Line 26: |
Line 26: |
| ==Dear Mr. Butler:== | | ==Dear Mr. Butler:== |
|
| |
|
| As part of the license renewal process for the University of Missouri at Columbia, Research Reactor (MURR), the U.S. Nuclear Regulatory Commission (NRC) staff reviewed your response to our request for additional information dated January 28, 2015, describing the I-131 Processing Laboratory, Attachment No. 25 (although portions of this system are considered proprietary, a public version, where proprietary information has been redacted, is available on the Agencywide Documents Access and Management System (ADAMS) Accession No. ML15034A474). NRC Headquarters inspectors reviewed the I-131 Processing Laboratory during a routine inspection conducted from March 30 through April 2, 2015, and documented their findings in NRC Inspection Report No. 50-186/2015-201 (ADAMS Accession No. | | As part of the license renewal process for the University of Missouri at Columbia, Research Reactor (MURR), the U.S. Nuclear Regulatory Commission (NRC) staff reviewed your response to our request for additional information dated January 28, 2015, describing the I-131 Processing Laboratory, Attachment No. 25 (although portions of this system are considered proprietary, a public version, where proprietary information has been redacted, is available on the Agencywide Documents Access and Management System (ADAMS) Accession No. ML15034A474). NRC Headquarters inspectors reviewed the I-131 Processing Laboratory during a routine inspection conducted from March 30 through April 2, 2015, and documented their findings in NRC Inspection Report No. 50-186/2015-201 (ADAMS Accession No. ML15120A338). An Unresolved Item No. 50-186/2015-201-01 was issued to provide for additional NRC staff review. NRC Research and Test Reactor Licensing branch staff visited the facility on May 12-13, 2015, as part of their review of the renewal of the MURR facility operating license, and also reviewed the I-131 Processing Laboratory. |
| ML15120A338). An Unresolved Item No. 50-186/2015-201-01 was issued to provide for additional NRC staff review. NRC Research and Test Reactor Licensing branch staff visited the facility on May 12-13, 2015, as part of their review of the renewal of the MURR facility operating license, and also reviewed the I-131 Processing Laboratory. | |
| Following these additional reviews, the NRC staff conducted a telephone conversation on May 28, 2015, between MURR staff: Mr. Les Foyto, and Mr. John Fruits, and NRC staff: | | Following these additional reviews, the NRC staff conducted a telephone conversation on May 28, 2015, between MURR staff: Mr. Les Foyto, and Mr. John Fruits, and NRC staff: |
| Dr. Mirela Gavrilas, Mr. Alexander Adams, Jr., Dr. Kevin Hsueh, Mr. John Adams, Mr. Johnny Eades, and Mr. Geoffrey Wertz. During this telephone call, the NRC staff communicated that it appears that additional safety review is necessary in order to determine if any engineered safety features, automated control systems, or additional technical specifications should be required during the operation of the I-131 Processing Laboratory to ensure that any accident scenario could not result in a dose consequence greater than the limits provided in Title 10 of the Code of Federal Regulations (10 CFR), Part 20, Standards for Protection Against Radiation. As a result, MURR staff decided to limit the iodine production in the hot cells to less than allowed by current MURR technical specification 3.7 and 10 CFR Part 20, Appendix B. Confirmation of this understanding was provided by an email from Mr. Les Foyto to Mr. Geoffrey Wertz (ADAMS Accession No. ML15154B803), dated May 28, 2015. | | Dr. Mirela Gavrilas, Mr. Alexander Adams, Jr., Dr. Kevin Hsueh, Mr. John Adams, Mr. Johnny Eades, and Mr. Geoffrey Wertz. During this telephone call, the NRC staff communicated that it appears that additional safety review is necessary in order to determine if any engineered safety features, automated control systems, or additional technical specifications should be required during the operation of the I-131 Processing Laboratory to ensure that any accident scenario could not result in a dose consequence greater than the limits provided in Title 10 of the Code of Federal Regulations (10 CFR), Part 20, Standards for Protection Against Radiation. As a result, MURR staff decided to limit the iodine production in the hot cells to less than allowed by current MURR technical specification 3.7 and 10 CFR Part 20, Appendix B. Confirmation of this understanding was provided by an email from Mr. Les Foyto to Mr. Geoffrey Wertz (ADAMS Accession No. ML15154B803), dated May 28, 2015. |
