Status of Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2002 - 10 CFR 50.75(f)(1)
ML030980522
Person / Time
Site: Indian Point, Pilgrim, Vermont Yankee, FitzPatrick  Entergy icon.png
Issue date: 03/31/2003
From: Kansler M
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, NRC/FSME
References
BVY-03-025, ENO Ltr.2.03.036, JPN-03-007, NL-03-056, RIS-01-007, FOIA/PA-2013-0151
Download: ML030980522 (16)


Text

Entergy Nuclear Northeast U- Entergy Nuclear Operations, Inc 15En terg'y 440 Hamilton Avenue White Plains, NY 10601 Tel 9142723200 Fax 914 272 3205 Michael R. Kansler President March 31, 2003 BVY-03-025 NL-03-056 JPN-03-007 ENO Ltr. 2.03.036 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

Entergy Nuclear Operations, Inc.

Indian Point Nuclear Generating Stations 1, 2 and 3 Docket Nos. 50-3, 50-247 and 50-286 Vermont Yankee Nuclear Power Station Docket No. 50-271 Pilgrim Nuclear Power Station Docket No. 50-293 James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Status of Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc.

For Year Ending December 31, 2002 - 10 CFR 50.75(f)(1)

References:

1. NUREG-1307, 'Report on Waste Burial Charges," Revision 10, dated October 2002.
2. NRC Regulatory Issue Summary 2001-07, "10 CFR 50.75(f)(1)

Reports on the Status of Decommissioning Funds (Due March 31, 2001)."

Dear Sir:

10 CFR 50.75(0(1) requires each power reactor licensee to report to the NRC by March 31, 1999, and every two years thereafter, on the status of its decommissioning funding for each reactor, or share of a reactor, that it owns. On behalf of Entergy Nuclear Indian Point 2 LLC, Entergy Nuclear Indian Point 3 LLC, Entergy Nuclear Vermont Yankee LLC, Entergy Nuclear Generation Company, and Entergy Nuclear FitzPatrick LLC, Entergy Nuclear Operations, Inc.

hereby submits the information requested for power reactors operated by Entergy Nuclear A (

Operations, Inc. U'0I 4,WZJ- 4" pasan"'o; Y-S

The estimated minimum decommissioning fund values were determined using the NRC's methodology in NUREG-1307 (Reference 1) and does not include activities outside of the scope of decommissioning as defined by 10 CFR 50.2.

Entergy will continue to monitor the status of the funds and will assure that we meet all NRC regulations and implement NRC guidance, as appropriate, to assure adequate funding for the decommissioning when required.

The information provided in Attachment 1 is based on NRC Regulatory Issue Summary 2001-07 (Reference 2).

There are no new commitments made in this letter. If you have any questions, please contact Ms. Charlene Faison at 914-272-3378.

Very tr uly2 achel R. Kansler President/

Attachment:

1. Status of Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. (Indian Point 1, Indian Point 2, Indian Point 3, Vermont Yankee, Pilgrim, and FitzPatrick) For Year Ending December 31, 2002 - 10 CFR 50.75(f)(1)
2. NRC Minimum Funding Calculation (10 CFR 50.75(c)) for Indian Point 1, Indian Point 2, Indian Point 3, Vermont Yankee, Pilgrim, and FitzPatrick cc: Next page.

2

cc:

Regional Administrator, Region I Mr. Travis Tate, Project Manager U.S. Nuclear Regulatory Commission Project Directorate I 475 Allendale Road Division of Licensing Project Management King of Prussia, PA 19406 Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mr. P. Milano Senior Project Manager Mail Stop 0-8B-1 Project Directorate 1-1 Washington, DC 20555-0001 Division of Licensing Project Management Office of Nuclear Reactor Regulation Senior Resident Inspector U. S. Nuclear Regulatory Commission U. S. Nuclear Regulatory Commission Mail Stop: O-8-C2 Pilgrim Nuclear Power Station Washington, DC 20555-0001 600 Rocky Hill Road Mail Stop 66 Resident Inspector's Office Plymouth, MA 02360 Indian Point 3 Nuclear Power Plant U. S. Nuclear Regulatory Commission Mr. R. M. Pulsifer, Project Manager P. O. Box 337 Project Directorate I Buchanan, NY 10511 Division of Licensing Project Management Office of Nuclear Reactor Regulation Mr. John L. Minns U. S. Nuclear Regulatory Commission Project Manager Mail Stop 0-8B-1 License Project Directorate IV-1 Washington, DC 20555-0001 Division of Licensing Project Management U. S. Nuclear Regulatory Commission USNRC Resident Inspector Mail Stop: 7-D-1 Vermont Yankee Nuclear Power Station Washington, DC 20555-0001 320 Governor Hunt Road P. 0. Box 157 Senior Resident Inspector Vernon, VT 05354 Indian Point 2 Nuclear Power Plant U. S. Nuclear Regulatory Commission Mr. David O'Brien P. O. Box 38 Commissioner Buchanan, NY 10511 Department of Public Service 120 State Street Mr. Guy Vissing, Project Manager Montpelier, VT 05602 Project Directorate I Office of Nuclear Reactor Regulation Mr. Paul Eddy U. S. Nuclear Regulatory Commission NYS Department of Public Service Mail Stop OWFN 8C2 3 Empire State Plaza, 10th Floor One White Flint North Albany, NY 12223 11555 Rockville Pike Rockville, MD 20852 Resident Inspector's Office James A. FitzPatrick Nuclear Power Plant U. S. Nuclear Regulatory Commission P. 0. Box 136 Lycoming, NY 13093 3

Attachment 1 to BVY-03-025, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

Status of Decommissioning Funding For Year Ending December 31, 2002 - 10 CFR 50.75(f)(1)

Plant Name: Indian Point Nuclear Generating Unit No. I

1. Amount of decommissioning funds estimated $297.80 million'[][21 to be required pursuant to 10 CFR 50.75 (b) and (c).

Decommissioning cost estimate escalated at $450.45 million 3.0% per year to the midpoint of decommissioning (December 2016).

2. Amount accumulated to the end of the $193.46 million 3]

calendar year preceding the date of the report (December 31, 2002).

Fund balance with 5.0% annual growth to the $383.03 million midpoint of decommissioning (December 2016).

3. A schedule of the annual amounts remaining None. [see item 7]

to be collected.

4. Assumptions used in determining rates of Escalation rate: 3.0%

escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates Rate of earnings: 5.0%

of other factors used in funding projections.

5. Any contracts upon which the licensee is None.

relying pursuant to 10 CFR 50.75(e)(1)(v).

6. Modifications occurring to a licensee's current None. [see item 7]

method of providing financial assurance since the last submitted report.

7. Any material changes to trust agreements. In November 2000, Con Edison entered into an agreement with Entergy for the sale of Indian Point 1 and 2. The agreement provided for a transfer of $430 million for which Entergy would assume full responsibility for decommissioning of both units.

Entergy established a $25 million provisional trust at closing to ensure that sufficient funds were available.

1

Attachment 1 to BVY-03-025, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

Status of Decommissioning Funding For Year Ending December 31, 2002 -10 CFR 50.75(f)(1)

Plant Name: Indian Point Nuclear Generating Unit No. 2

1. Amount of decommissioning funds estimated $355.11 million [1]

to be required pursuant to 10 CFR 50.75 (b) and (c).

Decommissioning cost estimate escalated at $537.13 million 3.0% per year to the midpoint of decommissioning (December 2016).

2. Amount accumulated to the end of the $232.03 million 3]

calendar year preceding the date of the report (December 31, 2002).

Fund balance with 5.0% annual growth to the $459.40 million midpoint of decommissioning (December 2016).

