ML072400092

From kanterella
Revision as of 19:37, 22 October 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Callaway Plant, Unit No. 1 - Issuance of Relief Requests (Rrs) ISI-36, ISI-37, and ISI-38 for Second Year Inservice Inspection (ISI) Interval (TAC No. MD3435)
ML072400092
Person / Time
Site: Callaway Ameren icon.png
Issue date: 09/17/2007
From: Hiltz T G
NRC/NRR/ADRO/DORL/LPLIV
To: Naslund C D
Union Electric Co
Donohew J N, NRR/DLPM,415-1307
References
TAC MD3435
Download: ML072400092 (13)


Text

September 17, 2007Mr. Charles D. NaslundSenior Vice President and Chief Nuclear OfficerUnion Electric CompanyPost Office Box 620Fulton, MO 65251

SUBJECT:

CALLAWAY PLANT, UNIT 1 - ISSUANCE OF RELIEF REQUESTS ISI-36,ISI-37, AND ISI-39 FOR THE SECOND 10-YEAR INSERVICE INSPECTION INTERVAL (TAC NO. MD3435)

Dear Mr. Naslund:

By letter dated October 25, 2006 (ULNRC-05183), Union Electric Company (the licensee)requested relief from certain examination requirements of Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components," of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (i.e., the ASME Code) for the second 10-year inservice inspection (ISI) interval at the Callaway Plant (Callaway). Relief Requests (RRs)ISI-34 through ISI-41 were submitted. This letter addresses RRs ISI-36, ISI-37, and ISI-39.

RRs ISI-35 and ISI-41 were approved in our two letters dated January 18, 2007. The remaining RRs will be addressed in future letters.In the supplemental letter dated June 29, 2007 (ULNRC-05423), the licensee has withdrawnRR ISI-37. Based on the attached safety evaluation, the Nuclear Regulatory Commission (NRC) staff has determined that the ASME Code examination coverage requirements are (1) met for the subject weld listed in RR ISI-36 and no relief from the ASME Code requirements is required, and (2) impractical for the subject welds listed in RR ISI-39. Based on this, for RR ISI-39, granting relief, pursuant to Paragraph 50.55a(g)(6)(i) of Title 10 of the Code ofFederal Regulations, is authorized by law and will not endanger life or property or the commondefense and security, and is otherwise in the public interest giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility.

Therefore, the NRC staff grants the relief in RR ISI-39 for the second 10-year ISI interval at Callaway. All other ASME Code,Section XI, requirements for which relief was not specifically requested and approved in this relief request remain applicable, including third-party review by the Authorized Nuclear Inservice Inspector.Sincerely,/RA/Thomas G. Hiltz, ChiefPlant Licensing Branch IVDivision of Operating Reactor LicensingOffice of Nuclear Reactor RegulationDocket No. 50-483

Enclosure:

Safety Evaluation cc w/encl: See next page

ML072400092*previously concurredOFFICENRR/LPL4/PMNRR/LPL4/LANRR/CVIB/BCOGC - NLO w/commentsNRR/LPL4/BCNAMEJDonohew*JBurkhardtMMitchell*JRund*THiltz DATE9/5/079/14/078/24/079/12/079/17/07 June 2007Callaway Plant, Unit 1 cc:John O'Neill, Esq.

Pillsbury Winthrop Shaw Pittman LLP 2300 N. Street, N.W.

Washington, D.C. 20037Mr. Keith A. Mills, Supervising EngineerRegional Regulatory Affairs/Safety Analysis AmerenUE P.O. Box 620 Fulton, MO 65251U.S. Nuclear Regulatory CommissionResident Inspector Office

8201 NRC Road Steedman, MO 65077-1302Mr. Les H. KanuckelManager, Quality Assurance AmerenUE P.O. Box 620 Fulton, MO 65251Missouri Public Service CommissionGovernor Office Building 200 Madison Street P.O. Box 360 Jefferson City, MO 65102-0360Regional Administrator, Region IVU.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005Mr. H. Floyd GilzowDeputy Director for Policy Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102-0176Mr. Rick A. MuenchPresident and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KA 66839Certrec Corporation4200 South Hulen, Suite 422 Fort Worth, TX 76109Technical Services Branch ChiefFEMA Region VII 2323 Grand Boulevard, Suite 900 Kansas City, MO 64108-2670Mr. Dan I. Bolef, PresidentKay Drey, Representative Board of Directors Coalition for the Environment 6267 Delmar Boulevard University City, MO 63130Mr. Lee Fritz, Presiding CommissionerCallaway County Courthouse 10 East Fifth Street Fulton, MO 65251Mr. David E. Shafer Superintendent, Licensing Regulatory Affairs AmerenUE P.O. Box 620 Fulton, MO 65251Manager, Regulatory AffairsAmerenUE P.O. Box 620 Fulton, MO 65251Mr. Keith G. Henke, PlannerDivision of Community and Public Health Office of Emergency Coordination 930 Wildwood P.O. Box 570 Jefferson City, MO 65102Director, Missouri State Emergency Management Agency P.O. Box 116 Jefferson City, MO 65102-0116Mr. Scott Clardy, DirectorSection for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATIONRELATED TO RELIEF REQUESTS ISI-36, ISI-37, AND ISI-39FOR SECOND 10-YEAR INSERVICE INSPECTION INTERVALUNION ELECTRIC COMPANYCALLAWAY PLANT, UNIT 1DOCKET NO. 50-48

