
E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo C. Holden P. Shemanski H. Nieh G. Holahan S. Black B. Boger D. Thatcher G. Galletti B. Thomas R. Architzel J. Moore R. Weisman M. Mayfield A. Murphy W. McDowell S. Droggitis N. Dudley RLEP Staff
A. ThadaniR. Zimmerman C. Julian R. Gardner D. Chyu M. Modes J. Vora NRC Staff Position on the License Renewal Rule (10 CFR 54.4) as it relates to the Station Blackout Rule (10 CFR 50.63)Staff PositionConsistent with the requirements specified in 10 CFR 54.4(a)(3) and 10 CFR 50.63(a)(1), theplant system portion of the offsite power system should be included within the scope of license renewal. The reasons for support of this position follow:RationaleThe license renewal rule, 10 CFR 54.4(a)(3), requires that, "All systems, structures, andcomponents relied on in safety analyses or plant evaluations to perform a function that demonstrates compliance with the Commission's regulations for.....station blackout (10 CFR 50.63)" be included within the scope of license renewal. The station blackout (SBO) rule, 10 CFR 50.63(a)(1), requires that each light-water-cooled nuclear power plant licensed to operate be able to withstand and recover from a station blackout of a specified duration that is based upon factors that include: "(iii) The expected frequency of loss of offsite power; and (iv)
The probable time needed to restore offsite power." The SBO rule in this regard is consistent with the staff findings identified in the statement of considerations and NUREG-1032. In particular, with regard to factor (iv), the staff found that offsite power is more likely to be restored (0.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> median time to restore) than the emergency diesel generators (8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> median time to repair) ending an SBO event.SBO is the loss of offsite and onsite ac electric power to the essential and non-essentialswitchgear buses in a nuclear power plant. It does not include the loss of ac power fed from inverters powered by station batteries nor loss of ac power from an SBO defined alternate ac power source. The SBO rule was added to the regulations in 10 CFR Part 50 because, as operating experience accumulated, concern arose that the reliability of both the offsite and onsite ac power systems might be less than originally anticipated, even for designs that met the requirements of General Design Criteria 17 and 18. As a result, the SBO rule required that nuclear power plants have the capability to withstand and recover from the loss of offsite and onsite ac power of a specified duration (the coping duration). Licensees' plant evaluations followed the guidance specified in NRC Regulatory Guide (RG)1.155 and NUMARC 87-00 to determine their required plant-specific coping duration. The criteria specified in RG 1.155 to calculate a plant-specific coping duration were based upon the expected frequency of loss of offsite power and the probable time needed to restore offsitepower, as well as the other two factors (onsite emergency ac power source redundancy and reliability) specified in 10 CFR 50.63(a)(1). In requiring that a plant's coping duration be based on the probable time needed to restore offsite power, 10 CFR 50.63(a)(1) is specifying that the offsite power system be an assumed method of recovering from an SBO. Disregarding the offsite power system as a means of recovering from an SBO would not meet the requirements of the rule and would result in a longer required coping duration. Enclosure The use of the offsite power system within 10 CFR 50.63(a)(1) as a means of recovering froman SBO should not be construed to be the only acceptable means of recovering from an SBO.
A licensee could recover offsite power or emergency (onsite) power. It is not possible to determine prior to an actual SBO event which source of power can be returned first. As a result, 10 CFR 50.63(c)(1)(ii) and its associated guidance in RG 1.155, Section 1.3 and Section 2, requires procedures to recover from an SBO that include restoration of offsite and onsite power. Based on the above, both the offsite and onsite power systems are relied upon to meet therequirements of the SBO rule. Elements of both offsite and onsite power are necessary to determine the required coping duration under 10 CFR 50.63(a)(1), and the procedures required by 10 CFR 50.63(c)(1)(ii) must address both offsite power and onsite power restoration. It follows, therefore, that both systems are used to demonstrate compliance with the SBO rule and must be included within the scope of license renewal consistent with the requirements of 10 CFR 54.4(a)(3). License renewal applicants are presently including the onsite power system within the scope of license renewal on the basis of the requirements under 10 CFR 54.4 (a)(1)
(safety-related systems). They are also including equipment that is relied upon to cope with an SBO (e.g., alternate ac power sources) on the basis of the requirements under 10 CFR 54.4(a)(3). Only the addition of the offsite power system is therefore necessary to complete the required scope of the electrical power systems under license renewal.The offsite power systems of U.S. nuclear power plants consist of a transmission system (grid)component that provides a source of power and a plant system component that connects that power source to a plant's onsite electrical distribution system which powers safety equipment.
The staff has historically relied upon the well-distributed, redundant, and interconnected nature of the grid to provide the necessary level of reliability to support nuclear power plant operations.
For purposes of the license renewal rule, the staff has determined that the plant system portion of the offsite power system that is used to connect the plant to the offsite power source should be included within the scope of the rule. This path typically includes the switchyard circuit breakers that connect to the offsite system power transformers (startup transformers), the transformers themselves, the intervening overhead or underground circuits between circuit breaker and transformer and transformer and onsite electrical distribution system, and the associated control circuits and structures. By ensuring that the appropriate offsite power system long-lived passive structures and components that are part of this circuit path are subject to an aging management review, we will ensure that the bases underlying the SBO requirements are maintained over the period of license renewal. This is consistent with the Commission's expectations in including the SBO regulated event under 10 CFR 54.4(a)(3) of the license renewal rule.Alternate ac power sources were accepted under the SBO rule as an alternate means ofwithstanding an SBO. The definition of an alternate ac power source is contained in 10 CFR 50.2. The definition addresses the capability of these power sources to cope with an SBO but not to recover from an SBO. While a very small number of alternate ac power sources may be very robust, the staff nevertheless finds that they were only reviewed as a means of coping with an SBO for the plant specified coping duration.
NUCLEAR ENERGY INSTITUTE Project No. 690
cc:Mr. Joe BartellU.S. Department of Energy NE-42 Washington, DC 20585Mr. Richard P. Sedano, CommissionerState Liaison Officer Department of Public Service 112 State Street Drawer 20 Montipelier, Vermont 05620-2601Mr. Alan P. NelsonNuclear Energy Institute 1776 I Street, N.W., Suite 400 Washington, DC 20006-3708 APN@NEI.ORGMr. Stephen T. HaleFlorida Power & Light Company 9760 S.W. 344 Street Florida City, Florida 33035Mr. William CorbinVirginia Electric & Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, Virginia 23060Mr. Frederick W. PolaskiManager License Renewal Exelon Corporation 200 Exelon Way Kennett Square, PA 19348Mr. Robert GillDuke Energy Corporation Mail Stop EC-12R P.O. Box 1006 Charlotte, NC 28201-1006Mr. Joseph GasperManager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.
Post Office Box 399 Hwy. 75 - North of Fort Calhoun Fort Calhoun, NE 68023-0399Mr. David LochbaumUnion of Concerned Scientists 1707 H Street, NW Suite 600 Washington, DC 20006-3919Mr. Paul GunterDirector of the Reactor Watchdog Project Nuclear Information & Resource Service
1424 16 th Street, NW, Suite 404Washington, DC 20036Mr. Hugh JacksonPublic Citizen's Critical Mass Energy &
Environment Program 215 Pennsylvania Ave. SE Washington DC 20003Mary OlsonNuclear Information & Resource Service, Southeast Office P.O. Box 7586 Asheville, North Carolina 28802