3. A schedule of the annual amounts remaining None. [see item 7]

to be collected.

4. Assumptions used in determining rates of Escalation rate: 3.0%

escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates Rate of earnings: 5.0%

of other factors used in funding projections.

5. Any contracts upon which the licensee is None.

relying pursuant to 10 CFR 50.75(e)(1)(v).

6. Modifications occurring to a licensee's current None. [see item 7]

method of providing financial assurance since the last submitted report.

7. Any material changes to trust agreements. In November 2000, Con Edison entered into an agreement with Entergy for the sale of Indian Point 1 and 2. The agreement provided for a transfer of $430 million for which Entergy would assume full responsibility for decommissioning of both units.

Entergy established a $25 million provisional trust at closing to ensure that sufficient funds were available.

2

Attachment 1 to BVY-03-025, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

Status of Decommissioning Funding For Year Ending December 31, 2002 - 10 CFR 50.75(f)(1)

Plant Name: Indian Point Nuclear Generating Unit No. 3

1. Amount of decommissioning funds estimated $353.70 million ill to be required pursuant to 10 CFR 50.75 (b) and (c).

Decommissioning cost estimate escalated at $567.58 million 3.0% per year to the midpoint of decommissioning (December 2018).

2. Amount accumulated to the end of the $336 million calendar year preceding the date of the report (December 31, 2002).

Fund balance with 5.0% annual growth to the $733.45 million midpoint of decommissioning (December 2018).

3. A schedule of the annual amounts remaining None.

to be collected.

4. Assumptions used in determining rates of Escalation rate: 3.0%

escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates Rate of earnings: 5.0%

of other factors used in funding projections.

5. Any contracts upon which the licensee is None.

relying pursuant to 10 CFR 50.75(e)(1)(v).

6. Modifications occurring to a licensee's current None.

method of providing financial assurance since the last submitted report.

7. Any material changes to trust agreements. None.

3

Attachment 1 to BVY-03-025, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

Status of Decommissioning Funding For Year Ending December 31, 2002 - 10 CFR 50.75(f)(1)

Plant Name: Vermont Yankee Nuclear Power Station

1. Amount of decommissioning funds estimated $395.97 million [I]

to be required pursuant to 10 CFR 50.75 (b) and (c).

Decommissioning cost estimate escalated at $581.49 million 3.0% per year to the midpoint of decommissioning (December 2015).

2. Amount accumulated to the end of the $315.85 million calendar year preceding the date of the report (December 31, 2002).

Fund balance with 5.0% annual growth to the $595.57 million midpoint of decommissioning (December 2015).

3. A schedule of the annual amounts remaining None. [see item 7]

to be collected.

4. Assumptions used in detefmining rates of Escalation rate: 3.0%

escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates Rate of eamings: 5.0%

of other factors used in funding projections.

5 Any contracts upon which the licensee is None.

relying pursuant to 10 CFR 50.75(e)(1)(v).

6. Modifications occurring to a licensee's current None. [see item 7]

method of providing financial assurance since the last submitted report.

7. Any material changes to trust agreements. In August 2001, Vermont Yankee Nuclear Power Corporation entered into an agreement with Entergy for the sale of Vermont Yankee nuclear unit. Upon the closing, $310.7 million was transferred to Entergy (Mellon Bank is the new trustee), which agreed to assume full responsibility for the decommissioning of the nuclear unit.

4

Attachment 1 to BVY-03-025, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

Status of Decommissioning Funding For Year Ending December 31, 2002 - 10 CFR 50.75(f)(1)

Plant Name: Pilgrim Nuclear Power Station

1. Amount of decommissioning funds estimated $408.16 million [1l to be required pursuant to 10 CFR 50.75 (b) and (c).

Decommissioning cost estimate escalated at $599.40 million 3.0% per year to the midpoint of decommissioning (December 2015).

