June 29, 2016 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 John A. Dent, Jr. Site Vice President
SUBJECT:
Pilgrim Nuclear Power Station's Fourth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)
REFERENCES:
Pilgrim Nuclear Power Station Docket No. 50-293 Renewed License No. DPR-35 1. NRC Order Number EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions,-" dated June 6, 2013 (Accession No. ML 13143A334) 2. NRC Interim Staff Guidance JLD-ISG-2013-02, "Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated November 2013 (Accession No. ML 13304B836) 3. NRC Endorsement of Industry "Hardened Containment Venting System (HCVS) Phase 1 Overall Integrated Plan Template (EA-13-109), Rev O" (Accession No. ML 14128A219) 4. NEI 13-02, "Industry Guidance for Compliance with NRC Order EA-13-109, To Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated November 2013 5. Entergy's Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 30, 2014 6. Notification of Permanent Cessation of Power Operations dated November 10, 2015 (Accession No. ML 15328A053) (PNPS letter 2.15.080) 7. Pilgrim Nuclear Power Station's Third Six-Month Status Report, Phase 2 Overall Integrated Plan, and Responses to Phase 1 Interim Staff Evaluation Open Items in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) (Accession No. ML 15358A042) (PNPS Letter 2.15.082) LETTER NUMBER: 2.16.031 Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station
Dear Sir or Madam:
Letter No. 2.16.031 Page 2 of 3 On June 6, 2013, the U. S. Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Entergy Nuclear Operations, Inc. (Entergy). Reference 1 was immediately effective and directs Entergy to install a reliable hardened venting capability for pre-core damage and under severe accident conditions, including those involving a breach of the reactor vessel by molten core debris. Specific requirements are outlined in Attachment 2 of Reference 1. Reference 1 required submission of Phase 1 and Phase 2 overall integrated plans pursuant to Section IV, Condition D. Reference 3 endorses industry guidance document NEI 13-02, Revision 0 (Reference 4) with clarifications and exceptions identified in Reference 2. References 5 and 7 provided the Entergy Phase 1 and Phase 2 overall integrated plans. Reference 1 requires submission of a status report at six-month intervals following submittal of the overall *integrated plan. References 2 and 4 provide direction regarding the content of the status reports. The purpose of this letter is to provide the fourth six-month status report pursuant to Section IV, Condition D, of Reference 1, that delineates pmgress made in implementing the requirements of Reference 1. The attached status report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any. Per Reference 6, Entergy plans to permanently cease operation of PNPS no later than June 1, 2019. The Hardened Containment Vent System Phase 1 and Phase 2 strategies documented in this submittal were accurate descriptions of the planned modifications and/or strategies to satisfy the requirements of NRC Order EA-13-109. However, based on Reference 6, an alternative approach1to the containment hardened vent Phase 1 and Phase 2 requirements will be submitted to the NRC with a request for extension of Order EA-13-109 to late-year 2019 to allow NRC approval of Order rescission. If you have any questions or require additional information, please contact Mr. Everett Perkins, Jr. at (508) 830-8323. There are no regulatory commitments contained in this letter. I declare under penalty of perjury that the foregoing is true and correct; executed on June 29, 2016. A. Dent, Jr. Site ice President JAD/rb Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station Letter No. 2.16.031 Page 3 of 3
Attachment:
Pilgrim Nuclear Power Station's Fourth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) cc: Mr. Daniel H. Dorman Regional Administrator, "Region I U.S. Nuclear Regulatory Commission 2100 Renaissance Boulevard, Suite 100 King of Prussia, PA 19406-1415 U. S. Nuclear Regulatory Commission Director, Office of Nuclear Reactor Regulation Washington, DC 20555-0001 Ms. Booma Venkataraman, Project Manager Office of Nuclear Reactor Regulation ,U.S. Nuclear Regulatory Commission Mail Stop 0-8C2A Washington, DC 20555 Mr. John Giarrusso Jr. Planning, Nuclear and Preparedness Section Chief Mass .. Emergency Management Agency 400 Worcester Road Framingham, MA 01702 NRC Resident Inspector Pilgrim Nuclear Power Station ATTACHMENT To PNPS Letter 2.16.031 Pilgrim Nuclear Power Station's Fourth Six-Month Status Report in Response to June 6, 2013 Commission Order* Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) (4 pages)
Attachment PNPS Letter 2.16.031 Pilgrim Nuclear Power Station's Fourth Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) 1 Introduction In Reference 8, Pilgrim Nuclear Power Station (PNPS) informed the NRC of its intent to permanently cease power operations. PNPS will submit an alternate plan in lieu of complying with the requirements of EA-13-109. The provided information is basically unchanged except, for reflection of use of the alternate approach, from the prior six month update. PNPS is no longer pursuing any design or modifications related directly to this plan. However, to meet the regulatory requirement to provide six month updates, PNPS is submitting this update. PNPS developed an Overall Integrated Plan (OIP) (Reference 1 in Section 8), documenting the installation of a Hardened Cont?inment Vent System (HCVS) that provides a reliable hardened venting capability for pre-core damage and under severe accident conditions, including those involving a breach of the reactor vessel by molten core debris, in response to Reference 2. This attachment provides an update of milestone accomplishments since submittal .of the Phase 1 OIP and the previous Six Month Status Reports, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any. 2 Milestone Accomplishments The following milestone(s) have been completed since the development of the OIP (Reference 1 ), and are current as of June 29, 2016.
