MONTHYEARML1124200222011-08-29029 August 2011 Request for License Amendment to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) (License Amendment Request LDCN 11-0012) Project stage: Request ULNRC-05823, Clarification of Information Contained in Request for License Amendment to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) (LDCN 11-0012)2011-11-0909 November 2011 Clarification of Information Contained in Request for License Amendment to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) (LDCN 11-0012) Project stage: Request ML1132602802011-11-22022 November 2011 Acceptance Review Email, Request for License Amendment to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Acceptance Review ML1132604512011-11-22022 November 2011 Correction Acceptance Review Email, Request for License Amendment to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Acceptance Review ML1201804512012-01-19019 January 2012 Regulatory Audit Plan for License Amendment Request to Implement NFPA 805, Risk-Informed, Performance-Based, Fire Protection Program Pursuant to 10 CFR 50.48(c) Project stage: Other ML1206004072012-02-15015 February 2012 Email, Request for Additional Information, Request to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1206004022012-02-15015 February 2012 Email, Request for Additional Information, Request to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1206001862012-03-0202 March 2012 Request for Additional Information, Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ULNRC-05851, Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 8052012-04-17017 April 2012 Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Response to RAI ML12108A2402012-04-17017 April 2012 Enclosure 1 to ULNRC-05851, Request for Additional Information (RAI) with Callaway Plant Response Project stage: Request ML12159A0942012-06-0606 June 2012 Email Request for Additional Information Round 2, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: Request ML12159A1032012-06-0606 June 2012 PRA Requests for Additional Information, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML12159A1112012-06-0606 June 2012 Fire Modeling Requests for Additional Information, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1217104322012-06-19019 June 2012 Email, Request for Additional Information Round 3, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1217104392012-06-19019 June 2012 Afpb, Request for Additional Information Round 3, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML1217104442012-06-19019 June 2012 Apla, Request for Additional Information Round 3, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML12194A6242012-07-12012 July 2012 Response to Request for Additional Information Re Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Response to RAI ML12335A2322012-12-11011 December 2012 Request for Additional Information, Round 2, Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML13008A3542013-01-0303 January 2013 Email Request for Additional Information,License Amendment Request to Adopt NFPA 805 Project stage: RAI ML13008A3502013-01-0808 January 2013 Email, Request for Additional Information License Amendment Request to Adopt NFPA 805 Project stage: RAI ML13022A0242013-01-22022 January 2013 Email, Two Revised Requests for Additional Information from 12/11/12 Ltr, Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants Project stage: RAI ULNRC-05952, Regarding Adoption of National Fire Protection Association Standard NFPA 8052013-02-19019 February 2013 Regarding Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Other ML13051A4502013-02-19019 February 2013 Enclosure 1, W/Attachments to ULNRC-05952 - Request for Additional Information (RAI) with Callaway Plant, Response Project stage: Request ML13204A2232013-07-30030 July 2013 Request for Additional Information, License Amendment Request to Adopt National Fire Protection Association Standard NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ULNRC-06011, Responses to RAI Set 3 Regarding Adoption of National Fire Protection Association Standard NFPA 8052013-08-0505 August 2013 Responses to RAI Set 3 Regarding Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Response to RAI ML13260A5912013-08-16016 August 2013 Request for Additional Information Email, Nrr/Dra/Afpb 18.01, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) Project stage: RAI ML13296A5302013-10-23023 October 2013 NRR E-mail Capture - Callaway - Request for NFPA 805 License Amendment Factual Accuracy Review Project stage: Other ML13318A1222013-11-14014 November 2013 NRR E-mail Capture - FW: Callaway NFPA 805 LAR, Fpe RAI 20 Project stage: RAI ML13274A5962014-01-13013 January 2014 Issuance of Amendment No. 206, Adopt National Fire Protection Association Standard 805, Performance Based Standard for Fire Protection for LWR Generating Plants Project stage: Approval ML14045A2842014-02-14014 February 2014 Amendment 31 to License Renewal Application Regarding Fire Protection Project stage: Other 2012-07-12
[Table View] |
Text
Lent. Susan From:
Lyon, Fred Sent:
Thursday, January 03, 2013 12:14 PM To:
rwink@amerin.com
Subject:
FW: ME7046 Additional AFPS, APLA, AND AHPS RAls for Callaway Plant, LAR to Adopt NFPA 805 From: Lyon, Fred Sent: Thursday[ January 03[ 2013 10:42 AM To: 'Elwood, Thomas S'
Subject:
FW: ME7046 Additional AFPB[ APLA, AND AHPB RAIs for Callaway Plant[ LAR to Adopt NFPA 805 FYI, the reviewer for DC Cook won't be back until Monday. Hopefully we can resolve the then. We want the DC Cook and Callaway RAls to worded the same.
From: Lyon[ Fred Sent: Thursday, January 03[ 2013 8:36 AM To: 'Elwood, Thomas B'
Subject:
FW: ME7046 Additional AFPB[ APLA[ AND AHPB RAIs for Callaway Plant, LAR to Adopt NFPA 805 Tom, the staff provided the following for consideration. Thanks, From: Robinson, Jay Sent: Thursday, January 03[ 2013 8:08 AM To: Lyon, Fred Cc: Fields[ Leslie
Subject:
RE: ME7046 Additional AFPB[ APLA[ AND AHPB RAIs for callaway Plant, LAR to Adopt NFPA 805 staff has provided some additional information for FM RAt 03.01 b. The contractor is in Texas so a late morning or early after call would be best if needed. If the following can be provided to the licensee maybe there won't be a need for a phone call on this RAI:
Based on the staffs independent calculations, EPM overestimated the plume radius for scenario C-31. 3618-8 because their calculations appear to be for thermoplastic cable targets. This is an error because the plant only has thermoset cable targets. The effect of the error, if any, is that the ZOI estimates are more conservative.
The intent of the RAI is (1) to advise the licensee that there is an error in the plume radius calculations and (2) to have the licensee confirm on the docket that the error has no ( adverse) effect on the results of the risk calculations.
in regards to PRA RAt 35, (Ray Gallucci) agrees to defer the RAI until the wording is resolved for DC Cook. The would be resubmitted at a later So there is no for a phone call.
I am following lip with the reviewers for DC Cook and will see where that RAI is and try to facilitate If you questions, let me know. Thanks. Jay.
From: Lyon, Fred Sent: Wednesday, January 02,2013 7:34 AM To: Fields, Leslie; Robinson, Jay
Subject:
RE: ME7046 Additional AFPB, APLA, AND AHPB RAls for Callaway Plant, LAR to Adopt NFPA 805 Leslie, Callaway requests a clarification phoncon with staff I can set one up using Outlook or you can me available times, Jay's email 11 let me know.
Jay, fyi, the licensee had the following Clarification is requested for FM RAt 03.01 b. The RAI states that the independent calculations for fire scenario C-31.3618-8 determined that thermoplastic damage criteria was used to calculate the plume radius. We are having difficulty determining where the NRC is finding this problem and request more specific details about the issue so we can respond accurately.
PRA RAI 35. We understand that the NRC is discussing a draft RAt for DC Cook that is nearly identical (to our RAI 35) but is being revised. We request the response to PRA RAt 35 on MCR Abandonment be deferred until after the specific RAt wording is resolved at DC Cook and at which time we would answer the revised RAt Thanks, Fred 2