2. Amount accumulated to the end of the $455.91 million calendar year preceding the date of the report (December 31, 2002).

Fund balance with 5.0% annual growth to the $859.68 million midpoint of decommissioning (December 2015).

3. A schedule of the annual amounts remaining None. [see item 7]

to be collected.

4. Assumptions used in determining rates of Escalation rate: 3.0%

escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates Rate of earnings: 5.0%

of other factors used in funding projections.

5. Any contracts upon which the licensee is None.

relying pursuant to 10 CFR 50.75(e)(1)(v).

6. Modifications occurring to a licensee's current None. [see item 7]

method of providing financial assurance since the last submitted report.

7. Any material changes to trust agreements. None (as of December 2002).

As of March 2003, Entergy has instructed Mellon Bank, the trustee, to transfer the balance in the Provisional Fund ($28.5 million) to the non-qualified portion of the Master Trust. The Provisional Trust will then be terminated.

5

Attachment 1 to BVY-03-025, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

Status of Decommissioning Funding For Year Endina December 31. 2002 - 10 CFR 50.75(f)(1)

Plant Name: James A. Fitzpatrick Nuclear Power Plant

1. Amount of decommissioning funds estimated $424.36 million [l1 to be required pursuant to 10 CFR 50.75 (b) and (c).

Decommissioning cost estimate escalated at $661.15 million 3.0% per year to the midpoint of decommissioning (December 2017).

2. Amount accumulated to the end of the $367 million calendar year preceding the date of the report (December 31, 2002).

Fund balance with 5.0% annual growth to the $762.97 million midpoint of decommissioning (December 2017).

3. A schedule of the annual amounts remaining None.

to be collected.

4. Assumptions used in determining rates of Escalation rate: 3.0%

escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates Rate of earnings: 5.0%

of other factors used in funding projections.

5. Any contracts upon which the licensee is None.

relying pursuant to 10 CFR 50.75(e)(1)(v).

6. Modifications occurring to a licensee's current None.

method of providing financial assurance since the last submitted report.

7. Any material changes to trust agreements. None.

6

Attachment 1 to BVY-03-025, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

Status of Decommissioning Funding For Year Ending December 31. 2002 - 10 CFR 50.75(f)(1)

Notes:

[1] The calculation of the NRC minimum value is provided in Attachment 2.

[2] In accordance with 10 CFR 50.75(c)(i)(1) PWR reactors below 1200 MWt are to use this minimum value. Indian Point 1 had a thermal power level of 615 MWt. (Refer to Attachment 3, pg. 15, of June 8, 2001 letter, M. R. Kanslerto USNRC regarding "Response to June 5, 2001 Letter, Indian Point Nuclear Generating Unit Nos. 1 and 2, Transfer of Facility Operating License (TAC Nos. MB0743 and MB0744).")

[3] The current fund balances for Indian Point 1 and 2 do not include an additional $25.42 million available in the provisional fund.

7

Attachment 2 to BVY-03-036, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

NRC Minimum Funding Calculation (10 CFR 50.75(c))

Plant Name: Indian Point Nuclear Generating Unit No. I Inputs:

Plant Characteristics Plant Type (PWR or BWR) PWR Region NE (Northeast)

Rated (in MWt) [1l 615 (NUREG-1350, Vol. 14)

Year 2002 Waste Vendor Used (Yes/No) Yes Burial Site South Carolina Atlantic Compact Member (Yes/No) No Producer Price Index wpu0543 (industrial electric power) 139.6 (December 2002) wpu0573 (light fuel oils) 84.7 Labor Adiustment Factors ecu13102i (Northeast) 161.3 (4th Quarter, 2002)

Burial Site Adiustments (South Carolina/non-Atlantic Compact Member)

PWR - direct disposal 18.732 (NUREG-1307, Rev. 10)

