MONTHYEARCNL-19-061, Seismic Probabilistic Risk Assessment for Sequoyah Nuclear Plant, Units 1 and 2 - Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task2019-10-18018 October 2019
[Table View]Seismic Probabilistic Risk Assessment for Sequoyah Nuclear Plant, Units 1 and 2 - Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Fo Project stage: Response to RAI ML19296B7862019-10-31031 October 2019 NUREG/CR-7245 State-of-the-Art Reactor Consequence Analyses (Soarca) Project Sequoyah Integrated Deterministic and Uncertainty Analyses Project stage: Request ML20161A3902020-04-0909 April 2020 Request for Supporting Information for the Sequoyah SPRA Audit Review - Follow-up to Plant Response Question 5 Project stage: Other ML20143A1752020-07-17017 July 2020 Staff Review of Seismic Probabilistic Risk Assessment Associated with Reevaluated Seismic Hazard Implementation of the Near-Term Task Force Recommendation 2.1: Seismic Project stage: Approval 2019-10-31 |
ML20161A390 | |
Person / Time | |
---|---|
Site: | Sequoyah |
Issue date: | 04/09/2020 |
From: | Stephen Philpott NRC/NRR/DORL/LPMB |
To: | Thompson R Tennessee Valley Authority |
Philpott S | |
References | |
EPID L-2019-JLD-0013 | |
Download: ML20161A390 (2) | |
Similar Documents at Sequoyah | |
---|---|
Category:E-Mail
MONTHYEARML24309A0552024-11-0101 November 2024
[Table view]NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24281A0072024-10-0202 October 2024 NRR E-mail Capture - Acceptance Review Results for the Sequoyah License Amendment Request to Modify the FHA Analysis, Tech Spec TS 3.9.4 and Tech Spec 3.3.6 (L-2024-LLA-0117) ML24177A1412024-06-11011 June 2024 NRR E-mail Capture - Audit Plan Related to Review of the Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, LAR to Revise Technical Specification Table 3.3.2-1 Function 5 ML24152A1542024-05-31031 May 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-03 ML24128A1802024-05-0707 May 2024 NRR E-mail Capture - Acceptance Review for Sequoyah License Amendment Request to Modify TS 3.8.1 and TS 3.8.2 (L-2024-LLA-0047) ML24123A0882024-05-0202 May 2024 NRR E-mail Capture - Correction Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24122B4872024-04-30030 April 2024 NRR E-mail Capture - Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24144A2322024-04-20020 April 2024 Tennessee Multi-Sector Permit (Tmsp), 2024 Annual Discharge Monitoring Report for Outfalls SW-3, SW-3, and SW-9 ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24074A4252024-03-14014 March 2024 NRR E-mail Capture - Sequoyah Hydrologic Analysis License Amendment Request - Notification of Change to Estimated Completion and Hours ML24059A4052024-02-28028 February 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-02 ML24053A0302024-02-21021 February 2024 NRR E-mail Capture - Request for Steam Generator (SG) Tube Inspection Call for Sequoyah, Unit 1 ML24047A2792024-02-15015 February 2024 RAI Related to the Exemption Request for 10 CFR 37.11 ML24045A1002024-02-13013 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Sequoyah Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML24036A0132024-01-23023 January 2024 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar Nuclear Plants, License Amendment Request to Revise TS Table 3.3.2-1, Function 5, Turbine Trip and Feedwater Isolation ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23165A2862023-06-14014 June 2023 Tennessee Multi-Sector Permit (Tmsp), 2023 Annual Discharge Monitoring Report for Outfalls SW-1, SW-16, SW-17, SW-18, SW-19, and SW-21 ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23062A5952023-02-27027 February 2023 Staff follow-up Questions to TVAs 12/19/2022 Response of the Staffs Rsi Regarding 08/04/2022 SQN Exemption Request ML23058A1312023-02-27027 February 2023 FW: TVA Intentions on EA-22-129 ML23052A0792023-02-21021 February 2023 NRR E-mail Capture - Acceptance Review for Browns Ferry and Sequoyah License Amendment Request to Adopt TSTF-541 ML23046A3552023-02-15015 February 2023 Annual Water Withdrawal Report 2022 ML23019A3442023-01-19019 January 2023 Tennessee Multi-Sector Permit (Tmsp), 2022 Annual Discharge Monitoring Report for Outfalls SW-1, SW-16, and SW-19 ML23013A0362023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML23013A0382023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML23026A0282023-01-12012 January 2023 001 Radiation Safety Baseline Inspection Information Request ML22348A0972022-12-14014 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22348A0442022-12-13013 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22348A0432022-11-28028 November 2022 NRR E-mail Capture - State Consultation - Sequoyah Nuclear Plant, Units 1 and 2, License Amendment Request to Modify the Approved 10 CFR 50.69 Categorization Process (L-2022-LLA-0033) ML22227A0712022-08-15015 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 (EPID L-2022-LLA-0103) - Corrected ML22227A0262022-08-12012 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22215A2752022-08-0303 August 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-554 ML22214A1582022-08-0202 August 2022 NRR E-mail Capture - Request for Additional Information for