Letter Sequence Other |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
|
MONTHYEARML0917402832009-07-10010 July 2009 University of Missouri at Columbia - Request for Additional Information License Renewal Project stage: RAI ML13079A2162013-02-28028 February 2013 Letter from Kelly Mescher the Court in Sherman V. the Curators of the University of Missouri Project stage: Other ML13079A2152013-03-0505 March 2013 Statement of Intent Project stage: Other ML13079A2172013-03-12012 March 2013 Letter from Ralph A. Butler Enclosed with University of Missouri-Columbia Research Reactor'S Responses to the U.S. Nuclear Regulatory Commission'S (NRC) Request for Additional Information, Dated February 11, 2013, Regarding Our Renewal Requ Project stage: Request ML13079A2142013-03-12012 March 2013 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding the Response to the University of Missouri at Columbia - Request for Additional Information Updated Financial Information for License Renewal (TAC No. ME1580), Dated 02/11/20 Project stage: Request ML13079A2182013-03-12012 March 2013 University of Missouri System 2012 Financial Report Project stage: Other ML14324A7072014-12-0303 December 2014 Request for Additional Information Regarding the MURR License Renewal Review (Updated Info 11/19/2014) Project stage: RAI ML15034A4732015-01-28028 January 2015 University of Missouri-Columbia Research Reactor Response to NRC Request for Additional Information Re License Renewal Application Project stage: Response to RAI ML15034A4742015-01-28028 January 2015 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding the Response to the University of Missouri at Columbia - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University o Project stage: Request ML15049A0392015-02-12012 February 2015 University of Missouri-Columbia - Response to Request for Additional Information Regarding the Renewal of Facility Operating License No. R- 103 Dated December.3, 2014 Project stage: Response to RAI ML15051A0042015-02-20020 February 2015 University of Missouri at Columbia, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15098A6482015-04-17017 April 2015 University of Missouri at Columbia - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML15154B8122015-07-21021 July 2015 University of Missouri at Columbia Acknowledgement of the Imposition of an Administrative Limit for the Quantity of Iodine Processed in the Iodine Processing Laboratory Hot Cells for Facility Operating License No. R 103 Project stage: Other ML15224B3092015-09-14014 September 2015 University of Missouri at Columbia - Request for Additional Information Regarding, Physical Security Plan Review for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML15260A4392015-09-15015 September 2015 University of Missouri-Columbia - Request for a Copy of the Emergency Plan in Support of the Renewal of Amended Facility License No. R-103 Project stage: Request ML15275A3142015-10-0101 October 2015 University of Missouri, Columbia - Responses to NRC Request for Additional Information, Dated April 17, 2015, Regarding Renewal Request for Amended Facility Operating License Project stage: Response to RAI ML15350A0882015-10-0606 October 2015 State of Missouri, Federal Assistance Clearinghouse Letter NRC Request for Additional Info Regarding the Physical Security Plan Review for Renewal of Facility Operating License No.R-103 for the Univ. of Missouri at Columbia Research Reactor Project stage: Request ML15280A3142015-10-28028 October 2015 University of Missouri at Columbia Research Reactor Request for Additional Information Regarding the Proposed Technical Specifications for the Murr License Renewal Review Project stage: RAI ML15344A0232015-12-0202 December 2015 University of Missouri(Um) at Columbia - Response to Request for Additional Information Regarding Physical Security Plan Review for Renewal of Facility Operating License No. R-103 for the Um at Columbia Research Reactor Project stage: Response to RAI ML15331A0492015-12-0909 