2013 Perry Nuclear Power Plant Initial License Examination Outline RO and SRO ES-301-2
ML13178A373
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 02/25/2013
From:
NRC/RGN-III
To:
FirstEnergy Nuclear Operating Co
Shared Package
ML11354A273 List:
References
Download: ML13178A373 (3)


Text

ES-301, Rev. 9 Control Room/In

-Plant Systems Outline Form ES-301-2 FENOC Facsimile Rev 0 Facility: Perry Date of Examination:

Feb. 20 13 Examination Level:

RO Operating Test Number:

01 Control Room Systems

@ (8 for RO); (7 for SRO

-I); (2 or 3 for SRO

-U, including 1 ESF)

System / JPM Title Type Code*

Safety Function a. OT-3701-C11_513 Withdraw Control Rods D , S, A , L 1 b. OT-3701-E51_006 Lineup RCIC to control RPV level per EOP

-SPI 6.6 N, S , L 2 c. OT-3701-B21_009 Open MSIV's N, S 3 d. OT-3701-E12_506 Re-establish Shutdown Cooling D , S, A , L 4 e. OT-3701-R43_501 Shutdown Div 2 Diesel Generator D, S, A 6 f. OT-3701-D17_001 Startup DW Airborne. Rad Monitor N, C 7 g. OT-3701-P41_001 Shift Service Water Pumps (normal)

N, S 8 h. OT-3701-M25_50 1 Shift CR Ventilation to ER N, S, A, EN 9 In-Plant Systems

@ (3 for RO); (3 for SRO

-I); (3 or 2 for SRO

-U) i. OT-3701-P54_502 Emergency run of motor fire pump D, A , E 8 j. OT-3701-T23_004 Containment Closure D, R , E 5 k. OT-3701-R10_303 Shed non-essential Divisional bus loads D , E 6 @ All RO and SRO

-I control room (and in

-plant) systems must be different and serve different safety functions; all 5 SRO

-U systems must serve different safety functions; in

-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO

-I / SRO-U (A)lternate path (C)ontrol room (D)irect from bank (E)mergency or abnormal in

-plant (EN)gineered safety feature (L)ow-Power / Shutdown (N)ew or (M)odified from bank including 1(A) (P)revious 2 exams (R)CA (S)imulator 4-6 / 4-6 / 2-3 - - - - - - - - - - - - - - - 9 / 8 / 4 1 / 1 / 1 - / - / 1(control room system) 1 / 1 / 1 2 / 2 / 1 3 / 3 / 2 (randomly selected) 1 / 1 / 1 - - - - - - - - - - - - - - -

ES-301, Rev. 9 Control Room/In

-Plant Systems Outline Form ES-301-2 FENOC Facsimile Rev 0 Facility: Perry Date of Examination:

Feb 2013 Examination Level:

SRO-I Operating Test Number:

01 Control Room Systems

@ (8 for RO); (7 for SRO

-I); (2 or 3 for SRO

-U, including 1 ESF)

System / JPM Title Type Code*

Safety Function a. OT-3701-C11_5 13 Withdraw Control Rods D, S, A, L 1 b. OT-3701-E51_006 Lineup RCIC to control RPV level per EOP

-SPI 6.6 N, S , L 2 c. OT-3701-B21_009 Open MSIV's N, S 3 d. 4 e. OT-3701-R43_501 Shutdown Div 2 Diesel Generator D, S, A 6 f. OT-3701-D17_001 Startup DW Airborne. Rad Monitor N, C 7 g. OT-3701-P41_001 Shift Service Water Pumps (normal)

N, S 8 h. OT-3701-M25_501 Shift CR Ventilation to ER N, S, A, EN 9 In-Plant Systems

@ (3 for RO); (3 for SRO

-I); (3 or 2 for SRO

-U) i. OT-3701-P54_502 Emergency run of motor fire pump D, A, E 8 j. OT-3701-T23_004 Containment Closure D, R, E 5 k. OT-3701-R10_303 Shed non-essential Divisional loads D, E 6 @ All RO and SRO

-I control room (and in

-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in

-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO

-I / SRO-U (A)lternate path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-Power / Shutdown (N)ew or (M)odified from bank including 1(A)

(P)revious 2 exams (R)CA (S)imulator 4-6 / 4-6 / 2-3 - - - - - - - - - - - - - - - 9 / 8 / 4 1 / 1 / 1 - / - / 1(control room system) 1 / 1 / 1 2 / 2 / 1 3 / 3 / 2 (randomly selected) 1 / 1 / 1 - - - - - - - - - - - - - - -

ES-301, Rev. 9 Control Room/In

-Plant Systems Outline Form ES-301-2 FENOC Facsimile Rev 0 Facility: Perry Date of Examination:

Feb 2013 Examination Level:

SRO-U Operating Test Number:

01 Control Room Systems

@ (8 for RO); (7 for SRO

-I); (2 or 3 for SRO

-U, including 1 ESF)

System / JPM Title Type Code*

Safety Function a. OT-3701-C11_5 13 Withdraw Control Rods D, S, A, L 1 b. c. OT-3701-B21_009 Open MSIV's N, S 3 d. e. f. g. h. OT-3701-M25_501 Shift CR Ventilation to ER N, S, A, EN 9 In-Plant Systems

@ (3 for RO); (3 for SRO

-I); (3 or 2 for SRO

-U) i. j. OT-3701-T23_004 Containment Closure D, R, E 5 k. OT-3701-R10_303 Shed non-essential Divisional loads D, E 6 @ All RO and SRO

-I control room (and in

-plant) systems must be different and serve different safety functions; all 5 SRO

-U systems must serve different safety functions; in

-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO

-I / SRO-U (A)lternate path (C)ontrol room (D)irect from bank (E)mergency or abnormal in

-plant (EN)gineered safety feature (L)ow-Power / Shutdown (N)ew or (M)odified from bank including 1(A)

(P)revious 2 exams (R)CA (S)imulator 4-6 / 4-6 / 2-3 - - - - - - - - - - - - - - - 9 / 8 / 4 1 / 1 / 1 - / - / 1(control room system) 1 / 1 / 1 2 / 2 / 1 3 / 3 / 2 (randomly selected) 1 / 1 / 1 - - - - - - - - - - - - - - -