ML16081A135: Difference between revisions
From kanterella
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 13: | Line 13: | ||
| document type = Letter, Response to Request for Additional Information (RAI) | | document type = Letter, Response to Request for Additional Information (RAI) | ||
| page count = 6 | | page count = 6 | ||
| revision = 0 | |||
}} | }} |
Revision as of 21:27, 25 February 2018
Letter Sequence Supplement | |
---|---|
TAC:MF7224, Add Action for Two Inoperable Control Room AC Subsystems, Add Action for Two Inoperable Creatcs Trains (Open) | |
Initiation Administration Questions
Results
Other: | |
MONTHYEARMNS-16-002, Proposed Technical Specifications (TS) Amendment TS 3.7.10, Control Room Area Chilled Water System (Mns), and TS 3.7.11, Control Room Area Chilled Water System (CNS)2016-01-0707 January 2016
[Table View]Proposed Technical Specifications (TS) Amendment TS 3.7.10, Control Room Area Chilled Water System (Mns), and TS 3.7.11, Control Room Area Chilled Water System (CNS) Project stage: Request ML16055A3332016-03-0101 March 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action LAR for Control Room Chilled Water System TS Project stage: Acceptance Review MNS-16-023, Response to Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding License Amendment Request for Control Room Chilled Water System Technical Specifications2016-03-16016 March 2016 Response to Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding License Amendment Request for Control Room Chilled Water System Technical Specifications Project stage: Supplement ML16085A0992016-03-31031 March 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request for Control Room Chilled Water System Technical Specifications Project stage: Acceptance Review 2016-03-01 |
ML16081A135 | |
Person / Time | |
---|---|
Site: | Mcguire, Catawba, McGuire ![]() |
Issue date: | 03/16/2016 |
Revision: | 0 |
From: | Capps S D Duke Energy Carolinas |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
MNS-16-023 | |
Download: ML16081A135 (6) | |
Category:Letter
MONTHYEARIR 05000413/20230042024-02-0202 February 2024
[Table view]Integrated Inspection Report 05000413-2023004 and 05000414-2023004 IR 05000369/20230042024-01-31031 January 2024 Integrated Inspection Report 05000369/2023004 and 05000370/2023004 ML24005A2512024-01-26026 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24019A1392024-01-25025 January 2024 TSTF 505 and 50.69 Audit Summary ML24019A2002024-01-24024 January 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000369/20234022023-12-14014 December 2023 Material Control and Accounting Program Inspection Report 05000369/2023402 and 05000370/2023402 ML23317A2272023-11-17017 November 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Transmittal of Dam Inspection Report - Non-Proprietary ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230032023-10-24024 October 2023 Integrated Inspection Report 05000369/2023003 and 05000370/2023003; and Inspection Report 07200038/2023001 IR 05000369/20230102023-10-13013 October 2023 Age Related Degradation Inspection Report 05000369/2023010 and 05000370/2023010 IR 05000369/20240102023-10-13013 October 2023 Notification of McGuire Nuclear Station Comprehensive Engineering Team Inspection U.S. Nuclear Regulatory Commission Inspection Report 05000369, 370/2024010 IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds IR 05000369/20233012023-09-20020 September 2023 William B. McGuire Nuclear Station - NRC Examination Report 05000369/2023301 and 05000370/2023301 ML23230A0652023-08-31031 August 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Relief Request Use of Later Edition of ASME Code ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230052023-08-25025 August 2023 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 (Report 05000369/2023005 and 05000370/2023005) IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) ML23233A1692023-08-17017 August 2023 EN 56683 - Curtiss Wright, Interim Notification Report for PotentialPurt2l IR 05000369/20230022023-07-28028 July 2023 Integrated Inspection Report 05000369/2023002 and 05000370/2023002 IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 IR 05000369/20234202023-07-24024 July 2023 Security Baseline Inspection Report 050003692023420 and 050003702023420 ML23206A0092023-07-24024 July 2023 William B. McGuire Nuclear Station Operator Licensing Written Examination Approval 05000369/2023301 and 05000370/2023301 