December 2015 University of Missouri at Columbia Review of the Emergency Plan in Support of the License Renewal Project stage: Approval ML15337A1752015-12-17017 December 2015 University of Missouri at Columbia Clarifications Needed to NRC Staff Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML16028A2552016-02-0808 February 2016 University of Missouri at Columbia; Request for Additional Information Updated Financial Information for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor (Tac No. Me1580) Project stage: RAI ML16103A5302016-04-0808 April 2016 Univ. of Missouri, Columbia - Transmittal of Responses to NRC Request for Additional Information Dated February 8, 2016 Regarding Renewal Request for Amendment Project stage: Response to RAI ML16110A1642016-04-15015 April 2016 University of Missouri - Columbia Research Reactor, Response to Request for Additional Information on License Renewal Amendment Request Project stage: Response to RAI ML16155A1322016-05-31031 May 2016 University of Missouri-Columbia Research Reactor'S Responses to the NRC Request for Additional Information, Dated October 28, 2015, Regarding Our Renewal Request for Amended Facility Operating License No. R-103 Project stage: Request ML16209A2362016-07-25025 July 2016 University of Missouri, Response to Request for Additional Information Regarding the Proposed Technical Specifications for the License Renewal Project stage: Response to RAI ML16215A4152016-08-0202 August 2016 MURR Hazards Summary Report - Addendums 1-5 Redacted, in Support of an Application for a Research Reactor Project stage: Request ML16216A1222016-08-24024 August 2016 University of Missouri at Columbia - Request for Additional Information Financial Information for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML16239A4252016-09-0707 September 2016 University of Missouri at Columbia - Request for Additional Information Regarding the Proposed Technical Specifications for the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML16313A5172016-11-0707 November 2016 University If Missouri, Response to NRC Request for RAI, Dated September 7, 2016 Regarding License Renewal Amendment Project stage: Request ML16321A4552016-11-15015 November 2016 Written Communication as Specified by 10 CPR 73.4 Regarding Changes to the University of Missouri-Columbia Research Reactor Physical Security Plan That Was Previously Submitted in Response to University of Missouri at Columbia - Request for Project stage: Request ML16321A4852016-11-15015 November 2016 University of Missouri-Columbia Research Reactor - Response to Request for Additional Information Regarding License Renewal Request Project stage: Response to RAI ML15289A0142016-11-18018 November 2016 FRN: General Notice: Environmental Assessment and Finding of No Significant Impact RE: Renewal of Facility Operating License No. R-103, University of Missouri at Columbia Project stage: Request ML15289A0122016-11-18018 November 2016 University of Missouri at Columbia - Environmental Assessment and Finding of No Significant Impact Regarding Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: Other ML16350A4242016-12-14014 December 2016 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding Responses to the University of Missouri at Columbia - Request for Additional Information Regarding the Proposed Technical Specifications for the Renewal of Facility Operating Project stage: Request ML16124A8872017-01-0404 January 2017 the University of Missouri Columbia Safety Evaluation Report for the Renewal of the Facility Operating License for the Nuclear Research Reactor Project stage: Approval 2015-07-21
[Table View] |
|
---|
Category:Letter
MONTHYEAR05000186/LER-2024-003, University of Missouri Research Reactor, Specification Deviation from Technical Specification 3.2.g.212024-10-25025 October 2024 University of Missouri Research Reactor, Specification Deviation from Technical Specification 3.2.g.21 ML24281A1322024-10-0404 October 2024 University of Missouri - Notification of NIST Award 60NANB23D160 NEPA Catex ML24270A0992024-10-0101 October 2024 Examination Confirmation Letter No. 50-186/Ol-25-01, University of Missouri - Columbia ML24142A1432024-08-27027 August 2024 Examination Result Letter No. 50-186/OL-24-02, University of Missouri - Columbia ML24142A1422024-08-27027 August 2024 