MONTHYEARML1124200222011-08-29029 August 2011 Request for License Amendment to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) (License Amendment Request Ldcn 11-0012) Project stage: Request ULNRC-05823, Clarification of Information Contained in Request for License Amendment to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) (LDCN 11-0012)2011-11-0909 November 2011 Clarification of Information Contained in Request for License Amendment to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) (LDCN 11-0012) Project stage: Request ML1132602802011-11-22022 November 2011 Acceptance Review Email, Request for License Amendment to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Acceptance Review ML1132604512011-11-22022 November 2011 Correction Acceptance Review Email, Request for License Amendment to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Acceptance Review ML1201804512012-01-19019 January 2012 Regulatory Audit Plan for License Amendment Request to Implement NFPA 805, Risk-Informed, Performance-Based, Fire Protection Program Pursuant to 10 CFR 50.48(c) Project stage: Other ML1206004022012-02-15015 February 2012 Email, Request for Additional Information, Request to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1206004072012-02-15015 February 2012 Email, Request for Additional Information, Request to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1206001862012-03-0202 March 2012 Request for Additional Information, Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML12108A2402012-04-17017 April 2012 Enclosure 1 to ULNRC-05851, Request for Additional Information (RAI) with Callaway Plant Response Project stage: Request ULNRC-05851, Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 8052012-04-17017 April 2012 Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Response to RAI ML12159A0942012-06-0606 June 2012 Email Request for Additional Information Round 2, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Request ML12159A1032012-06-0606 June 2012 PRA Requests for Additional Information, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML12159A1112012-06-0606 June 2012 Fire Modeling Requests for Additional Information, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1217104322012-06-19019 June 2012 Email, Request for Additional Information Round 3, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1217104442012-06-19019 June 2012 Apla, Request for Additional Information Round 3, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1217104392012-06-19019 June 2012 Afpb, Request for Additional Information Round 3, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ULNRC-05876, Response to Request for Additional Information Re Adoption of National Fire Protection Association Standard NFPA 8052012-07-12012 July 2012 Response to Request for Additional Information Re Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Response to RAI ML12335A2322012-12-11011 December 2012 Request for Additional Information, Round 2, Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML13008A3542013-01-0303 January 2013 Email Request for Additional Information,License Amendment Request to Adopt NFPA 805 Project stage: RAI ML13008A3502013-01-0808 January 2013 Email, Request for Additional Information License Amendment Request to Adopt NFPA 805 Project stage: RAI ML13022A0242013-01-22022 January 2013 Email, Two Revised Requests for Additional Information from 12/11/12 Ltr, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants. Project stage: RAI ULNRC-05952, Regarding Adoption of National Fire Protection Association Standard NFPA 8052013-02-19019 February 2013 Regarding Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Other ML13051A4502013-02-19019 February 2013 Enclosure 1, W/Attachments to ULNRC-05952 - Request for Additional Information (RAI) with Callaway Plant, Response Project stage: Request ML13204A2232013-07-30030 July 2013 Request for Additional Information, License Amendment Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML13260A5912013-08-16016 August 2013 Request for Additional Information Email, Nrr/Dra/Afpb 18.01, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML13296A5302013-10-23023 October 2013 NRR E-mail Capture - Callaway - Request for NFPA 805 License Amendment Factual Accuracy Review Project stage: Acceptance Review ML13246A3502013-10-31031 October 2013 NFPA-805 LAR F&O Table Project stage: Other ML13318A1222013-11-14014 November 2013 NRR E-mail Capture - FW: Callaway NFPA 805 LAR, Fpe RAI 20 Project stage: RAI ML13274A5962014-01-13013 January 2014 Issuance of Amendment No. 206, Adopt National Fire Protection Association Standard 805, Performance Based Standard for Fire Protection for LWR Generating Plants Project stage: Approval ML14045A2842014-02-14014 February 2014 Amendment 31 to License Renewal Application Regarding Fire Protection Project stage: Other 2012-07-12
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000483/20240032024-10-23023 October 2024 Integrated Inspection Report 05000483/2024003 IR 05000483/20240132024-10-21021 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000483/2024013 IR 05000483/20244012024-10-0909 October 2024 Material Control and Accounting Program Inspection Report 05000483/2024401 Public ULNRC-06901, Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter)2024-10-0101 October 2024 Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter) ML24247A3042024-09-11011 September 2024 Regulatory Audit Questions for License Renewal Commitments 34 and 35 (EPID L-2024-LRO-0009) - Non-Proprietary IR 05000483/20244032024-08-28028 August 2024 Security Baseline Inspection 05000483-2024-403 IR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) IR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24158A5222024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation ML24036A1712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0079 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) IR 05000483/20230042024-01-19019 January 2024 – Integrated Inspection Report 05000483/2023004 ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 2024-09-11
[Table view] |
Text
WAmeren MISSOURI April 17, 2012 ULNRC-05851 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Ladies and Gentlemen:
10 CFR 50.90 DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO. FACILITY OPERATING LICENSE NPF-30 Callaway Plant RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING ADOPTION OF NATIONAL FIRE PROTECTION ASSOCIATION STANDARD NFPA 805 (TAC No. ME7046)
Reference:
- 1) Ameren Missouri Letter ULNRC-05781, "Request for License Amendment to Adopt NFPA 805, 'Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)' (License Amendment Request LDCN 11-0012)," dated August 29, 2011.
