ML15126A237: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 51: Line 51:
ES-301                            Control Room/In-Plant Systems Outline                            Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________                        Date of Examination: AUGUST 2014_
ES-301                            Control Room/In-Plant Systems Outline                            Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________                        Date of Examination: AUGUST 2014_
Exam Level: RO                                                          Operating Test No.: PI-ILT-NRC-14 _
Exam Level: RO                                                          Operating Test No.: PI-ILT-NRC-14 _
                              @
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
System / JPM Title                                  Type Code*          Safety Function
System / JPM Title                                  Type Code*          Safety Function
Line 61: Line 60:
: f. EDG / SYNCHRONIZE D1 ON BUS 15                                                  D, EN, S                6
: f. EDG / SYNCHRONIZE D1 ON BUS 15                                                  D, EN, S                6
: g. NIS / PR DAILY CALIBRATION - SP 1005                                            N, S                    7
: g. NIS / PR DAILY CALIBRATION - SP 1005                                            N, S                    7
: h. IAS / INSTRUMENT AIR SYSTEM HIGH PRESSURE                                      A, N, S                  8
: h. IAS / INSTRUMENT AIR SYSTEM HIGH PRESSURE                                      A, N, S                  8 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
                      @
In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
: i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE                                    A, D, E, L, P            1
: i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE                                    A, D, E, L, P            1
: j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS                                  D, E, L, R              2
: j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS                                  D, E, L, R              2
Line 74: Line 71:
ES-301                            Control Room/In-Plant Systems Outline                            Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________                        Date of Examination: AUGUST 2014_
ES-301                            Control Room/In-Plant Systems Outline                            Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________                        Date of Examination: AUGUST 2014_
Exam Level: SRO-I                                                        Operating Test No.: PI-ILT-NRC-14 _
Exam Level: SRO-I                                                        Operating Test No.: PI-ILT-NRC-14 _
                              @
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
System / JPM Title                                  Type Code*          Safety Function
System / JPM Title                                  Type Code*          Safety Function
Line 84: Line 80:
: f. EDG / SYNCHRONIZE D1 ON BUS 15                                                  D, EN, S                6
: f. EDG / SYNCHRONIZE D1 ON BUS 15                                                  D, EN, S                6
: g. NONE
: g. NONE
: h. IAS / SWAP IA COMPRESSORS WITH HIGH AIR PRESS                                  A, N, S                  8
: h. IAS / SWAP IA COMPRESSORS WITH HIGH AIR PRESS                                  A, N, S                  8 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
                      @
In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
: i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE                                    A, D, E, L, P            1
: i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE                                    A, D, E, L, P            1
: j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS                                  D, E, L, R              2
: j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS                                  D, E, L, R              2
Line 97: Line 91:
ES-301                            Control Room/In-Plant Systems Outline                            Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________                        Date of Examination: AUGUST 2014_
ES-301                            Control Room/In-Plant Systems Outline                            Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________                        Date of Examination: AUGUST 2014_
Exam Level: SRO-U                                                        Operating Test No.: PI-ILT-NRC-14 __
Exam Level: SRO-U                                                        Operating Test No.: PI-ILT-NRC-14 __
                              @
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
System / JPM Title                                  Type Code*          Safety Function
System / JPM Title                                  Type Code*          Safety Function
Line 107: Line 100:
: f. NONE
: f. NONE
: g. NONE
: g. NONE
: h. IAS / SWAP IA COMPRESSORS WITH HIGH AIR PRESS                                  A, N, S                  8
: h. IAS / SWAP IA COMPRESSORS WITH HIGH AIR PRESS                                  A, N, S                  8 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
                      @
In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
: i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE                                    A, D, E, L, P            1
: i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE                                    A, D, E, L, P            1
: j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS                                  D, E, L, R              2
: j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS                                  D, E, L, R              2

Latest revision as of 12:04, 5 February 2020

2014 Prairie Island Nuclear Generating Plant Initial License Examination Revised Forms Es 301-1 and Es 301-2
ML15126A237
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 05/19/2014
From: Bielby M
NRC/RGN-III/DRS/OLB
To:
Northern States Power Co
Shared Package
ML13093A444 List:
References
Download: ML15126A237 (5)


Text

ES-301 Administrative Topics Outline Form ES-301-1 Facility: __PRAIRIE ISLAND_______________________ Date of Examination: AUGUST 2014 _

Examination Level: RO Operating Test Number: PI-ILT-NRC-14_

Administrative Topic Type Describe activity to be performed (see Note) Code*

DETERMINE BLENDED FLOW CONCENTRATION 2.1.25 (3.9/4.2)

Conduct of Operations D, R This is a bank JPM where the examinee determines the boric acid flow setting for the Boric Acid Flow Control Valve.

VERIFY CORRECT PROCEDURE 2.1.21 (3.5*/3.6*)

Conduct of Operations M, R Original JPM has operator verify correct revision of SP 1313. The modified JPM will have the operator verify the correct revision of a procedure other than SP 1313.

REVIEW CLEARANCE ORDER 2.2.13 (4.1/4.3)

This JPM will be different than previous versions of Equipment Control N, R reviewing a clearance order by isolating a different system and inputting different mistakes for the operator to discover.

REMOVE RADIATION MONITOR FROM SERVICE 2.3.5 (2.9/2.9)

Radiation Control D, R This is a bank JPM where the examinee removes 1R-11, Containment Air Particulate Radiation Monitor, from service.

Emergency Procedures/Plan NONE NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.

  • Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)

(N)ew or (M)odified from bank ( 1)

(P)revious 2 exams ( 1; randomly selected)

ES-301 Administrative Topics Outline Form ES-301-1 Facility: __PRAIRIE ISLAND_______________________ Date of Examination: AUGUST 2014 _

Examination Level: SRO Operating Test Number: PI-ILT-NRC-14 Administrative Topic Type Describe activity to be performed (see Note) Code*

ASSESS SHIFT STAFFING LEVELS 2.1.5 (2.9*/3.9)

Conduct of Operations D, R This is a bank JPM where the examinee must determine if the U1 SS can be released due to an emergency.

PERFORM PRA CALCULATION USING EOOS SOFTWARE 2.1.19 (3.9/3.8)

Conduct of Operations D, R This is a bank JPM where the examinee must use the plant computer to determine PRA status of Unit 1 and Unit 2.

AUTHORIZE INSTALLATION OF A BYPASS 2.2.11 (2.3/3.3)

Equipment Control D, R This is a bank JPM where the examinee approves the use of a bypass using a plant administrative work instruction.

AUTHORIZE EMERGENCY RADIATION EXPOSURE 2.3.4 (3.2/3.7)

Radiation Control D, R This is a bank JPM where the examinee determines if an individual can receive an emergency exposure or not.

VALIDATE IMMINENT AIRBORNE THREAT 2.4.28 (3.2/4.1)

Emergency Procedures/Plan N, R This is a new JPM to perform SRO actions of AB-8, Response to Security Threat.

NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.

  • Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)

(N)ew or (M)odified from bank ( 1)

(P)revious 2 exams ( 1; randomly selected)

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________ Date of Examination: AUGUST 2014_

Exam Level: RO Operating Test No.: PI-ILT-NRC-14 _

Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code* Safety Function

a. CRDS / UNCONTROLLED ROD INSERTION A, M, S 1
b. ESFAS / CONTAINMENT ISOLATION FAILURE L, D, S, EN 2
c. ECCS / RAISE 11 SI ACCUMULATOR LEVEL D, EN, S 3
d. SWS / LOSS OF COOLING WATER HEADER PRESSURE A, N, S 4S
e. RCS / PRT HI TEMP AND HI LEVEL A, M, S 5
f. EDG / SYNCHRONIZE D1 ON BUS 15 D, EN, S 6
g. NIS / PR DAILY CALIBRATION - SP 1005 N, S 7
h. IAS / INSTRUMENT AIR SYSTEM HIGH PRESSURE A, N, S 8 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE A, D, E, L, P 1
j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS D, E, L, R 2
k. FP / INITIATE CARDOX D, E 8

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/ 8/ 4 (E)mergency or abnormal in-plant 1/ 1/ 1 (EN)gineered safety feature - / - / 1 (control room system)

(L)ow-Power / Shutdown 1/ 1/ 1 (N)ew or (M)odified from bank including 1(A) 2/ 2/ 1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)

(R)CA 1/ 1/ 1 (S)imulator

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________ Date of Examination: AUGUST 2014_

Exam Level: SRO-I Operating Test No.: PI-ILT-NRC-14 _

Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code* Safety Function

a. CRDS / UNCONTROLLED ROD INSERTION A, M, S 1
b. ESFAS / CONTAINMENT ISOLATION FAILURE L, D, S, EN 2
c. ECCS / RAISE 11 SI ACCUMULATOR LEVEL D, EN, S 3
d. SWS / LOSS OF COOLING WATER HEADER PRESSURE A, N, S 4S
e. RCS / PRT HI TEMP AND HI LEVEL A, M, S 5
f. EDG / SYNCHRONIZE D1 ON BUS 15 D, EN, S 6
g. NONE
h. IAS / SWAP IA COMPRESSORS WITH HIGH AIR PRESS A, N, S 8 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE A, D, E, L, P 1
j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS D, E, L, R 2
k. FP / INITIATE CARDOX D, E 8

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/ 8/ 4 (E)mergency or abnormal in-plant 1/ 1/ 1 (EN)gineered safety feature - / - / 1 (control room system)

(L)ow-Power / Shutdown 1/ 1/ 1 (N)ew or (M)odified from bank including 1(A) 2/ 2/ 1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)

(R)CA 1/ 1/ 1 (S)imulator

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: __PRAIRIE ISLAND_______________________ Date of Examination: AUGUST 2014_

Exam Level: SRO-U Operating Test No.: PI-ILT-NRC-14 __

Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code* Safety Function

a. NONE
b. NONE
c. ECCS / RAISE 11 SI ACCUMULATOR LEVEL D, EN, S 3
d. SWS / LOSS OF COOLING WATER HEADER PRESSURE A, N, S 4S
e. NONE
f. NONE
g. NONE
h. IAS / SWAP IA COMPRESSORS WITH HIGH AIR PRESS A, N, S 8 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
i. CRDS / LOCALLY TRIP THE REACTOR AND TURBINE A, D, E, L, P 1
j. PZR LCS / RAISE PZR LEVEL USING LOCAL CONTROLS D, E, L, R 2
k. NONE

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/ 8/ 4 (E)mergency or abnormal in-plant 1/ 1/ 1 (EN)gineered safety feature - / - / 1 (control room system)

(L)ow-Power / Shutdown 1/ 1/ 1 (N)ew or (M)odified from bank including 1(A) 2/ 2/ 1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)

(R)CA 1/ 1/ 1 (S)imulator