ML21307A033: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:DTE                                                                              October 11, 2021 10 CFR 50.59 10 CFR 52 Appendix E 10 CFR 52.3 NRC3-21-0002 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001
{{#Wiki_filter:}}
 
==Reference:==
Fermi 3 NRC Docket No. 52-033 NRG License No. NPF-95
 
==Subject:==
DTE Electric Company Submittal of Fermi 3 Periodic Reports This submittal provides periodic Fermi 3 reports as required by NRC regulations and license conditions for a Part 52 combined license holder. This submittal provides the following report updates:
* Semi-Annual Departures Report
* Semi-Annual Changes, Tests and Experiments Report
* Semi-Annual Schedule for Implementation of Operational Programs and other License Conditions Report
* Annual Final Safety Analysis Report (FSAR) Update Semi-Annual Departures Report: During the period from April 12, 2021 to October 11, 2021, there were no plant-specific departures from the ESBWR DCD for Fermi 3.
Semi-Annual Changes, Tests, and Experiments Report: During the period from April 12, 2021 to October 11, 2021, there were no changes, tests or experiments made pursuant to 10 CFR 50.59(c).
* Semi-Annual Schedule Update for Implementation of Operational Programs and Other License Conditions: During the period from April 12, 2021 to October 11, 2021, there were no schedule updates. The scheduled implementation dates for the operational programs remain as "To Be Determined" (TBD).
Annual FSAR Update: No FSAR information has been revised, deleted, or added since the last submittal. Therefore, the previously submitted FSAR continues to be current.
 
USNRC NRC3-21-0002 Page2 If you have any questions, or need additional information, please contact me at (313) 235-0443.
Sincerely,
.("l, '---- \ l~~              ~
Michael K. Brandon, Manager Nuclear Development - Licensing DTE Electric Company CC:    Michael Dudek, NRG Fermi 3 Project Branch Chief Demetrius Murray, NRG Fermi 3 Project Manager Fermi 2 Resident Inspector Andrea D. Veil, Director, NRG Office of Nuclear Reactor Regulation NRG Region Ill Regional Administrator NRG Region II Regional Administrator Supervisor, Electric Operators, Michigan Public Service Commission Michigan Department of Environmental Quality OWMRP, Radiological Protection Section Craig D. Sly, Dominion Energy, Inc.
Kent Halac, General Electric Art Zaremba, Duke Energy Steve Franzone, Florida Power and Light}}

Revision as of 16:53, 16 January 2022

DTE Electric Company Submittal of Fermi 3 Periodic Reports
ML21307A033
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/11/2021
From: Brandon M
DTE Electric Company
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC3-21-0002
Download: ML21307A033 (2)


Text