Sequoyah Units 1 and 2 License Amendment Request for Fire and Seismic PRA Modification to 10 CFR 50.69 (L-2022-LLA-0033) ML22196A0732022-07-15015 July 2022 NRR E-mail Capture - (External_Sender) State Notification for Sequoyah Units 1 and 2 Amendment Issuance - TSTF-505 RICT (L-2021-LLA-0145) ML22194A8762022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-529 ML22173A0332022-06-17017 June 2022 NRR E-mail Capture - (External_Sender) State Notification for Sequoyah Units 1 and 2 Amendment Issuance - Reactor Trip System Instrumentation (L-2021-LLA-0200) ML22166A4292022-06-0606 June 2022 NRR E-mail Capture - LAR to Adopt TSTF-577 ML22151A0102022-05-27027 May 2022 NRR E-mail Capture - Revised Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22146A3322022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Related to Sequoyah Nuclear Plants LAR to Adopt TSTF-505 ML22151A0092022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22146A3342022-05-25025 May 2022 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Relief Requests (EPID L-2022-LLR-0045 - 0047) ML22137A2692022-05-17017 May 2022 Notice of Termination, TNR192066, Gravel Lot Restoration Project ML22136A0182022-05-16016 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, Alternative Request RP-11 and Watts Bar Nuclear Plant, Units 1 and 2, Alternative Request IST-RR-9 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to TVAs Request to Revised the TVA Plants Radiological Emergency Plans ML22132A1762022-05-12012 May 2022 Tennessee Multi-Sector Permit (Tmsp), 2021 Annual Discharge Monitoring Report for Outfalls SW-2, SW-3, SW-4, SW-6, SW-8, SW-9, and SW-13 2024-06-11 Category:Request for Additional Information (RAI) MONTHYEARML24309A0552024-11-0101 November 2024
[Table view]NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24152A1542024-05-31031 May 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-03 ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A1002024-02-13013 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Sequoyah Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23307A0832023-11-0808 November 2023 Enclosure - Request for Additional Information HDI-Sequoyah NDE Exemption Request 10-30-2023 ML23307A0822023-11-0808 November 2023 Request for Additional Information – August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation ML23062A5942023-02-27027 February 2023 Enclosure - NRC SQN Exemption Rsi Response Staff Follow Up Questions ML23062A5952023-02-27027 February 2023 Staff follow-up Questions to TVAs 12/19/2022 Response of the Staffs Rsi Regarding 08/04/2022 SQN Exemption Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22257A0622022-09-14014 September 2022 Requalification Program Inspection - Sequoyah Nuclear Plant ML22255A0842022-09-0909 September 2022 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-04 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22214A1582022-08-0202 August 2022 NRR E-mail Capture - Request for Additional Information for Sequoyah Units 1 and 2 License Amendment Request for Fire and Seismic PRA Modification to 10 CFR 50.69 (L-2022-LLA-0033) ML22151A0102022-05-27027 May 2022 NRR E-mail Capture - Revised Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22151A0092022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22146A3322022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Related to Sequoyah Nuclear Plants LAR to Adopt TSTF-505 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to TVAs Request to Revised the TVA Plants Radiological Emergency Plans ML21237A4952021-08-25025 August 2021 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-04 ML21160A0352021-06-0303 June 2021 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021-03 ML21095A0482021-04-0505 April 2021 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Transition to Westinghouse Fuel ML21092A0972021-04-0202 April 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML20259A4782020-09-15015 September 2020 Emergency Preparedness Program Inspection Request for Information ML20261H4172020-09-14014 September 2020 NRR E-mail Capture - Sequoyah Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Hydrologic UFSAR Update ML20261H4162020-09-0202 September 2020 NRR E-mail Capture - Draft Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, Request to Revise UFSAR Hydrologic Analysis ML20189A2112020-07-0101 July 2020 Request for Additional Information Regarding Hydrologic UFSAR Update ML20106F1042020-04-14014 April 2020 Request for Additional Information Regarding the Hydrologic Analysis LAR ML20161A3902020-04-0909 April 2020 Request for Supporting Information for the Sequoyah SPRA Audit Review - Follow-up to Plant Response Question 5 ML20098D8612020-04-0707 April 2020 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000327/2020012 and 05000328/2020012) and Request for Information) ML20036E2842020-02-0505 February 2020 20200123 - Sequoyah Radiation Safety Inspection Document Request Letter ML19323D7562019-11-18018 November 2019 Nrc'S Request for Additional Information - Exigent Amendment ML19235A0992019-08-22022 August 2019 Emergency Preparedness Program Inspection Request for Information