2013 Perry Nuclear Power Plant Initial License Examination Outline RO and SRO ES-301-2
ML13178A373
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 02/25/2013
From:
NRC/RGN-III
To:
FirstEnergy Nuclear Operating Co
Shared Package
ML11354A273 List:
References
Download: ML13178A373 (3)


Text

ES-301, Rev. 9 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Perry Date of Examination: Feb. 2013 Examination Level: RO Operating Test Number: 01 Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code* Safety Function

a. OT-3701-C11_513 Withdraw Control Rods D, S, A, L 1
b. OT-3701-E51_006 Lineup RCIC to control RPV level per EOP- N, S, L 2 SPI 6.6
c. OT-3701-B21_009 Open MSIVs N, S 3
d. OT-3701-E12_506 Re-establish Shutdown Cooling D, S, A, L 4
e. OT-3701-R43_501 Shutdown Div 2 Diesel Generator D, S, A 6
f. OT-3701-D17_001 Startup DW Airborne. Rad Monitor N, C 7
g. OT-3701-P41_001 Shift Service Water Pumps (normal) N, S 8
h. OT-3701-M25_501 Shift CR Ventilation to ER N, S, A, EN 9 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
i. OT-3701-P54_502 Emergency run of motor fire pump D, A, E 8
j. OT-3701-T23_004 Containment Closure D, R, E 5
k. OT-3701-R10_303 Shed non-essential Divisional bus loads D, E 6

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room ---------------

(D)irect from bank 9 / 8 / 4 (E)mergency or abnormal in-plant 1 / 1 / 1 (EN)gineered safety feature - / - / 1(control room system)

(L)ow-Power / Shutdown 1 / 1 / 1 (N)ew or (M)odified from bank including 1(A) 2 / 2 / 1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)

(R)CA 1 / 1 / 1 (S)imulator ---------------

FENOC Facsimile Rev 0

ES-301, Rev. 9 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Perry Date of Examination: Feb 2013 Examination Level: SRO-I Operating Test Number: 01 Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code* Safety Function

a. OT-3701-C11_513 Withdraw Control Rods D, S, A, L 1
b. OT-3701-E51_006 Lineup RCIC to control RPV level per EOP- N, S, L 2 SPI 6.6
c. OT-3701-B21_009 Open MSIVs N, S 3
d. 4
e. OT-3701-R43_501 Shutdown Div 2 Diesel Generator D, S, A 6
f. OT-3701-D17_001 Startup DW Airborne. Rad Monitor N, C 7
g. OT-3701-P41_001 Shift Service Water Pumps (normal) N, S 8
h. OT-3701-M25_501 Shift CR Ventilation to ER N, S, A, EN 9 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
i. OT-3701-P54_502 Emergency run of motor fire pump D, A, E 8
j. OT-3701-T23_004 Containment Closure D, R, E 5
k. OT-3701-R10_303 Shed non-essential Divisional loads D, E 6

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room ---------------

(D)irect from bank 9 / 8 / 4 (E)mergency or abnormal in-plant 1 / 1 / 1 (EN)gineered safety feature - / - / 1(control room system)

(L)ow-Power / Shutdown 1 / 1 / 1 (N)ew or (M)odified from bank including 1(A) 2 / 2 / 1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)

(R)CA 1 / 1 / 1 (S)imulator FENOC Facsimile Rev 0

ES-301, Rev. 9 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Perry Date of Examination: Feb 2013 Examination Level: SRO-U Operating Test Number: 01 Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code* Safety Function

a. OT-3701-C11_513 Withdraw Control Rods D, S, A, L 1 b.
c. OT-3701-B21_009 Open MSIVs N, S 3 d.

e.

f.

g.

h. OT-3701-M25_501 Shift CR Ventilation to ER N, S, A, EN 9 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U) i.
j. OT-3701-T23_004 Containment Closure D, R, E 5
k. OT-3701-R10_303 Shed non-essential Divisional loads D, E 6

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room ---------------

(D)irect from bank 9 / 8 / 4 (E)mergency or abnormal in-plant 1 / 1 / 1 (EN)gineered safety feature - / - / 1(control room system)

(L)ow-Power / Shutdown 1 / 1 / 1 (N)ew or (M)odified from bank including 1(A) 2 / 2 / 1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)

(R)CA 1 / 1 / 1 (S)imulator FENOC Facsimile Rev 0