- The Overall Integrated Plan was issued on June 30, 2014.
- The First Six Month Status Report was issued on December 16, 2014.
- The Second Six Month Status Report issued on June 30, 2015.
- The Third Six Month Status Report was issued on December 17, 2015.
- The Interim Staff Evaluation (ISE) was received on March 24, 2015.
- The Fourth Six Month Status Report was issued on June 29, 2016 (This submittal).
- 3. Milestone Schedule Status r The following provides an update to Part 5 of the OIP. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed. Milestone Target Activity Status Comments Completion Date Complete HCVS Gap Analysis June 2014 Complete Submit Overall Integrated Plan June 2014 Complete Submit 6 Month Status Report Oecember 2014 Complete Submit 6 Month Status Report June 2015 Complete Submit 6 Month Status Report December 2015 Complete Simultaneous with Phase 2 OIP Design Engineering On-site/Complete July 2016 Started Suspended Submit 6 Month Status Report June 2016 Complete Complete Operations Procedure Changes Developed December 2016 Not Started Suspended Site Specific Maintenance Procedure December 2016 Not Started Suspended* Developed Submit 6 Month Status Report December 2016 Not Started Training Complete December 2016 Not Started Suspended* Implementation Outage March 2017 Not Started Suspended Procedure Changes Active March 2017 Not Started Suspended* Walk Through Demonstration/Functional Test March 2017 Not Started Suspended* Submit Completion Report June 2017 Not Started Suspended Submit 6 Month Status Report June 2017 Not Started Submit 6 Month Status Report December 2017 Not Started Submit 6 Month Status Report June 2018 Not Started Submit 6 Month Status Report December 2018 Not Started Submit 6 Month Status Report June 2019 Not Started *Operations procedure changes may result from the alternate approach 4 Changes to Compliance Method There are no changes to the compliance method as documented in the Phase 1 OIP (Reference 1 ). ' 5 Need for Relief/Relaxation and Basis for the Relief/Relaxation As noted in this submittal cover letter, Entergy plans to permanently cease operation of PNPS no later than June 1, 2019. The HCVS Phase 1 and Phase 2 strategies documented in this submittal were accurate descriptions of the current modifications and/or strategies to satisfy the requirements of NRC Order EA-13-109. However, based on Reference 6, an alternative approach to the containment hardened vent Phase 1 and Phase 2 will be submitted to the NRC with a request for extension of the Order EA-13-109 to mid-year 2019 to allow NRC approval of Order rescission. 6 Open Items from Overall Integrated Plan and Interim Staff Evaluation PNPS has received the Interim Staff Evaluation (ISE) with Open Items identified (Reference 7). * / These open items have been addressed in Attachment 2 to the Third 6-month status report submittal dated December 17, 2015 via PNPS Letter 2.15.082. 7 Interim Staff Evaluation Impacts There are no potential impacts to the Phase 1 Interim Staff Evaluation identified at this time. ' 8 References The following references support the updates to the Phase 1 OIP described in this enclosure. 1. Pilgrim's Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 30, 2014 2. NRC Order Number EA-13-109, "Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" dated June 6, 2013 . ' 3. NEI 13-02, "Industry Guidance for Compliance with NRC Order EA-13-109, To Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated November 2013 4. NRC Interim Staff Guidance JLD-ISG-2013-02, "Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated November 2013 (Accession No. ML 133048836) 5. NRC Endorsement of Industry "Hardened Containment Venting System (HCVS) Phase 1 Overall Integrated Plan Template (EA-13-109) Rev O" (Accession No. ML 14128A219) 6. Nuclear Regulatory Commission Audits of Licensee Responses to Phase 1 of Order EA-13-109 to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions (Accession No. ML 14126A545)
- 7. Nuclear Regulatory Commission Interim Staff Evaluation dated March 24, 2015, "Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 1 of Order EA-13-109 (Severe Accident Capable Hardened Vents). (Accession No. ML 15043A754) (PNPS Letter 1.15.016) 8. Notification of Permanent Cessation of Power Operations dated November 10, 2015 (Accession No. ML 15328A053). (PNPS Letter 2.15.080)