|
---|
Category:Legal-Order
MONTHYEARML20317A1172020-11-12012 November 2020 Commission Memorandum and Order (CLI-20-12) ML20206K8542020-07-22022 July 2020 Order Directing Dismissal of Case (DC Cir.)(Case No. 19-1198) NRC-72-1044, 7-22-20 Order (DC Cir.)(Case No. 19-1198)(Consolidated with 20-1019)2020-07-22022 July 2020 7-22-20 Order (DC Cir.)(Case No. 19-1198)(Consolidated with 20-1019) ML20156A4042020-06-0404 June 2020 Order of the Secretary ML20062G8622020-03-12012 March 2020 2-12-20 Order Consolidating Cases (DC Cir.)(Case No. 19-1198) ML20014E6612020-01-14014 January 2020 Letter from Commission Secretary Annette Vietti-Cook to Janet Azarovitz ML19353C7492019-12-19019 December 2019 Letter from Commission Secretary Annette Vietti-Cook to Mary Lampert of Pilgrim Watch ML19351D6952019-12-17017 December 2019 Commission Memorandum and Order (CLI-19-11) ML19303B3132019-10-28028 October 2019 Statement of Issues (DC Cir.)(Case No. 19-1198) 10-28-19 ML19274B2762019-09-27027 September 2019 Massachusetts Scheduling Order (DC Cir.)(Case No. 19-1198)- 9-27-19 ML19256C4952019-09-13013 September 2019 Order (Granting Motion for Twenty-Two Minute Enlargement of Time) ML19255J0832019-09-12012 September 2019 Letter from Commission Secretary Annette Vietti-Cook to David Madigan, Et Al ML19283C9552019-09-11011 September 2019 Letter from Commission Secretary Annette Vietti-Cook to Congressman William R. Keating ML19253D1862019-09-10010 September 2019 Letter from Commission Secretary Annette Vietti-Cook to Diane Turco and Deb Katz ML19248C8112019-09-0505 September 2019 Order (Clarifying Deadline for Responding to Motions for Stay) ML19246A8082019-09-0303 September 2019 Letter from NRC Acting Secretary, Rochelle C. Bavol, to Judeth Van Hamm ML19241A5872019-08-29029 August 2019 Letter from NRC Acting Secretary, Richard Laufer, to Lawrence Delafield ML19241A5882019-08-29029 August 2019 Letter from NRC Acting Secretary, Richard Laufer, to Janet Azarovitz ML19238A2792019-08-26026 August 2019 Letters from NRC Acting Secretary, Rochelle Bavol, to Senator Markey, Senator Warren and Congressman Keating Re Pilgrim Nuclear Power Station License Transfer Request ML19238A2832019-08-26026 August 2019 Letter from NRC Acting Secretary to Diane Turco of Cape Downwinders and Deb Katz of Citizens Awareness Network ML19238A2982019-08-26026 August 2019 Letter from NRC Acting Secretary to Henrietta Cosentino of the Plymouth Area League of Women Voters ML19170A1012019-08-22022 August 2019 Letter, Order Approving Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator ML19233A2892019-08-21021 August 2019 Order (Granting Motion for Extension of Time) ML19228A1322019-08-16016 August 2019 Order (Clarifying NRC Staff Filing of a Notification of Significant Licensing Action) ML19226A1072019-08-14014 August 2019 Commission Memorandum and Order CLI-19-08 ML19225D2552019-08-13013 August 2019 Letter to the Honorable Edward J. Markey from Annette L. Vietti-Cook, Secretary of the Commission ML19095B1692019-04-0505 April 2019 Memorandum to the Parties (Regarding Commissioner Caputo'S Upcoming Site Visit) ML19079A3012019-03-20020 March 2019 Order (Granting Petitioners Extension of Time to Reply to Applicants' Answer) ML19066A3152019-03-0707 March 2019 Letters from Commission Secretary Annette Vietti-Cook to Senators Edward J. Markey, Elizabeth Warren, and Bill Keating ML19059A4442019-02-28028 February 2019 Letter from Commission Secretary Annette Vietti-Cook to Senator Vinny Demacedo, Et Al ML17096A7362017-04-0606 April 2017 Commission Memorandum and Order (CLI-17-06) ML16299A1852016-10-20020 October 2016 Letter from the Chairman to Senator Edward J. Markey, Et Al. Re Entergy Nuclear Operations, Inc. Request for Extension of Time to Comply with NRC Order EA-13-109 for Pilgrim Nuclear Power Station