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23159A2712023-06-20020 June 2023 William B. McGuire Nuclear Station, Unit 1 - Relief Request Impractical Reactor System Welds ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 ML23115A2122023-05-0101 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000369/20230012023-05-0101 May 2023 Integrated Inspection Report 05000369/2023001 and 05000370/2023001 IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 ML23094A1832023-04-18018 April 2023 Audit Plan TSTF-505, Rev. 2, RITSTF Initiative 4B & 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors (EPIDs L-2023-LLA-0021 & L-2023-LLA-0022) ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000369/20220062023-03-0101 March 2023 Annual Assessment Letter for McGuire Nuclear Station Units 1 and 2 (NRC Inspection Report 05000369/2022006 and 05000370 2022006) IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000369/20220042023-01-30030 January 2023 Mcguire Nuclear Station - Integrated Inspection Report 05000369/2022004 and 05000370/2022004 IR 05000369/20224202023-01-11011 January 2023 Security Baseline Inspection Report 05000369/2022420 and 05000370/2022420 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22347A1512022-12-13013 December 2022 William B. Mcguire Nuclear Station Notification of Licensed Operator Initial Examination 05000369/2023301 and 05000370/2023301 ML22340A6662022-12-0808 December 2022 Summary of November 30, 2022, Public Meeting with Duke Energy Carolinas, LLC for McGuire Nuclear Station, Units 1 & 2 Proposed LAR to Adopt TSTF-505, Rev. 2 and 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems ML22290A1012022-11-29029 November 2022 Issuance of Amendment Nos. 326 and 305, Regarding Changes to Technical Specification 3.4.3, Reactor Coolant System Pressure Temperature Limits ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 2024-02-02 Category:Response to Request for Additional Information (RAI) MONTHYEARRA-23-0136, Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023
[Table view]Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0154, Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0142, Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require2023-07-0707 July 2023 Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require RA-23-0076, Supplement to Response to Request for Additional Information (RAI) Regarding McGuire Nuclear Station Unit 1 Spring, 2022 Outage Steam Generator Tube Inspection Report2023-03-16016 March 2023 Supplement to Response to Request for Additional Information (RAI) Regarding McGuire Nuclear Station Unit 1 Spring, 2022 Outage Steam Generator Tube Inspection Report RA-23-0024, Response to Request for Additional Information (RAI) for Relief Request for RPV Reactor Coolant System Welds2023-02-28028 February 2023 Response to Request for Additional Information (RAI) for Relief Request for RPV Reactor Coolant System Welds RA-23-0025, End of Cycle 28 (M1R28) Steam Generator Tube Inspection Report Response to Request for Additional Information (RAI)2023-02-15015 February 2023 End of Cycle 28 (M1R28) Steam Generator Tube Inspection Report Response to Request for Additional Information (RAI) RA-22-0195, Response to Request for Additional Information (RAI) for the Proposed Method to Manage Aging Due to Environmentally Assisted Fatigue for the Safety Injection Nozzle2022-06-29029 June 2022 Response to Request for Additional Information (RAI) for the Proposed Method to Manage Aging Due to Environmentally Assisted Fatigue for the Safety Injection Nozzle RA-22-0147, Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, Response to Request for Additional Information (RAI) Regarding License Amendment Request for Relocating the Duke Energy Emergency Operations Facility2022-05-13013 May 2022 Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, Response to Request for Additional Information (RAI) Regarding License Amendment Request for Relocating the Duke Energy Emergency Operations Facility RA-22-0102, Response to Request for Additional Information (RAI) Regarding Revision 1 of DPC-NE-1007-P, Conditional Exemption of the EOC Mtc Measurement Methodology2022-04-0707 April 2022 Response to Request for Additional Information (RAI) Regarding Revision 1 of DPC-NE-1007-P, Conditional Exemption of the EOC Mtc Measurement Methodology RA-22-0003, Response to Requests for Additional Information for Reactor Vessel Closure Stud Exam Extension Alternative2022-01-31031 