31.0INTRODUCTION

By application dated October 25, 2006 (Agencywide Documents Access and ManagementSystem (ADAMS) Accession No. ML063050203), Union Electric Company (the licensee) requested relief from certain examination requirements of Section XI, "Rules for Inservice Inspection [ISI] of Nuclear Power Plant Components," of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (i.e., the ASME Code) for the second 10-year inspection interval at the Callaway Plant (Callaway). Relief Requests (RRs) ISI-34 through ISI-41 were submitted in the application; however, this safety evaluation (SE) only addresses RRs ISI-36, ISI-37, and ISI-39.The Nuclear Regulatory Commission (NRC) staff has reviewed and evaluated the informationprovided by the licensee in its letter dated October 25, 2006, which proposed ISI program plan RRs ISI-36, ISI-37, and ISI-39 for the second 10-year inspection interval at Callaway. The licensee provided additional information on RR ISI-37 in its letter dated June 29, 2007 (ADAMS Accession No. ML072390353).In its letter dated June 29, 2007, the licensee withdrew RR ISI-37. Therefore, RRs ISI-36 andISI-39 are evaluated below in this SE; however, RR ISI-37 is not evaluated because it has been withdrawn.2.0REGULATORY REQUIREMENTSThe ISI of the ASME Code for Class 1, 2, and 3 components is performed in accordance withSection XI of the ASME Code and applicable addenda as required by Paragraph 50.55a(g) in Title 10 of the Code of Federal Regulations (i.e., 10 CFR 50.55a(g)). Pursuant to 10 CFR50.55a(g)(6)(i), the NRC may grant such relief and impose alternative requirements as it determines is authorized by law and will not endanger life or property or the common defense and security and is otherwise in the public interest giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility. Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (includingsupports) shall meet the requirements, except the design and access provisions and the preservice examination requirements, set forth in the ASME Code,Section XI, to the extent practical within the limitations of design, geometry, and materials of construction of the components. The regulations require that ISI of components and system pressure tests conducted during the first 10-year interval and subsequent intervals comply with the requirements in the latest edition and addenda of Section XI of the ASME Code incorporated by reference in 10 CFR 50.55a(b) 12 months prior to the start of the 120-month interval, subject to the limitations and modifications listed therein.The licensee stated that the ASME Code of record for the Callaway Plant second 10-yearinterval ISI program, is the 1989 Edition with no Addenda of Section XI of the ASME Code.The table listing the two RRs that are addressed in this SE is given below with the ASME Codecomponent, the applicable weld numbers, and the applicable ASME Code requirements:Table - RRs ISI-36 and ISI-39Request for ReliefNumberASME CodeComponent (Area or Weld to be Examined)Weld ID No.Applicable ASMECode Requirement (100% Weld Coverage)ISI-36Reactor PressureVessel (RPV) Lower Torus to Dollar Plate Weld2-RV-102-151ASME Code,Exam Category B-A, Item No. B1.21, Figure IWB-2500-3, 74.2% Volume CoverageISI-39RPV A, B, C, and DOutlet Nozzle to Shell Welds2-RV-107-121-A,2-RV-107-121-B, 2-RV-107-121-C, and 2-RV-107-121-DASME Code,Exam Category B-D, Item No. B3.90, Figure IWB-2500-7(a) 79.3% Volume Coverage3.0NRC STAFF EVALUATION OF RRs NOS. ISI-36 AND ISI-39 3.1RR No. ISI-36Applicable ASME Code ComponentsThe ASME Code component is the RPV Lower Torus to Dollar Plate Weld numbered2-RV-102-151. Applicable ASME Code RequirementsThe applicable ASME Code requirements are the following:1.ASME Code,Section XI, IWC-2500-1, Category B-A, Item B1.21, which requiresvolumetric examination of essentially 100 percent of the accessible weld length of the RPV Lower Torus to Dollar Plate Weld numbered 2-RV-102-151.2.ASME Code Case N-460, "Alternative Examination Coverage for Class 1 and Class 2Welds," as an alternative approved for use by the NRC in Regulatory Guide 1.147, Revision 14, "Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1," states that a reduction in examination coverage due to part geometry or interference for any ASME Code Class 1 or 2 weld is acceptable provided that the reduction is less than 10 percent, (i.e., greater than 90 percent examination coverage is obtained).Licensee's Basis for Relief Request (As stated in the licensee's application in the attachmentfor 10 CFR 50.55a Request Numbers ISI-36 (A.) through ISI-39 (D.))A.The [RPV] Lower Torus to Dollar Plate weld is positioned at about the sameelevation as the peripheral bottom-mounted instrumentation (BMI) tubes. Scanning was conducted between obstructing penetrations with the scan boundaries maximized by visually assisted position[ing] of the exam head so that scan starts and stops were as close to the tubes as tool configuration allowed.