ML12341A0782012-12-0606 December 2012 CLI-12-21 Memorandum and Order Denying Jones River Watershed Association and Pilgrim Watch Review of LBP-12-11 ML12264A3882012-09-18018 September 2012 Entergy Nuclear Operations, Inc.; Entergy Nuclear Generation Company Order Granting Extension ML12264A3942012-09-18018 September 2012 Entergy Nuclear Operations, Inc.; Entergy Nuclear Generation Company Corrected Order ML12202B0802012-07-20020 July 2012 Memorandum and Order (Denying Petition for Intervention and Request to Reopen Proceeding and Admit New Contention) ML12202B1742012-07-20020 July 2012 Order of the Secretary Extending Time for Commission Review of LBP-12-11 ML12170A9142012-06-18018 June 2012 Memorandum and Order (Denying Petition for Intervention and Request to Reopen Proceeding and Admit New Contention, LBP-12-11) ML12159A1522012-06-0707 June 2012 Memorandum and Order - CLI-12-15 ML12146A1112012-05-25025 May 2012 Response of the Secretary to the April 30, 2012 Request of Pilgrim Water and Jones River Watershed Association Opposing NRC Staff'S Recommendation in Secy 12-0062 ML12145A6262012-05-24024 May 2012 Memorandum and Order (Denying Petition for Intervention and Request to Reopen the Proceeding and Admit New Contention) ML12138A1112012-05-17017 May 2012 Memorandum and Order, (Requesting Filing on Petitions Under 10 C.F.R. 2.206) ML12138A1502012-05-17017 May 2012 Establishment of Atomic Safety and Licensing Board in the Matter of the Pilgrim Nuclear Power Station ML12138A3022012-05-17017 May 2012 Order (Granting NRC Staff'S Unopposed Motion for Extension; Seeking Input from Parties) ML12137A3132012-05-16016 May 2012 Memorandum of the Secretary Referring the Jones River Watershed Association and Pilgrim Watch'S Request to Reopen the Record, for a Hearing, to File New Contentions, and Jones River Watershed Association Motion to Intervene, in the Pilgrim ML12136A5582012-05-15015 May 2012 Establishment of Atomic Safety and Licensing Board in the Matter of Entergy Nuclear Operations, Inc., License Renewal for Pilgrim Nuclear Power Station ML12131A6392012-05-10010 May 2012 Secretary Referral Memorandum Referring the Jones River Watershed Association Motion to Reopen, Request for Hearing and Request to File a New Contention, in the Pilgrim Nuclear Power Station, Docket No. 50-293-LR Proceeding ML12109A1182012-04-18018 April 2012 Inquiry (Regarding Information on Expected NMFS ESA Determination) ML12093A2702012-04-0202 April 2012 Establishment of Atomic Safety and Licensing Board ML12090A5182012-03-30030 March 2012 Commission Memorandum and Order CLI-12-10 2020-07-22
[Table view] |
Text
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION DOCKETED 01/31/08 ATOMIC SAFETY AND LICENSING BOARD PANEL SERVED 01/31/08 Before Administrative Judges:
Ann Marshall Young, Chair Dr. Paul B. Abramson Dr. Richard F. Cole In the Matter of: Docket No. 50-293-LR ENTERGY NUCLEAR GENERATION ASLBP No. 06-848-02-LR COMPANY AND ENTERGY NUCLEAR OPERATIONS, INC. January 31, 2008 (Pilgrim Nuclear Power Station)
ORDER (Board Questions for the NRC Staff and Applicant)
The Board received the initial filings of direct testimony from the Applicant on January 8, 2008,1 and from the NRC Staff on January 30, 2008.2 In response to these filings the Board hereby directs both the NRC Staff and the Applicant to answer the following questions in detailed filings by February 11, 2008. These questions are considered to be in addition to any other questions the Board might present to the parties on or before February 18, 2008, pursuant to our scheduling order of December 19, 2007.3 1
Entergys Initial Statement of Position on Pilgrim Watch Contention 1 and Supporting Exhibits (Jan. 8, 2008).
2 NRC Staff Initial Statement of Position on Contention 1 and Supporting Exhibits (Jan.
8, 2008).
