ML12283A246 | 28 September 2012 | Part 21 - Fairbanks Morse Opposed Piston EDG Oil Pump Leak | Hydrostatic |
ML12319A012 | 27 September 2012 | Error in Main Steam Line High Flow Calculational Methodology | |
ML12347A308 | 12 December 2012 | Part 21 60-Day Interim Report Notification: Error in Main Steam Line High Flow Calculational Methodology | |
ML12348A136 | 13 December 2012 | Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers | |
ML12352A123 | 13 December 2012 | 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers | |
ML13002A030 | 21 December 2012 | Part 21 Notification - Defect Discoveredd in COM-5 and SSC-T Protective Relays Distributed by Abb, Inc | |
ML13002A470 | 28 December 2012 | 10 C.F.R. Part 21 Notification to Customers - COM-5 and SSC-T Protective Relays - Telephone Relay Armature Pivot Pin, Resubmitted to Include Attachment 1, Which Was Inadvertently Omitted in the Original Fax | |
ML13042A096 | 8 February 2013 | Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Error in Main Steam Line High Flow Calculational Methodology | |
ML13044A075 | 8 February 2013 | Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology | |
ML13064A012 | 25 February 2013 | Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve | Anchor Darling |
ML13073A107 | 12 March 2013 | Notification of Potential Part 21 Report - Defective Raw Material Used to Manufacture Valve Stems | |
ML13079A320 | 18 March 2013 | Notification of Potential Part 21 Interim Report Re Possible Deviation or Defect in Nuclear Qualified High Efficiency Particulate Air Filters | |
ML13093A153 | 2 April 2013 | Part 21 Report - Foxboro Power Supply Potential Failures Due to Defective Tie Wraps and Holders | |
ML13127A014 | 3 May 2013 | Part 21 Report - Fuel Injectors Failed Pressure Test | |
ML13142A329 | 6 May 2013 | Notification of Potential Part 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0109, Rev. 0 | |
ML13165A342 | 12 June 2013 | 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers | |
ML13238A253 | 21 August 2013 | Notification of Potential Part 21 Report - Foxboro Power Supply Potential Failures Due to Defective the Wraps and Holders | |
ML13246A084 | 23 August 2013 | Notification of Potential Defect & Interim Report Regarding a Potential Defect of Materials Supplied to Operating Us Nuclear Power Plants by Mirion Technologies (Conax Nuclear) Inc. (Mtcn) with Containment Electric Penetration Assemblies | |
ML13277A010 | 23 September 2013 | Interim Report Update for Component ASME Material Supplied by Mirion Technologies (Conax Nuclear), Inc. (Mtcn), as Part of Containment Electric Penetration Assemblies (EPA) | |
ML14042A202 | 5 February 2014 | Part 21 Report Regarding Unqualified Material Used in Electrical Penetration Assemblies | |
ML14069A468 | 2 March 2014 | Part 21 Report - Defective Raw Material Used to Manufacture Valve Stems | |
ML14094A445 | 1 April 2014 | Notification of Part 21 Report on Defective Raw Material Used to Manufacture Valve Stems | |
ML14105A018 | 11 April 2014 | Part 21 - Model 1154HP Transmitters with Integral 1159 Remote Diaphragm Seals May Exhibit Degraded Functional Reliability | |
ML14204A707 | 23 July 2014 | Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV | |
ML14204A708 | 23 July 2014 | Enclosure 2, Description of Closure Evaluation, Non-Proprietary Information - Class I (Public) | Safe Shutdown Shutdown Margin Scram Discharge Volume |
ML14210A010 | 23 July 2014 | Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve | Safe Shutdown Shutdown Margin Scram Discharge Volume |
ML14274A052 | 22 September 2014 | Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities | |
ML15022A650 | 20 January 2015 | Letter from Steven R. Eisenberg USNRC 10CFR Part 21 Notification | |
ML15103A244 | 6 April 2015 | Part 21 Report - Deviation of Hk Circuit Breaker Close Latch Spring | Commercial Grade Dedication |
ML16039A269 | 3 February 2016 | Nutherm International, Inc. - Potential Issue Regarding Incorrect Industrial Irradiation Dose, Per Cooper, Oconee, Fitzpatrick, Point Beach, Brunswick, and Susquehanna | |
ML16139A834 | 10 May 2016 | Electroswitch - Transmittal of 10CFR Part 21 Reporting of Defects and Noncompliance Regarding Vendor Inspection of Electroswitch Corporation Docket No. 99900833 | |
ML16243A472 | 25 August 2016 | Part 21 Reporting of Defects and Noncompliance | |
ML16251A098 | 2 September 2016 | Part 21 - Potential Failure of Battery System Connections | |
ML16321A451 | 21 October 2016 | Part 21 Reporting of Defects and Noncompliance | |
ML17026A414 | 20 January 2017 | C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling | |
ML17081A453 | 20 March 2017 | Part 21 - Plastic Jar Dedication Sampling | |
ML17104A288 | 13 April 2017 | Emerson Process Management, LLC - Fisher Information Notice, (FIN) 2017-02 | |
ML17114A070 | 13 April 2017 | Part 21 Notification - Identified Fisher 546S Electro-Pneumatic Transducers Standard Mounting Brackets Failed Seismic Testing Standards | |
ML17114A071 | 13 April 2017 | 10 CFR Part 21 Notification of Deviation - Gkt Relay | |
ML17179A378 | 7 June 2017 | TE Connectivity - Part 21 Transfer of Information TE-023 | |
ML17194A825 | 11 July 2017 | Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections | Anchor Darling |
ML17212A628 | 24 July 2017 | Lake Engineering Co. - Potentially Degraded Snubber SF1154 Hydraulic Fluid Second - Interim Notification Per 10 CFR Part 21 | |
ML17223A200 | 9 August 2017 | 10 CFR Written Notification for Hex Head Cap Screws Nova Machine Products Part Numbers: BPRT.008227.30, BPRT.008468.30, and BPRT.008342.30 | Non-Destructive Examination |
ML17243A136 | 28 August 2017 | Fisher Information Notice, (FIN) 2017-04 - Erroneous Rotary Seating Torque Calculation in Flowscanner Software | |
ML18211A302 | 25 July 2018 | Interim Notification Per 10 CFR Part 21, Degraded Snubber SF1154 Hydraulic Fluid Batch No. 11 KLVS146 | |
ML18295A199 | 24 September 2018 | Lake Engineering - Second Interim Notification Per 10 CFR Part 21: Degraded Snubber SF1154 Hydraulic Fluid Batch No. 11KLVS146 | |
ML19071A112 | 1 March 2019 | Lake Engineering Co., Corrected Potentially Degraded Snubber SF1154 Hydraulic Fluid Batch 11KLVS146 Final Report, Per 10 CFR Part 21 | |
ML19077A096 | 5 March 2019 | Interim Notification Per 10 CFR Part 21, Degraded Snubber SF1154 Hydraulic Fluid Batch No. ZJS1518 | |
ML19168A010 | 31 May 2019 | Curtis-Wright Nuclear Division- Notification Report for Potential Part 21 Update | |
ML19168A012 | 31 May 2019 | Paragon Energy Solution LLC-10 CFR Part 21 Report of Defect GS2 Terry Turbine Introl Positioners |