Examination Report Letter No. 50-186/OL-24-02, University of Missouri - Columbia ML24184A1132024-07-0202 July 2024 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.10.d IR 05000186/20242012024-05-29029 May 2024 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2024201 05000186/LER-2024-001, Written Communication as Required by by LER 2024-001-00 for University of Missouri Research Reactor Technical Specification 6.6.c(3) Re Deviation from Technical Specification 3.1 0.d2024-05-23023 May 2024 Written Communication as Required by by LER 2024-001-00 for University of Missouri Research Reactor Technical Specification 6.6.c(3) Re Deviation from Technical Specification 3.1 0.d ML24081A1332024-04-0202 April 2024 University of Missouri-Columbia (MURR) – Change of Facility Project Manager ML24044A1162024-03-0101 March 2024 Examination Confirmation Letter No. 50-186/OL-24-02, University of Missouri-Columbia ML24064A1922024-03-0101 March 2024 Federal Funding for the Conversion of the University of Missouri-Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel ML24059A4412024-02-28028 February 2024 Univ. of Missouri - Columbia - Submittal of Annual Operating Report Technical Specification 6.6.e IR 05000186/20232022023-12-12012 December 2023 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023202 ML23198A0222023-08-29029 August 2023 Examination Report Letter No. 50-186/OL-23-02, University of Missouri - Columbia ML23198A0232023-08-29029 August 2023 Examination Result Letter No. 50-186/OL-23-02, University of Missouri-Columbia ML23221A1172023-08-0303 August 2023 Written Communication as Specified by 10 CFR 50.4(b)(4) Regarding the Submittal of the Physical Security Plan for the University of Missouri Research Reactor as a Part of the Process to Renew Amended Facility Operating License R-103 ML23213A0592023-08-0101 August 2023 Written Communication as Specified by University of Missouri Research Reactor Technical Specification 6.6.2(d) Regarding a Permanent Change in the Facility Organization Involving the Executive Director ML23186A2132023-07-31031 July 2023 Examination Confirmation Letter No. 50-186/OL-23-03, University of Missouri - Columbia IR 05000186/20232012023-07-31031 July 2023 The Curators of the University of Missouri – U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023201 05000186/LER-2023-003, University of Missouri - Columbia Research Reactor, Written Communication as Required Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.b2023-06-0606 June 2023 University of Missouri - Columbia Research Reactor, Written Communication as Required Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.b ML23124A0422023-05-0808 May 2023 Examination Confirmation Letter 50-186/OL-23-02, University of Missouri - Columbia ML23103A0742023-04-10010 April 2023 University of Missouri, Columbia Research Reactor, Shipment of Radioactive Material Shipment Identifier MURR 23-01 Highway Route Controlled Quantity ML23024A2772023-04-0707 April 2023 Cover Letter for the Security Inspection Report for the University of Missouri (Public) - October 2022 ML23087A1132023-03-29029 March 2023 Examination Report No. 50-186/OL-23-01, University of Missouri-Columbia ML23089A3162023-03-29029 March 2023 Letter Notifying Univ. of Missouri That Us Dept. of Energy Funding Will Not Be Available in Fiscal Year 2023 to Complete the Conversion of MURR to LEU Fuel ML23087A1142023-03-29029 March 2023 Examination Results Letter No. 50-186/OL-23-01, University of Missouri - Columbia ML23055B1372023-02-24024 February 2023 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e IR 05000186/20222022023-02-23023 February 2023 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2022202 - Cover Letter and Enclosure ML23031A0132023-02-14014 February 2023 Examination Confirmation Letter No. 50-186/OL-23-01, University of Missouri-Columbia ML23017A2072023-01-13013 January 2023 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 6.1.f ML22349A0422022-12-0808 December 2022 Written Communication as Specified in 10 CFR 50.54(b)(5) Regarding Changes to the University of Missouri-Columbia Research Reactor Facility Emergency Plan Without Prior Commission Approval Pursuant to 10 CFR 50.54(q)(3) ML22314A2102022-11-0909 November 2022 Written Communication as Required by Technical Specification 6.6.d(2), Other