3 Licensing Board Order (Revising Schedule for Evidentiary Hearing and Responding to Pilgrim Watchs December 14 and 15 Motions) (Dec. 19, 2007).
Board Questions
- 1. With regard to the Condensate Storage System (CSS) -
- a. What is the minimum leakage rate that is certain to be detectable by the testing of the condensate storage tank (CST) water level every four hours, and, conversely, what is the maximum leakage rate that would not be detected by that testing? Provide a detailed statement of the basis of and sources for your answer.
- b. What is the minimum leakage rate that is certain to be detected by the quarterly testing of the water flow from the reactor core isolation cooling (RCIC) pump and the high pressure cooling injection (HPCI) pump, and, conversely, what is the maximum leakage rate that would not be detected by that testing? Provide a detailed statement of the basis of and sources for your answer.
- c. What is the smallest leakage rate that could reasonably be expected to challenge the ability of the CSS system piping at issue to fail to satisfy its intended function(s) as relevant for license renewal? Provide a detailed statement of the basis of and sources for your answer.
- 2. With Regard to the Salt Service Water (SSW) system -
Explain how any leak in the SSW buried pipes that might carry radioactive water from the plant to the canal that dumps into the bay could challenge the ability of the SSW system to satisfy its intended function(s)? For example, is there any correlation between any potential leak in those pipes and any potential plugs in them that might prevent them from discharging water from the SSW, thereby impeding the ability to remove heat from the RBCCW? Provide a detailed statement of the basis of and sources for your answer.
The Parties shall provide thorough technical support for their answers, including appropriate affidavits.
It is so ORDERED.
THE ATOMIC SAFETY AND LICENSING BOARD4
/RA/
Ann Marshall Young, Chair ADMINISTRATIVE JUDGE
/RA/
Dr. Paul B. Abramson ADMINISTRATIVE JUDGE
/RA/
Dr. Richard F. Cole ADMINISTRATIVE JUDGE Rockville, Maryland January 31, 2008 4
Copies of this Order were sent this date by Internet electronic mail transmission to counsel for (1) the Licensee, (2) the NRC Staff, and (3) Intervenor.
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )
)
ENTERGY NUCLEAR GENERATION CO. )
AND )
ENTERGY NUCLEAR OPERATIONS, INC. ) Docket No. 50-293-LR
)
)
(Pilgrim Nuclear Power Station) )
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing LB ORDER (BOARD QUESTIONS FOR THE NRC STAFF AND APPLICANT) have been served upon the following persons by U.S. mail, first class, or through NRC internal distribution.
Office of Commission Appellate Administrative Judge Adjudication Ann Marshall Young, Chair U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Board Panel Washington, DC 20555-0001 Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Administrative Judge Administrative Judge Richard F. Cole Paul B. Abramson Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop - T-3 F23 Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 Susan L. Uttal, Esq. David R. Lewis, Esq.
David Roth, Esq. Paul A. Gaukler, Esq.
Kimberly Sexton, Esq. Pillsbury, Winthrop, Shaw, Pittman, LLP James E. Adler, Esq. 2300 N. Street, N.W.
Office of the General Counsel Washington, DC 20037-1128 Mail Stop - O-15 D21 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
2 Docket No. 50-293-LR LB ORDER (BOARD QUESTIONS FOR THE NRC STAFF AND APPLICANT)
Perry H. Buckberg, Project Manager Mary Lampert, Director Plant Licensing Branch I-I Pilgrim Watch Division of Operating Reactor Licensing 148 Washington Street Office of Nuclear Reactor Regulation Duxbury, MA 02332 U.S. Nuclear Regulatory Commission Mail Stop O11-F1 Washington, DC 20555-0001 Sheila Slocum Hollis, Esq. Mark D. Sylvia, Town Manager Town of Plymouth MA Town Managers Office Duane Morris, LLP 11 Lincoln Street 1667 K. Street, N.W. Plymouth, MA 02360 Suite 700 Washington, DC 20006 Terrence A. Burke, Esq Chief Kevin M. Nord Entergy Nuclear Fire Chief & Director Duxbury Emergency 1340 Echelon Parkway Management Agency Mail Stop: M-ECH-62 668 Tremont Street Jackson, MS 39213 Duxbury, MA 02332
[Original signed by Evangeline S. Ngbea]
Office of the Secretary of the Commission Dated at Rockville, Maryland this 31st day of January 2008