2014 Prairie Island Nuclear Generating Plant Initial License Examination Form ES-201-1
ML15127A185
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 08/22/2014
From: Bielby M
NRC/RGN-III/DRS/OLB
To:
Northern States Power Co
Shared Package
ML13093A444 List:
References
Download: ML15127A185 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Prairie Island Units 1 and 2 Date of Examination: 08/04/2014 - 08/15/2014 Developed by: Written - Facility NRC

// Operating - Facility NRC Target Date*

Task Description (Reference)

Chief Examiners Initials

-180

1.

Examination administration date confirmed (C.1.a; C.2.a and b) meb/rdb

-120

2.

NRC examiners and facility contact assigned (C.1.d; C.2.e) meb/rdb

-120

3.

Facility contact briefed on security and other requirements (C.2.c) meb/rdb

-120

4.

Corporate notification letter sent (C.2.d) meb/rdb

[-90]

[5.

Reference material due (C.1.e; C.3.c; Attachment 3)]

NA

{-75}

6.

Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d) meb/rdb

{-70}

{7.

Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)}

meb/rdb

{-45}

8.

Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d) meb/rdb

-30

9.

Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202) meb/rdb

-14

10.

Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202) meb/rdb

-14

11.

Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) meb/rdb

-14

12.

Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) meb/rdb

-7

13.

Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) meb/rdb

-7

14.

Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 5; ES-202, C.2.e; ES-204) meb/rdb

-7

15.

Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) meb/rdb

-7

16.

Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) meb/rdb

  • Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.

[Applies only] {Does not apply} to examinations prepared by the NRC.