PWR - w/waste vendors 9.467 BWR - direct disposal 16.705 BWR - w/waste vendors 8.860 Adiustment Factors Energy (E) 1.143 Labor (L) 1.922 Burial (B) 9.467 Minimum Amount (millions, $1986) $85.56 (size adjusted for megawatts)

Escalation Factor (L, E, B) 3.481 (65% L, 13% E, 22% B)

NRC Minimum (millions, $2002) $297.80 wlwaste vendor 1] In accordance with 10 CFR 50 75(c)(i)(1) PWR reactors below 1200 MWt are to use this minimum value Indian Point 1 had a thermal power level of 615 MWt (Refer to Atachment 3, pg 15, of June 8,2001 letter, M. R Kansler to USNRC regarding 'Response to June 5, 2001 Letter, Indian Point Nuclear Generating Unit Nos. 1 and 2, Transfer of Facility Operating License (TAC Nos. MB0743 and MB0744) ")

1

Attachment 2 to BVY-03-036, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

NRC Minimum Funding Calculation (10 CFR 50.75(c))

Plant Name: Indian Point Nuclear Generating Unit No. 2 Inputs:

Plant Characteristics Plant Type (PWR or BWR) PWR Region NE (Northeast)

Rated (in MWt) 3071 (NUREG-1350, Vol. 14)

Year 2002 Waste Vendor Used (Yes/No) Yes Burial Site South Carolina Atlantic Compact Member (Yes/No) No Producer Price Index wpu0543 (industrial electric power) 139.6 (December 2002) wpu0573 (light fuel oils) 84.7 Labor Adiustment Factors ecu13102i (Northeast) 161.3 (4th Quarter, 2002)

Burial Site Adiustments (South Carolina/non-Atlantic Compact Member)

PWR - direct disposal 18.732 (NUREG-1307, Rev. 10)

PWR - w/waste vendors 9.467 BWR - direct disposal 16.705 BWR - w/waste vendors 8.860 Adjustment Factors Energy (E) 1.143 Labor (L) 1.922 Burial (B) 9.467 Minimum Amount (millions, $1986) $102.02 (size adjusted for megawatts)

Escalation Factor (L, E, B) 3.481 (65% L, 13% E, 22% B)

NRC Minimum (millions, $2002) l $355.11 wlwaste vendor 2

Attachment 2 to BVY-03-036, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

NRC Minimum Funding Calculation (10 CFR 50.75(c))

Plant Name: Indian Point Nuclear Generating Unit No. 3 Inputs:

Plant Characteristics Plant Type (PWR or BWR) PWR Region NE ( Nlortheast)

Rated (in MWt) 3025 (D4UREG-1350, Vol. 14)

Year 2002 Waste Vendor Used (Yes/No) Yes Burial Site South CarcAlina Atlantic Compact Member (Yes/No) No Producer Price Index wpu0543 (industrial electric power) 139.6 ([)ecember 2002) wpu0573 (light fuel oils) 84.7 Labor Adjustment Factors ecu13102i (Northeast) 161.3 (4th Quarter, 2002)

Burial Site Adiustments (South Carolina/non-Atlantic Compact Member)

PWR - direct disposal 18.732 (NUREG-1307, Rev. 10)

PWR - w/waste vendors 9.467 BWR - direct disposal 16.705 BWR - w/waste vendors 8.860 Adiustment Factors Energy (E) 1.143 Labor (L) 1.922 Burial (B) 9.467 Minimum Amount (millions, $1986) $101.62 (size adjusted for megawatts)

Escalation Factor (L, E, B) 3.481 (65% L, 13% E, 22% B)

NRC Minimum (millions, $2002) 1 $353.70 wlwaste vendor 3

Attachment 2 to BVY-03-036, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

NRC Minimum Funding Calculation (10 CFR 50.75(c))

Plant Name: Vermont Yankee Nuclear Power Station Inputs:

Plant Characteristics Plant Type (PWR or BWR) BWR Region NE (Northeast)