January 2022 Response to Requests for Additional Information for Reactor Vessel Closure Stud Exam Extension Alternative RA-21-0321, Response to Request for Additional Information (RAI) Regarding Refuel 24 (C2R24) Inservice Inspection (ISI) and Steam Generator Inspection (SG-ISI) Report2021-12-14014 December 2021 Response to Request for Additional Information (RAI) Regarding Refuel 24 (C2R24) Inservice Inspection (ISI) and Steam Generator Inspection (SG-ISI) Report RA-21-0259, Response to Request for Additional Information for Request to Use Provisions of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI for Repair/ Replacement Activities in Accordance with 10 CFR 50.55a(g)(42021-10-0404 October 2021 Response to Request for Additional Information for Request to Use Provisions of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI for Repair/ Replacement Activities in Accordance with 10 CFR 50.55a(g)(4 RA-21-0063, 1, 2; Catawba Nuclear Station 1, 2; H. B. Robinson Steam Electric Plant 2; Mcgguire Nuclear Station 1, 2; Oconee Nuclear Station 1, 2, 3; Shearon Harris Nuclear Power Plant 1 - Response to RAI Re Amend for Emergency Plan2021-03-11011 March 2021 1, 2; Catawba Nuclear Station 1, 2; H. B. Robinson Steam Electric Plant 2; Mcgguire Nuclear Station 1, 2; Oconee Nuclear Station 1, 2, 3; Shearon Harris Nuclear Power Plant 1 - Response to RAI Re Amend for Emergency Plan RA-21-0032, Duke Energy - Response to Requests for Additional Info for Request to Use a Provision of Later Edition & Addenda of the ASME Boiler & Pressure Vessel Code, Section XI for Repair/Replacement Activities in Accordance with 10 CFR 50.55a(g)(42021-02-11011 February 2021 Duke Energy - Response to Requests for Additional Info for Request to Use a Provision of Later Edition & Addenda of the ASME Boiler & Pressure Vessel Code, Section XI for Repair/Replacement Activities in Accordance with 10 CFR 50.55a(g)(4)( RA-21-0017, Response to Request for Additional Information Re License Amendment Request to Revise Tech Spec 3.8.1 to Reduce Emergency Diesel Generator Maximum Steady State Voltage2021-01-29029 January 2021 Response to Request for Additional Information Re License Amendment Request to Revise Tech Spec 3.8.1 to Reduce Emergency Diesel Generator Maximum Steady State Voltage RA-20-0104, Response to NRC Request for Additional Information - Catawba Nuclear Station-SG Report (RA-19-0391)-C2R232020-04-0606 April 2020 Response to NRC Request for Additional Information - Catawba Nuclear Station-SG Report (RA-19-0391)-C2R23 RA-20-0087, Response to Request for Additional Information Regarding Request for Alternative in Accordance with 10CFR 50.55a(z)(1) to Delay the Update of the ASME Code of Record for the First Inspection Period2020-04-0202 April 2020 Response to Request for Additional Information Regarding Request for Alternative in Accordance with 10CFR 50.55a(z)(1) to Delay the Update of the ASME Code of Record for the First Inspection Period RA-20-0002, Response to Request for Additional Information (RAI) Regarding License Amendment Request to Revise Technical Specification 3.4.3, RCS Pressure and Temperature (P/T) Limits2020-02-13013 February 2020 Response to Request for Additional Information (RAI) Regarding License Amendment Request to Revise Technical Specification 3.4.3, RCS Pressure and Temperature (P/T) Limits RA-19-0280, Response to NRC RAI Clarifications Regarding License Amendment Request Proposing Changes to the Technical Specifications 3.8.12019-07-10010 July 2019 Response to NRC RAI Clarifications Regarding License Amendment Request Proposing Changes to the Technical Specifications 3.8.1 RA-19-0189, Supplement to Response for Request for Additional Information Regarding License Amendment Request Proposing Changes to the Technical Specifications 3.8.12019-04-0808 April 2019 Supplement to Response for Request for Additional Information Regarding License Amendment Request Proposing Changes to the Technical Specifications 3.8.1 RA-19-0004, Response to NRC for Additional Information (RAI) Regarding License Amendment Request Proposing Changes to the Technical Specifications 3.8.1 for Catawba Nuclear Station, Units 1 and 22019-03-0707 March 2019 Response to NRC for Additional Information (RAI) Regarding License Amendment Request Proposing Changes to the Technical Specifications 3.8.1 for Catawba Nuclear Station, Units 1 and 2 RA-19-0026, Response to Request for Additional Information (RAI) Regarding