Final examination coverage was estimated at 74.2%.B.[Not for RR ISI-36]C.[Not for RR ISI-36]

D.[Not for RR ISI-36]The design configuration/restriction makes the [ASME] Code-required examinationcoverage requirements impractical. Plant modifications or the replacement of components designed to allow for complete coverage would be needed to meet the ASME Code requirements. This would impose a considerable burden to [the licensee of the] Callaway Plant.Licensee's Proposed Alternative Examination (As stated in the licensee's application)[The licensee for] Callaway proposes to accept the percent coverage obtained on thesubject examinations. The best-effort examination approach, in addition to the other considerations or actions described below, provides reasonable assurance of safety and/or structural integrity.

![Does not apply to RR ISI-36.]

!The reactor vessel shell welds are constructed of low alloy steel ... Thesematerials have been shown to be resistant to stress corrosion cracking in pressurized water environments. There is no [potential] degradation mechanism,other than fatigue, active in the subject welds that would cause weld failure.

!VT-2 examinations performed in conjunction with system pressure testing eachrefueling, along with reactor coolant system leak rate limitations imposed by the plant's Technical Specifications, as well as containment atmospheric particulateradioactivity monitoring, provide additional assurance that a leak would be detected prior to any gross failure occurring.NRC Staff's EvaluationWhen writing the inspection requirements for welds on the bottom of the RPV, the ASME CodeCommittees considered the difficulty in examining these welds because of the various components under the RPV (i.e., reactor supports, control rod drives, and instrumentation tube penetrations). The ASME Code,Section XI, Category B-A, Item B1.21 specifically states that it requires a volumetric examination of essentially 100 percent of the accessible weld length of the RPV Lower Torus to Dollar Plate Weld 2-RV-102-151. Because of the following:1.the licensee's statement in its basis for RR ISI-36 that the scanning of the weld wasconducted between obstructing penetrations with the scan boundaries maximized by visually assisted positioning of the exam head so that scan starts and stops were as close to the tubes as the tool configuration allowed, and 2.the figure of the bottom-head dollar BMI tube scans that supports the above licensee'sstatement on the scanning of the weld (the figure is sheet 20 of 21 in the Westdyne Reactor Vessel Weld Results Summary Report for the lower torus to dollar plate weld, weld No. 2-RV-102-151 (the subject weld of RR ISI-36) in the attachment to the licensee's application for RRs ISI-36 through ISI-39),the NRC staff concludes that the licensee did meet the ASME Code requirement to examineessentially 100 percent of the accessible weld length for weld 2-RV-102-151 (i.e., 100 percent of the accessible weld length). Based on this conclusion, the NRC staff further concludes thatrelief is not required for the subject weld because the licensee has met the ASME Code requirement.3.2RR No. ISI-39Applicable ASME Code ComponentsThe applicable ASME Code components are the RPV A, B, C, and D Outlet Nozzle-to-Shellweld numbers 2-RV-107-121-A, 2-RV-107-121-B, 2-RV-107-121-C, and 2-RV-107-121-D.Applicable ASME Code RequirementsThe applicable ASME Code requirement is the ASME Code,Section XI, IWB-2500-1,Category B-D, Item B3.90, which requires volumetric examination of 100 percent of the weld inspection volume as required in Figure IWB-2500-7(a). Licensee's Basis for Relief Request (As stated in the licensee's application in the attachmentfor 10 CFR 50.55a Request Numbers ISI-36 (A.) through ISI-39 (D.))A.[Not for RR ISI-39]B.[Not for RR ISI-39]

C.[Not for RR ISI-39]D.[The licensee for the] Callaway Plant obtained 100% coverage for reflectorsparallel to the weld seam by a combination of radial scan paths (Star scans) and scans from within the nozzle bore (Bore scans). However, the proximity of the nozzle protrusion or boss to the [RPV] Outlet Nozzle-to-Shell welds limits the parallel scans from the vessel ID [inside diameter] (Tangential scans). Because of this, limited coverage of 58.6% was achieved [when] examining for transverse reflectors. Combined final ultrasonic examination coverage was estimated at 79.3%.The design configuration/restriction makes the [ASME] Code-required examinationcoverage requirements impractical. Plant modifications or the replacement of components designed to allow for complete coverage would be needed to meet the ASME Code requirements. This would impose a considerable burden to [the licensee of the] Callaway Plant.Licensee's Proposed Alternative Examination (As stated in the licensee's application)[The licensee for] Callaway proposes to accept the percent coverage obtained on thesubject examinations. The best-effort examination approach, in addition to the other considerations or actions described below, provides reasonable assurance of safety and/or structural integrity.