Reports, Regarding a Change in University of Missouri-Columbia Research Reactor Organization Involving the Reactor Facility Director ML22304A0042022-10-27027 October 2022 University of Missouri - Columbia, Shipment of Radioactive Material, Highway Route Controlled Quantity ML22291A0322022-10-14014 October 2022 University of Missouri Written Communication as Required by 10 CFR 73, Appendix G Regarding a Deviation from the MURR Physical Security Plan ML22290A0042022-10-12012 October 2022 University of Missouri-Columbia Research Reactor, Reportable Event Report Pursuant to 20.2201(a)(ii) Regarding Loss of Licensed Material During Shipment IR 05000186/20222012022-06-14014 June 2022 The Curators of the University of Missouri - U.S. NRC Routine Inspection Report No. 05000186/2022201 ML22158A0792022-06-0606 June 2022 Submittal of Revised Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22097A0592022-04-0707 April 2022 Approval for Spent Nuclear Fuel Highway Route Application - NRC Route No. 182D - Docket Number 050-0186 ML22088A0782022-03-25025 March 2022 Univ. of Missouri, Federal Funding for the Conversion of the Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel IR 05000186/20212032022-03-0202 March 2022 The Curators of the University of Missouri U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2021203 ML22056A5162022-02-25025 February 2022 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22038A6012022-02-0808 February 2022 Acceptance for Spent Nuclear Fuel Highway Route Application NRC No. 182D-Docket No. 050-0186 ML22013B1412022-01-21021 January 2022 Examination Confirmation Letter No. 50-186-OL-22-02, University of Missouri-Columbia 05000186/LER-2021-004, University of Missouri Research Reactor, Deviation from Technical Specification 3.2.g.102021-11-23023 November 2021 University of Missouri Research Reactor, Deviation from Technical Specification 3.2.g.10 ML21327A3042021-11-23023 November 2021 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.f.6 ML21298A1972021-10-25025 October 2021 University of Missouri-Columbia Research Reactor - Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.g.6 ML21253A2482021-09-23023 September 2021 Examination Confirmation Letter No. 50-186/OL-22-01, University of Missouri Columbia ML21221A3252021-08-0909 August 2021 University of Missouri-Columbia Research Reactor, Written Communication as Required by Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specifications 3.2.a ML21217A2982021-08-0505 August 2021 University of Missouri-Columbia Research Reactor - Reportable Event Report Pursuant to 20.2203(a)(2)(iv) ML21215A4982021-07-0707 July 2021 Univ of Missouri, Submittal of Revised Road Transportation Security Plan for the Shipment of Irradiated Reactor Fuel 2024-08-27
[Table view] |
Text
July 21, 2015 Mr. Ralph Butler, Director Research Reactor Center University of Missouri-Columbia Research Park Columbia, MO 65211
SUBJECT:
UNIVERSITY OF MISSOURI AT COLUMBIA - ACKNOWLEDGEMENT OF AN ADMINISTRATIVE LIMIT FOR THE QUANTITY OF IODINE PROCESSED IN THE IODINE PROCESSING LABORATORY HOT CELLS FOR FACILITY OPERATING LICENSE NO. R-103 FOR THE UNIVERSITY OF MISSOURI AT COLUMBIA RESEARCH REACTOR (TAC NO. ME1580)
Dear Mr. Butler:
As part of the license renewal process for the University of Missouri at Columbia, Research Reactor (MURR), the U.S. Nuclear Regulatory Commission (NRC) staff reviewed your response to our request for additional information dated January 28, 2015, describing the I-131 Processing Laboratory, Attachment No. 25 (although portions of this system are considered proprietary, a public version, where proprietary information has been redacted, is available on the Agencywide Documents Access and Management System (ADAMS) Accession No. ML15034A474). NRC Headquarters inspectors reviewed the I-131 Processing Laboratory during a routine inspection conducted from March 30 through April 2, 2015, and documented their findings in NRC Inspection Report No. 50-186/2015-201 (ADAMS Accession No. ML15120A338). An Unresolved Item No. 50-186/2015-201-01 was issued to provide for additional NRC staff review. NRC Research and Test Reactor Licensing branch staff visited the facility on May 12-13, 2015, as part of their review of the renewal of the MURR facility operating license, and also reviewed the I-131 Processing Laboratory.