Proposed Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 and 10 (18-GO-001)2019-02-11011 February 2019 Response to Request for Additional Information (RAI) Regarding Proposed Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 and 10 (18-GO-001) RA-19-0005, Response to NRC Request for Additional Information Regarding Review Request of the Aging Management Program and Inspection Plan for the Reactor Vessel Internals to Implement MRP-227-A2019-01-30030 January 2019 Response to NRC Request for Additional Information Regarding Review Request of the Aging Management Program and Inspection Plan for the Reactor Vessel Internals to Implement MRP-227-A RA-18-0162, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal2018-12-0606 December 2018 Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal RA-18-0229, Response to NRC Request for Additional Information Regarding License Amendment Request Proposing Changes to the Technical Specification 3.8.12018-12-0303 December 2018 Response to NRC Request for Additional Information Regarding License Amendment Request Proposing Changes to the Technical Specification 3.8.1 RA-18-0213, Response to the Second Request for Additional Information Regarding the License Amendment Request to Revise the Licensing Bases for Protection from Tornado-Generated Missiles2018-11-0101 November 2018 Response to the Second Request for Additional Information Regarding the License Amendment Request to Revise the Licensing Bases for Protection from Tornado-Generated Missiles RA-18-0097, (Cns), Units 1 and 2 - Response to NRC Requests for Additional Information (Rais) License Amendment Request to Revise Technical Specification Section 3.7.8, Nuclear Service Water System2018-08-17017 August 2018 (Cns), Units 1 and 2 - Response to NRC Requests for Additional Information (Rais) License Amendment Request to Revise Technical Specification Section 3.7.8, Nuclear Service Water System ML18191A5642018-07-10010 July 2018 Attachment 3 - Response to NRC Request for Additional Information MNS-18-036, Redacted Response to the Request for Additional Information Regarding the License Amendment Request to Revise the Licensing Bases for Protection from Tornado Generated Missiles2018-07-0303 July 2018 Redacted Response to the Request for Additional Information Regarding the License Amendment Request to Revise the Licensing Bases for Protection from Tornado Generated Missiles ML20052D9362018-07-0303 July 2018 Response to Nrg Request for Additional Information (RAI) Regarding NAC Magnastor Cask Loaded to Incorrect Helium Backfill Density CNS-18-023, (Cns), Units 1 and 2 - Response to NRC Requests for Additional Information (Rais) License Amendment Request to Revise Technical Specification Section 3.7.8, Nuclear Service Water System2018-05-0808 May 2018 (Cns), Units 1 and 2 - Response to NRC Requests for Additional Information (Rais) License Amendment Request to Revise Technical Specification Section 3.7.8, Nuclear Service Water System NRC-18-0016, Response to Request for Additional Information (Set 2) Regarding License Amendment Request to Revise Technical Specifications to Eliminate Main Steam Line Radiation Monitor Reactor Trip and Primary Containment Isolation System Group 1..2018-02-21021 February 2018 Response to Request for Additional Information (Set 2) Regarding License Amendment Request to Revise Technical Specifications to Eliminate Main Steam Line Radiation Monitor Reactor Trip and Primary Containment Isolation System Group 1.. CNS-17-058, Supplement to the High Frequency Supplement to Seismic Hazard Screening Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukus2017-12-28028 December 2017 Supplement to the High Frequency Supplement to Seismic Hazard Screening Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushi CNS-17-061, Third Ten-Year Inservice Inspection Plan, Limited Volumetric Examinations Response to NRC Requests for Additional Information2017-12-21021 December 2017 Third Ten-Year Inservice Inspection Plan, Limited Volumetric Examinations Response to NRC Requests for Additional Information ML17349A1572017-12-12012 December 2017 Response to Request for Additional Information Regarding License Amendment Request for Temporary Changes to Technical Specifications to Address the 'A' Train Nuclear Service Water System Non-Conforming Condition MNS-17-048, Response to Request for Additional Information License Amendment Request Permanent Extension of Type a and Type C Leak Rate Test Frequencies2017-12-12012 December 2017 