ML19162A2462019-06-11011 June 2019 RP Inspection Document Request 2019-03 ML19149A6222019-05-29029 May 2019 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, Request for Alternative to 18-ISI-1 EPID: L-2019-LLR-0006 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19015A4192019-01-15015 January 2019 NRR E-mail Capture - RAI - Sequoyah Nuclear Plant, Units 1 and 2, LAR to Adopt 10 CFR50.69 Risk-informed SSC ML18344A0752018-12-10010 December 2018 NRR E-mail Capture - Request for Additional Information - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers and to Revise Updated Final Analysis Report (SQN-TS-17-04) ML18296A0022018-10-22022 October 2018 NRR E-mail Capture - Additional Information Needs - Sequoyah Units 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers Revise Updated Final Analysis Report (SQN-TS-17-04) ML18283B0592018-10-10010 October 2018 NRR E-mail Capture - Additional Information Needs Identified During Audit - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers Revise Updated Final Analysis Report (SQN-TS-17-04) ML18283A6232018-09-25025 September 2018 04 RP Inspection Document Request ML18233A1942018-08-21021 August 2018 NRR E-mail Capture - Additional Information Needs Identified - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers and to Revise Updated Final Analysis Report (SQN-TS-17-04) ML18138A1102018-05-17017 May 2018 Enclosurequest for Additional Information (Letter to E. D. Schrull Request for Additional Information Regarding Tennessee Valley Authority'S Decommissioning Funding Plan Update for Browns Ferry and Sequoyah Isfsis) ML18057A6372018-02-23023 February 2018 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet Topical Report TVA-NPG-AWA16 - EPIC: L-2016-TOP-0011) ML17191A2062017-07-0606 July 2017 NRR E-mail Capture - Sequoyah Nuclear Station, Unit 1 & 2 - Request for Additional Information Related to LAR for Technical Specification 3.8.1.17 Note Modification (CAC Nos. MF9398 and MF9399) ML17150A0792017-05-23023 May 2017 NRR E-mail Capture - Request for Additional Information Related to TVA Fleet LAR for EAL Change to Adopt NEI-99-01 Rev.6 (CAC Nos. MF9054 - MF9060) ML17112A0402017-04-20020 April 2017 NRR E-mail Capture - Sequoyah Nuclear Station, Unit 1 & 2 - Request for Additional Information Related to LAR for Technical Specification 3.8.1, AC SOURCES-OPERATING ML17004A0612017-01-0404 January 2017 Notification of NRC Triennial Fire Protection Inspection (Team)(Report 05000327/2017007 and 05000328/2017007) ML15194A3882015-07-13013 July 2015 Request for Additional Information Related to LAR to Revise Ice Condenser Ice Mas Tech Spec ML15175A2912015-06-24024 June 2015 E-mail Re. Request for Additional Information RR RP-07 ML15159B1642015-06-22022 June 2015 Requests for Additional Information for the Review of the Sequoyah Nuclear Plant, Units 1 and 2, License Renewal Application-Set 25 (TAC Nos. MF0481 and MF0482) ML15050A0962015-02-19019 February 2015 E-mail Re. Request for Additional Information Related to LAR to Ice Condendser Inc Mass Tech Spec 2024-05-31 |
Text
From: Philpott, Stephen To: Thompson, Russell R Cc: Valentin-Olmeda, Milton
Subject:
Follow-up to Plant Response Question 5 - Sequoyah SPRA Audit Review Date: Thursday, April 09, 2020 12:07:00 PM Good morning Russell, The staff has been reviewing the responses to the audit review questions that you posted in the e-Portal. At this point, I dont think we have any further fragility-related questions. With regard to the response to Question 5 (Plant Response), the reviewers would like to get a little further understanding of a couple points. We would like to set up a follow-up call to discuss the response a bit further. Below is a more detailed description of the points the staff would like to discuss.
Could you please review the discussion points below and let me know when your appropriate staff might be available for a call?
Question 5.1 - Topic #16 - Review of Plant Modifications and Licensee Actions PRA, Accounting for NEI 12-13 (SPID Section 6.7)
Based on the results in the Sequoyah SPRA submittal, it appears that SEIS_-0-30-5, HAMARV, and HACIV may provide non-trivial risk reduction. The response to Question #5 provides information about the licensees rationale for the lack of cost-justified plant improvements that would eliminate or significantly reduce the risk of one or more of the failures resulting in a reduction in seismic LERF of 1E-06 per year for either unit for each of the above-mentioned seismic failures. The staff would like to better understand the response to Question #5 given the potential for risk reduction from the individual seismic failures identified above.
Therefore, the staff would like a discussion to clarify the following topics from the response to Question #5:
- a. The approach used to identify potential plant modifications and any plant modifications that were considered, but not discussed in the response to Question
- 5.
- b. Quantitative results (i.e., change in SCDF, SLERF, and importance measures) for the sensitivity study where the median capacity of the fragility group SEIS_0-30-5 (Relay Chatter - 480V/6.9V SD BD GE HEA Breakers) was increased to 1.65g.