{{#Wiki_filter:June 30, 2021 Mr. Mike Annacone Vice President, Columbia Fuel Operations and Manager, Columbia Plant Westinghouse Electric Company 5801 Bluff Road Hopkins, SC 29061
{{#Wiki_filter:}}
 
==SUBJECT:==
WESTINGHOUSE ELECTRIC COMPANY - CALENDAR YEAR 2022 INSPECTION SCHEDULE
 
==Dear Mr. Annacone:==
 
Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at Westinghouse Electric Company for calendar year 2022. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.
Please note that any regional initiative or other reactive inspection is not included in the schedule. If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Thomas Vukovinsky at (404) 997-4622 with any questions or concerns you may have regarding this letter or the inspection schedule.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
                                              /RA/
Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection Docket No. 70-1151 License No. SNM-110
 
==Enclosure:==
 
2022 Westinghouse Electric Company Inspection Schedule cc: w/ encl: Distribution via LISTSERV
 
ML21182A310 X    Non-Sensitive        X Publicly Available x    SUNSI Review Sensitive              Non-Publicly Available OFFICE RII/DFFI          RII/DFFI NAME    E. Michel        N. Peterka DATE    6/29/2021        6/23/2021 WESTINGHOUSE ELECTRIC COMPANY 2022 INSPECTION/ACTIVITY PLAN CALENDAR WESTINGHOUSE NCS1/EP Dates                      02/28/22 - 03/04/22 Number of Inspectors        2 88015 - Nuclear Criticality Safety Inspection Procedures (IPs) 88050 - Emergency Preparedness WESTINGHOUSE OPS1 Dates                      03/07/22 - 03/11/22 Number of Inspectors        2 Inspection Procedures (IPs) 88020 - Operational Safety WESTINGHOUSE NCS2/PMA Dates                      07/18/22 - 07/22/22 Number of Inspectors        2 88015 - Nuclear Criticality Safety Inspection Procedures (IPs) 88070 - Plant Modifications (Annual)
WESTINGHOUSE RP/ENV Dates                      09/12/22 - 09/16/22 Number of Inspectors        3 88030 - Radiation Protection Inspection Procedure (IP) 88045 - Effluent Control and Environmental Protection WESTINGHOUSE OPS2 Dates                      11/14/22 - 11/18/22 Number of Inspectors        2 Inspection Procedure (IP)  88020 - Operational Safety Enclosure}}

Revision as of 04:53, 8 September 2021

Westinghouse Electric Company - Calendar Year 2022 Inspection Schedule
ML21182A310
Person / Time
Site: Westinghouse
Issue date: 06/30/2021
From: Eric Michel
NRC/RGN-II/DFFI
To: Annacone M
Westinghouse
References