Response to Request for Additional Information License Amendment Request Permanent Extension of Type a and Type C Leak Rate Test Frequencies CNS-17-047, Response to NRC Inspection Report 05000414/2017012 and Preliminary White Finding2017-08-29029 August 2017 Response to NRC Inspection Report 05000414/2017012 and Preliminary White Finding RA-17-0039, Response to Request for Additional Information (RAI) Regarding 10 CFR 50.55a(z)(1)Proposed Alternative to ASME Section XI Threads in Flange Examination (17-GO-001)2017-08-0909 August 2017 Response to Request for Additional Information (RAI) Regarding 10 CFR 50.55a(z)(1)Proposed Alternative to ASME Section XI Threads in Flange Examination (17-GO-001) RA-17-0035, Supplement to License Amendment Request Proposing Changes to Technical Specification 3.5.1, AC Sources - Operating.2017-07-20020 July 2017 Supplement to License Amendment Request Proposing Changes to Technical Specification 3.5.1, AC Sources - Operating. RA-17-0036, Supplement to the Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Multiple Technical Specification Task Force Travelers2017-07-17017 July 2017 Supplement to the Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Multiple Technical Specification Task Force Travelers MNS-17-030, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal2017-06-28028 June 2017 Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal RA-17-0029, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Multiple Technical Specification Task Force Travelers2017-06-0808 June 2017 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Multiple Technical Specification Task Force Travelers RA-17-0030, Response to Request for Additional Information Regarding Application to Reverse Technical Specifications to Adopt Multiple Technical Specification Task Force Travelers2017-06-0808 June 2017 Response to Request for Additional Information Regarding Application to Reverse Technical Specifications to Adopt Multiple Technical Specification Task Force Travelers MNS-17-023, Response to Request for Additional Information to License Amendment Request Permanent Extension of Type a and Type C Leak Rate Test Frequencies2017-05-25025 May 2017 Response to Request for Additional Information to License Amendment Request Permanent Extension of Type a and Type C Leak Rate Test Frequencies CNS-17-031, Response to NRC Requests for Additional Information End of Cycle 21 Refueling Outage Inservice Inspection Report and Steam Generator Inservice Inspection Summary Report2017-05-24024 May 2017 Response to NRC Requests for Additional Information End of Cycle 21 Refueling Outage Inservice Inspection Report and Steam Generator Inservice Inspection Summary Report CNS-17-004, Response to NRC Request for Additional Information on License Amendment Request to Adopt National Fire Protection Association (NFPA) 805 Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants.2017-01-26026 January 2017 Response to NRC Request for Additional Information on License Amendment Request to Adopt National Fire Protection Association (NFPA) 805 Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants. CNS-16-077, Expedited Seismic Evaluation Process Closeout, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2016-12-0808 December 2016 Expedited Seismic Evaluation Process Closeout, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident CNS-16-066, Stations - Supplemental Information Regarding Reevaluated Seismic Hazard Screening and Prioritization Results - Response to NRC Request for Information, Per 10CFR50.54(f) Regarding Recommendation 2.1 of the Near-Term Task..2016-10-20020 October 2016 Stations - Supplemental Information Regarding Reevaluated Seismic Hazard Screening and Prioritization Results - Response to NRC Request for Information, Per 10CFR50.54(f) Regarding Recommendation 2.1 of the Near-Term Task.. ML16294A2542016-10-13013 October 2016 Response to Request for Additional Information Regarding Relief Request 16-MN-002, Alternative to Defect Removal Prior to Performing Repair Activities on Nuclear Service Water System Piping RA-16-0035, Response to Request for Additional Information (RAI) Regarding Application for Emergency Operations Facility (EOF) Consolidation2016-10-0303 October 2016 Response to Request for Additional Information (RAI) Regarding Application for Emergency Operations Facility (EOF) Consolidation 2023-07-07 |
Retrieved from "https://kanterella.com/w/index.php?title=ML16081A135&oldid=347251"