!For the Inlet Nozzle Safe-end to Elbow welds, [the licensee for] Callawayperformed supplemental eddy current and enhanced visual examinations.

!The reactor vessel shell welds are constructed of low alloy steel, and the InletNozzle Safe-end to Elbow welds are constructed of stainless steel materials.

These materials have been shown to be resistant to stress corrosion cracking in pressurized water environments. There is no [potential] degradation mechanism, other than fatigue, active in the subject welds that would cause weld failure.

!VT-2 examinations performed in conjunction with system pressure testing eachrefueling, along with reactor coolant system leak rate limitations imposed by the plant's Technical Specifications, as well as containment atmospheric particulateradioactivity monitoring, provide additional assurance that a leak would be detected prior to any gross failure occurring.NRC Staff's EvaluationASME Code,Section XI requires volumetric examination of 100 percent as required inFigure IWB-2500-7(a) for the RPV Outlet Nozzle-to-Shell Welds numbered 2-RV-107-A, 2-RV-107-B, 2-RV-107-C, and 2-RV-107-D. The licensee was unable to meet the ASME Coderequirements due to the proximity of the nozzle protrusion or boss that limits the parallel scans from the RPV ID for tangential scans. For the licensee to meet the ASME Code requirements, modifications to, or the replacement of, the subject components would be required and would be major changes to the plant, which would place a burden on the licensee. Based on this, the NRC staff concludes that the ASME Code requirements are impractical.

The licensee obtained 100 percent coverage for reflectors parallel to the weld seam by a combination of radial scan paths and scans from within the nozzle bore. Because of the configuration of the subject nozzles, the coverage was limited to 58.6 percent in examining for transverse reflectors. The licensee obtained an aggregate examination coverage of 79.3 percent for each of the subject nozzles. The licensee also performed supplemental eddy current and enhanced visual examinations. Therefore, the NRC staff determined that the examinations performed would have detected any significant patterns of degradation, if any had occurred. The NRC staff also determined that the volumetric and ASME Code VT-2 visual examinations during system walkdowns performed provided reasonable assurance of the structural integrity of RPV outlet nozzle-to-shell welds numbered 2-RV-107-A, 2-RV-107-B, 2-RV-107-C, and 2-RV-107-D.

4.0CONCLUSION

The NRC staff has reviewed the licensee's application dated October 25, 2006, which submittedthe licensee's RRs ISI-36, ISI-37, and ISI-39. RR ISI-37 was withdrawn in the licensee's letter dated June 26, 2007.Based on its evaluation in Section 3.1 of this SE, the NRC staff concludes for RR ISI-36 thatrelief is not required for Callaway because the licensee has met the ASME Code volumetric examination requirements for the RPV Lower Torus to Dollar Plate Weld 2-RV-102-151. Furthermore, based on its evaluation in Section 3.2 of this SE, the NRC staff concludes that theASME Code examination coverage requirements are impractical for the subject welds listed in RR ISI-39. Based on the coverages obtained, if significant service-induced degradation were occurring, there is reasonable assurance that evidence of it would be detected by the volumetric examinations that were performed. The volumetric examinations, supplemental eddy current and enhanced visual examinations, and VT-2 visual examinations during plant walkdowns performed provide reasonable assurance of structural integrity of the RPV Outlet Nozzle-to-Shell Welds numbered 2-RV-107-A, 2-RV-107-B, 2-RV-107-C, and 2-RV-107-D. The NRC staff has determined that granting relief pursuant to 10 CFR 50.55a(g)(6)(i) for RR ISI-39 is authorized by law and will not endanger life or property, or the common defense and security, and is otherwise in the public interest giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility. Therefore, pursuant to 10 CFR 50.55a(g)(6)(i), the NRC staff concludes that RR ISI-39 is granted for Callaway for the second 10-year ISI interval. All other ASME Code,Section XI requirements for which relief was not specifically requestedand approved in the subject requests for relief remain applicable, including third-party review by the authorized Nuclear Inservice Inspector.Principal Contributor: Thomas K. McLellan Date: September 17, 2007