Reference:
- 2) Ameren Missouri Letter ULNRC-05823, "Clarification oflnformation Contained in Request for License Amendment to Adopt NFPA 805, 'Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)' (LDCN 11-0012)," dated November 9, 2011. In Reference 1, Union Electric Company (dba Ameren Missouri) requested an amendment to Facility Operating License Number NPF-30 for the Callaway Plant pursuant to 10 CFR 50.90. The letter and its attachments were submitted for the purpose of adopting a new fire protection licensing basis based on NFPA 805 which complies with the requirements in 10 CFR 50.48(a) and (c) and the guidance in Revision 1 of Regulatory Guide (RG) 1.205, "Risk-Informed, Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants." In Reference 2 supplemental information requested by the Nuclear Regulatory Commission (NRC) Staff was provided in order to complete the acceptance review of the application.
PO Box 620 Fulton, MD 65251 AmerenMissouri.com ULNRC-05851 April 17, 2012 Page2 On March 2, 2012 Callaway Plant formally received from the NRC Staff a request for additional information (RAI) related to this application request (Reference Agencywide Documents Access and Management System (ADAMS) Accession No. ML120600186).
On April12, 2012 a teleconference with the NRC Staff was conducted to discuss draft responses to the RAI discussed above. During this teleconference, Ameren Missouri was requested to withhold responses to certain RAI questions in order to resolve follow-up questions as well as allow additional time for the NRC Staff to complete its review of the remaining draft responses.
The purpose of this letter is to provide the responses to RAI questions which have been determined acceptable to the NRC Staff. The responses to the remaining RAI questions will be provided based on an agreed upon completion date with the NRC Staff during the week of April 16, 2012. Enclosure 1 provides the available RAI question responses.
Enclosure 1 also contains a description of changes to the license amendment request (LAR) that Ameren Missouri has identified in connection with responding to the RAI. Attachments are provided with the enclosure to show the LAR Transition Report changes from the original submittal.
This submittal does contain revised/new commitments which are provided in the revised LAR Transition Report Attachment S, Plant Modifications and Items to be Completed during Implementation.
The No Significant Hazards Consideration determination provided in the original submittal is not altered by the additional information provided in this letter. Ifthere are any questions, please contact Mr. Scott Maglio at (573) 676-8719 or Mr. Roger Wink at (314) 225-1561.
I declare under penalty of perjury that the foregoing is true and correct. Sincerely, Executed on: t.f/ 11 /'ZDI Xlt<>t{A.
V Scott A. Maglio Regulatory Affairs Manager RCW/nls Enclosure 1 : Request for Additional Information (RAI) with Callaway Plant Response ULNRC-05851 April17, 2012 Page3 cc: U.S. Nuclear Regulatory Commission (Original and 1 copy) Attn: Document Control Desk Washington, DC 20555-0001 Mr. Elmo E. Collins Regional Administrator U. S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Mohan C. Thadani (2 copies) Senior Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 0-8B 1 Washington, DC 20555-2738 ULNRC-05851 April 17, 2012 Page4 Index and send hardcopy to QA File A160.0761 Hardcopy:
Certrec Corporation 4150 International Plaza Suite 820 Fort Worth, TX 76109 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)
Electronic distribution for the following can be made via Tech Spec ULNRC Distribution:
A. C. Heflin F. M. Diya C. 0. Reasoner III D. W. Neterer L. H. Graessle J. S. Geyer S. A. Maglio R. Holmes-Bobo NSRB Secretary T. B. Elwood Mr. Bill Muilenburg (WCNOC) Mr. Tim Hope (Luminant Power) Mr. Ron Barnes (APS) Mr. Tom Baldwin (PG&E) Mr. Wayne Harrison (STPNOC) Ms. Linda Conklin (SCE) Mr. John O'Neill (Pillsbury Winthrop Shaw Pittman LLP) Missouri Public Service Commission Mr. Dru Buntin (DNR)