Following these additional reviews, the NRC staff conducted a telephone conversation on May 28, 2015, between MURR staff: Mr. Les Foyto, and Mr. John Fruits, and NRC staff:
Dr. Mirela Gavrilas, Mr. Alexander Adams, Jr., Dr. Kevin Hsueh, Mr. John Adams, Mr. Johnny Eades, and Mr. Geoffrey Wertz. During this telephone call, the NRC staff communicated that it appears that additional safety review is necessary in order to determine if any engineered safety features, automated control systems, or additional technical specifications should be required during the operation of the I-131 Processing Laboratory to ensure that any accident scenario could not result in a dose consequence greater than the limits provided in Title 10 of the Code of Federal Regulations (10 CFR), Part 20, Standards for Protection Against Radiation. As a result, MURR staff decided to limit the iodine production in the hot cells to less than allowed by current MURR technical specification 3.7 and 10 CFR Part 20, Appendix B. Confirmation of this understanding was provided by an email from Mr. Les Foyto to Mr. Geoffrey Wertz (ADAMS Accession No. ML15154B803), dated May 28, 2015.
Please notify me immediately if your understanding differs from what is set forth above or if for any reason you intend to change, deviate from or not complete any of the actions set forth above, and advise me of the changes or deviations.
R. Butler Be advised this letter does not preclude issuance of an order formalizing the above commitments or requiring other actions on the part of the licensee, nor does it preclude the NRC from taking enforcement action for violations of NRC requirements that may have prompted the issuance of this letter.
In accordance with 10 CFR, Section 2.390, "Public inspections, exemptions, requests for withholding," a copy of this letter, and your response, if you choose to provide one, will be made available electronically for public inspection in the NRC Public Document Room and in ADAMS, accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the public without redaction. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a redacted copy of your response that deletes such information. If you request withholding of such material, you must specifically identify the portions of your response that you seek to have withheld, and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request for withholding confidential commercial or financial information).
If you have any questions regarding this review, please contact Mr. Geoffrey Wertz at (301) 415-0893, or by e-mail at Geoffrey.Wertz@nrc.gov.
Sincerely,
/RA/
Mirela Gavrilas, Deputy Director Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-186 cc: See next page
University of Missouri-Columbia Docket No. 50-186 cc:
Mr. Les Foyto, Associate Director Reactor and Facilities Operations Research Reactor Center University of Missouri - Columbia Research Park Columbia, MO 65211 Homeland Security Coordinator Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102 Planner, Dept. of Health and Senior Services Section for Environmental Public Health 930 Wildwood Drive, P.O. Box 570 Jefferson City, MO 65102-0570 Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101 A-95 Coordinator Division of Planning Office of Administration P.O. Box 809, State Capitol Building Jefferson City, MO 65101 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
(Pkg.) ML15154B830; (Letter) ML15154B812; (E-mail) ML15154B803;
- concurred via email NRR-088 OFFICE DPR/PRLB/PM* DPR/LA DPR/PRLB/BC DPR/PRLB/PM NRR (DHardesty for) (AAdams for)
NAME GWertz ELee/NParker MGavrilas AAdams GWertz DATE 06/08/2015 06/04/2015 06/11/2015 06/12/2015 07/21/2015