Rated (in MWt) 1593 (NUREG-1350, Vol. 14)

Year 2002 Waste Vendor Used (Yes/No) Yes Burial Site South Carolina Atlantic Compact Member (Yes/No) No Producer Price Index wpu0543 (industrial electric power) 139.6 (December 2002) wpu0573 (light fuel oils) 84.7 Labor Adiustment Factors ecu13102i (Northeast) 161.3 (4th Quarter, 2002)

Burial Site Adiustments (South Carolina/non-Atlantic Compact Member)

PWR - direct disposal 18.732 (NUREG-1307, Rev. 10)

PWR - w/waste vendors 9.467 BWR - direct disposal 16.705 BWR - w/waste vendors 8.860 Adiustment Factors Energy (E) 1.135 Labor (L) 1.922 Burial (B) 8.860 Minimum Amount (millions, $1986) $118.34 (size adjusted for megawatts)

Escalation Factor (L, E, B) 3.346 (65% L, 13% E, 22% B)

NRC Minimum (millions, $2002) l $395.97 l w/waste vendor 4

Attachment 2 to BVY-03-036, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

NRC Minimum Funding Calculation (10 CFR 50.75(c))

Plant Name: Pilgrim Nuclear Power Station Inputs:

Plant Characteristics Plant Type (PWR or BWR) BWR Region NE (Northeast)

Rated (in MWt) 1998 (NUREG-1350, Vol. 14)

Year 2002 Waste Vendor Used (Yes/No) Yes Burial Site South Carolina Atlantic Compact Member (Yes/No) No Producer Price Index wpu0543 (industrial electric power) 139.6 (December 2002) wpu0573 (light fuel oils) 84.7 Labor Adiustment Factors ecu13102i (Northeast) 161.3 (4th Quarter, 2002)

Burial Site Adiustments (South Carolina/non-Atlantic Compact Member)

PWR - direct disposal 18.732 (NUREG-1307, Rev. 10)

PWR - w/waste vendors 9.467 BWR - direct disposal 16.705 BWR - w/waste vendors 8.860 Adiustment Factors Energy (E) 1.135 Labor (L) 1.922 Burial (B) 8.860 Minimum Amount (millions, $1986) $121.98 (size adjusted for megawatts)

Escalation Factor (L, E, B) 3.346 (65% L, 13% E, 22% B)

NRC Minimum (millions, $2002) l $408.16 w/waste vendor 5

Attachment 2 to BVY-03-036, NL-03-056, JPN-03-007, ENO Ltr. 2.03.036 Entergy Nuclear Operations, Inc.

NRC Minimum Funding Calculation (10 CFR 50.75(c))

Plant Name: James A. Fitzpatrick Nuclear Power Plant Inputs:

Plant Characteristics Plant Type (PWR or BWR) BWR Region NE (Northeast)

Rated (in MWt) 2536 (NUREG-1350, Vol. 14)

Year 2002 Waste Vendor Used (Yes/No) Yes Burial Site South Carolina Atlantic Compact Member (Yes/No) No Producer Price Index wpu0543 (industrial electric power) 139.6 (December 2002) wpu0573 (light fuel oils) 84.7 Labor Adiustment Factors ecu13102i (Northeast) 161.3 (4th Quarter, 2002)

Burial Site Adiustments (South Carolina/non-Atlantic Compact Member)

PWR - direct disposal 18.732 (NUREG-1307, Rev. 10)

PWR - w/waste vendors 9.467 BWR - direct disposal 16.705 BWR - w/waste vendors 8.860 Adiustment Factors Energy (E) 1.135 Labor (L) 1.922 Burial (B) 8.860 Minimum Amount (millions, $1986) $126.82 (size adjusted for megawatts)

Escalation Factor (L, E, B) 3.346 (65% L, 13% E, 22% B)

NRC Minimum (millions, $2002) $424.36 w/waste vendor 6